5 floors · 78,595 sq ft · built 2007 · class W1 · owner of record: Nyc Educational Construction Fund
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 8 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 47 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 47 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 78,595 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 168 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 168 days | Annual filing |
| Energy audit and retro-commissioning (2034) Likely applies Local Law 87 · Calendar year 2034 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 1554). Agency page | Dec 31, 2034 in 2969 days | Next due 2034 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Feb 24, 2026 | Construction CLASS - 2 RE-ISSUE #35692517K. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: AT 3RD FLOOR GYM, CMU WALLS HAVE STEP CRACKS AT VARIOUS LOCATIONS WITH BROKEN BLOCKS IN PLACE. AT STAIR "A" BETWEEN LOCATIONS W #35728877X | Mar 10, 2026 POP/IN-VIO | $0 |
| Mar 28, 2025 | Construction CLASS - 2 REISSUE #35678778H DATE OF ISSUE: 04-11-2024. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER AT THE TIME OF INSPECTION OBSERVED AND NOTED AT 3RD FLOOR GYM. CMU WALLS HAVE STEP CRACKS AT VARIOUS LOCATIONS #35692517K | May 1, 2025 POP/IN-VIO | $0 |
| Apr 11, 2024 | Construction CLASS - 2 REISSUE#35672356K FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:OBSERVED AT 3 FLR-GYM,CMU WALLS HAVE STEP CRACKS AT VARIOUS LOCATIONS WITH BROKEN BLOCKS IN PLACE.AT STAIR A BETWEEN 2 FLR & 3 FLR,S #35678778H | Nov 21, 2024 POP/IN-VIO | $0 |
| Mar 28, 2023 | Construction CLASS - 2 REISSUE#35650631Z FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.AT TIME OF INSPECTION I OBSERVED AT GYM CMU WALL HAVE A STEP CRACKS ALSO OBSERVED CRACKS IN STAIRWELL AREA VIOLATION#35650631Z ISSUED 03/2 #35672356K | Aug 24, 2023 POP/IN-VIO | $0 |
| Mar 28, 2022 | Construction CLASS - 2 REISSUE#35548292M.DATE:2/17/2021.FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.AT THE TIME OF INSPECTION I OBSERVED AND NOTED HORIZONTAL AND STEP CRACKS IN GYM,CMU WALLS ALSO OBSERVED CRACKS IN STAIRWEL #35650631Z | Jul 14, 2022 POP/IN-VIO | $0 |
| Feb 17, 2021 | Construction CLASS - 2 REISSUE #35442189Z FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER NOTED OBSERVED HORIXONTAL AND SEP CRACKS IN GYM CMU WALLS ALSO OBSERVED CRACKS IN STAIRWELLS AT STAIR "A" BETWEN 2ND AND 3RD FLOOR STAIR #35548292M | May 20, 2021 POP/IN-VIO | $0 |
| Mar 19, 2019 | Construction CLASS - 2 RE-ISSUE#35316890J FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED:@THE THIRD FLOOR GYM EXIT NEAR EXIT (4) VERICAL AND HORIZONTAL CRACKS WERE OBSERVED ON THE WALL.REM:REPAIR AND/OR REPLACE. #35384046Z | Jun 13, 2019 POP/IN-VIO | $0 |
| Feb 6, 2018 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER AT 3 FLOOR GYM NEAR EXIT (4) VERTICAL AND HORIZONATAL CRACKS IN CMU WALL TOTAL LINEAR FEET APPROX. (TEN LF)REMEDY: REPAIR /REPLACE #35316890J | May 3, 2018 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Dec 20, 2008 | CONSTRUCTION #MOST0010IB | VIOLATION WORK WITHOUT PERMIT - ACTIVE |
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #01423 | DOB VIOLATION - ACTIVE |
| Apr 15, 1992 | CONSTRUCTION #B4MCC02 | VIOLATION UNSERVED ECB-ACTIVE |
None open.
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 13, 2026, 7:10 PM ET. BBL 1015540032.