1 floors · 14,227 sq ft · built 1972 · class F4 · owner of record: Boerum Johnson Ave Assoc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 68 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2020-09-15 (Accepted). Agency page | Dec 31, 2026 in 68 days | 2 of 2 without an accepted 2026 report yet |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 1 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 799 days | Next cycle year 2028 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jan 3, 2023 | Plumbing CLASS - 1 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLAINT MANNER: LACK OF A SYSTEM OF AUTOMATIC SPRINKLERS WHERE REQUIRE PER BC 903.2; 27-954 I OBSERVED ON THE GROUND FLOOR IN THE NORTH WEST SIDE OF THE WAREHOUSE BEING US #39076822N | Jul 10, 2023 IN VIOLATION | $0 |
| Jan 3, 2023 | Construction CLASS - 1 FAILURE TO MAINTAIN BUILDING IN CODE COMPLAINT MANNER I OBSERVED IN THE CELLAR HAVING BACK PITCHED WASTE LINE OPEN WASTE LINE USING FENCO COUPLING ON WASTE LINE. FIRST FLOOR SPRINKLER HEAD COVERED IN PAINT AND #39076821L | Mar 15, 2023 IN VIOLATION | $0 |
| Dec 8, 2004 | Boilers Hazardous BQ9 36 32A 11A 50A 50B 1992 FULTON NATL BD 65953 50A PIPE DOWN SAFETY VALVE DISCHARGE TO A SAFE POINT 50B PIPE DOWN GLASS DRAIN VALVE TO A SAFE POINT. #32046698N | Aug 28, 2006 IN VIOLATION | $0 |
| Dec 8, 2004 | Boilers Non-Hazardous BQ9/48B 36 11A 50A 50B 1986 FULTON NATL BD 49590 50A PIPE DOWN SAFETY VALVE DISCHARGE TO A SAFE POINT. 50B PIPE DOWN GLASS DRAIN VALVE TO A SAFE POINT. #32046699P | Aug 28, 2006 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION #00006 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #03519 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #03518 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #03517 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #02393 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #02392 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #02391 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION #01152 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION #01224 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION #00011 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION #00012 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION #00013 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION #01225 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION #01226 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION #02472 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION #03612 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION #04603 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION #04696 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00538 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00536 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00537 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION #01689 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION #01688 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION #01687 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION #00613 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION #00591 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION #00590 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION #00592 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #21599 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 1) | Active |
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 1) | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-INT-HP Violation Issued-Failure To File 2020 Internal Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-INT-HP Violation Issued-Failure To File 2020 Internal Inspection Affirmation of Correction for HP Device | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 24, 2026, 10:23 AM ET. BBL 3030740001.