4 floors · 169,320 sq ft · built 1937 · class W1 · owner of record: Nyc Department Of Education
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 63 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (3 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-12-16 (Accepted). Agency page | Dec 31, 2026 in 63 days | 3 of 3 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 169,320 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 184 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 184 days | Annual filing |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 2 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1159 days | Next cycle year 2029 |
| Energy audit and retro-commissioning (2034) Likely applies Local Law 87 · Calendar year 2034 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 1184). Agency page | Dec 31, 2034 in 2985 days | Next due 2034 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 10, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.LACK OF EMERGENCY LIGHTING FOR EXITS,EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1;27-542.NOTED:AT 3RD FL LIBRARY RM 303 NOT INSTALLED/PROVIDED WITHOUT #35734771Z | Aug 5, 2026 POP/IN-VIO | $0 |
| Jul 10, 2026 | Construction CLASS - 2 REISSUE ECB #35725379J. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANTMANNER. NOTED: AT (3RD FL)HALLWAY SMOKE DOORS NEAR RM 328, STAIR 1 (2ND)HALLWAY SMOKE DOORS NEAR RM 231, STAIR H, F, (1ST FL)CAFETERIA, STAI #35734767X | Aug 5, 2026 POP/IN-VIO | $0 |
| Jul 10, 2026 | Construction CLASS - 2 REISSUE ECB #35725378H. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANTMANNER. ILLUMINATION FOR EXITS, EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1; 27-381. NOTED: AT (1ST FL)CAFETERIA EMERGENCY LIGHTS NOT #35734768H | Aug 5, 2026 POP/IN-VIO | $0 |
| Jul 10, 2026 | Construction CLASS - 2 REISSUE ECB#35725375M FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:AT ROOF PARAPET NOT INSTALLED/PROVIDED WITHOUT 42"HEIGHT REQUIRED THROUGHOUT VARIOUS AREAS.REM:REPAIR AND/OR REPLACE. #35734770R | Aug 5, 2026 POP/IN-VIO | $0 |
| Sep 10, 2025 | Construction CLASS - 2 REPAIR #35682726H DATE OF ISSUE: 06-11-2024. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. AT THE TIME OF INSPECTION OBSERVED AND NOTED AT 4TH FLOOR ROOM #417 BULKHEAD DOOR AT STAIR B, AT 3RD FL. CORRI #35725379J | Oct 3, 2025 POP/IN-VIO | $0 |
| Sep 10, 2025 | Construction CLASS - 2 REISSUE #35682727J DATE OF ISSUE: 06-11-2024. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. ILLUMINATION FOR EXITS, EXIT DISCHARGESAND PUBLIC CORRIDORS PER BC 1006.1; 27-381. AT THE TIME OF INSPECTION #35725378H | Oct 3, 2025 POP/IN-VIO | $0 |
| Sep 10, 2025 | Construction CLASS - 2 REISSUE#35682730K DATE OF ISSUE:06.11.2024 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.AT THE TIME OF INSPECTION OBSERVED AND NOTED AT ROOF LEVEL PARAPET IS NOT 42"HIGH AS REQUIRED FACING SCHOOLYARD.R #35725375M | Oct 9, 2025 POP/IN-VIO | $0 |
| Jun 11, 2024 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER:ILLUMINATION FOREXITS,EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1;27-381.AT 3 FLOOR STAIR C BY RM 307 AND 2 FL STAIR H BY 209A EMERGENCY LIGHTSARE NO #35682727J | Aug 20, 2024 POP/IN-VIO | $0 |
| Jun 11, 2024 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.AT 4 FLOOR 417,BULKHEAD DOORS STAIR B,3 FL CORRIDOR BY 331,2 FL,207A CORRIDOR BY 228, 1 FL LUNCHROOM ENTRY BY 117,CORRIDOR BY 102A AND KITCHEN ENTRY ARE NOT #35682726H | Aug 20, 2024 POP/IN-VIO | $0 |
| Jun 11, 2024 | Construction CLASS - 2 REISSUE#35674888K FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.AT ROOF LEVEL,PARAPET IS NOT 42" HIGH AS REQUIRED FACING SCHOOL YARDREM:REPAIR AND/OR REPLACE. #35682730K | Aug 20, 2024 POP/IN-VIO | $0 |
| May 9, 2023 | Construction CLASS - 2 REISSUE#35655202N FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:ROOF LEVEL,PARAPET IS NOT 42"HIGH AS REQUIRED FACING SCHOOLYARD.REM:PROVIDE PARAPET AS REQUIRED. #35674888K | Aug 1, 2023 POP/IN-VIO | $0 |
| May 20, 2022 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: OBSERVEDDURING INSPECTION OF ROOF LEVEL PARAPET WALLS FACING SCHOOL YARD ARE NOT AT REQUIRED HEIGHT. REMEDY: REPAIR AND/OR REPLACE #35655202N | Sep 6, 2022 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Aug 29, 1995 | LOCAL LAW 62/91 - BOILERS #44658 | DOB VIOLATION - ACTIVE |
| Jun 7, 1994 | LOCAL LAW 62/91 - BOILERS #05306 | DOB VIOLATION - ACTIVE |
| Jun 28, 1993 | LOCAL LAW 62/91 - BOILERS #14186 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Sep 18, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle B (premises is in Community District 2) | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Jul 10, 2026 | ECB | Construction: FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.LACK OF EMERGENCY LIGHTING FOR EXITS,EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1;27-542.NOTED:AT 3RD FL LIBRARY RM 303 NOT INSTALLED/PROVIDED WITHOUT | Open |
| Jul 10, 2026 | ECB | Construction: REISSUE ECB#35725376Y FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED:AT BASEMENT ELECTRIC METER RM FOUNDATION WALLS WATER POROUS/PENETRATION/DAMAGE THROUGHOUT VARIOUS AREAS.REM:REPAIR AND/OR REPLAC | Closed |
| Jul 10, 2026 | ECB | Construction: REISSUE ECB #35725379J. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANTMANNER. NOTED: AT (3RD FL)HALLWAY SMOKE DOORS NEAR RM 328, STAIR 1 (2ND)HALLWAY SMOKE DOORS NEAR RM 231, STAIR H, F, (1ST FL)CAFETERIA, STAI | Open |
| Jul 10, 2026 | ECB | Construction: REISSUE ECB #35725378H. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANTMANNER. ILLUMINATION FOR EXITS, EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1; 27-381. NOTED: AT (1ST FL)CAFETERIA EMERGENCY LIGHTS NOT | Open |
| Jul 10, 2026 | ECB | Construction: REISSUE ECB#35725375M FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:AT ROOF PARAPET NOT INSTALLED/PROVIDED WITHOUT 42"HEIGHT REQUIRED THROUGHOUT VARIOUS AREAS.REM:REPAIR AND/OR REPLACE. | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 29, 2026, 8:36 AM ET. BBL 4011840014.