3 floors · 75 apartments · 135,845 sq ft · built 2005 · class RM · owner of record: Unavailable Owner
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 45 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 45 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 61 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 135,845 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 166 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 166 days | Annual filing |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 289 days | Registered through 2027-09-01 |
| Gas piping inspection (2027 cycle) Likely applies Local Law 152 · During 2027 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 15 is on the 2027 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2027 in 410 days | Next cycle year 2027 |
| Energy audit and retro-commissioning (2035) Likely applies Local Law 87 · Calendar year 2035 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 8815). Agency page | Dec 31, 2035 in 3332 days | Next due 2035 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Aug 12, 2010 | Construction CLASS - 2 (MISC)27-338(J)/BC1509.9COMBUSTIBLE ROOF DECK/TERRACE EXCEEDS 20% OF ROOF AREA.@ TIME OF INSPECTION I DID OBSERVE @ ROOF TOP LEVEL A COMBUSTIBLE DECK COVERING MORE THAN 20% OF ROOF AREA.REM:REDUCE COMBUSTIBLE R #34845932X | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 (MISC)27-338(J)/BC1509.9COMBUSTIBLE ROOF DECK/TERRACE EXCEEDS 20% OF ROOF AREA.@ TIME OF INSPECTION I DID OBSERVED @ ROOF TOP LEVEL A COMBUSTIBLE DECK COVERING MORE THAN 20%OF ROOF AREA.REM:REMOVE COMBUSTIBLE R #34845926J | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 (MISC)27-338(J)/BC1509.9COMBUSTIBLE ROOF DECK/TERRACE EXCEEDS 20% OF ROOF AREA.@ TIME OF INSPECTION I DID OBSERVE @ ROOF LEVEL A COMBUSTIBLEDECK COVERING MORE THAN 20% OF ROOF AREA.REM:REDUCE COMBUSTIBLE ROOF D #34845927L | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 (MISC)27-338(J)/BC1509.9COMBSUTIBLE ROOF DECK/TERRACE EXCEEDS 20% OF ROOF AREA.@ TIME OF INSPECTION I DID OBSERVE @ ROOF LEVEL A COMBUSTIBLEDECK COVERING MORE THAN 20% OF ROOF AREA.REM:REDUCE COMBUSTIBLE ROOF D #34845931Y | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 (MISC)27-338(T)/BC1509.9COMBUSTIBLE ROOF DECK/TERRACE EXCEEDS 20%OF ROOF AREA.@ TIME OF INSPECTION I DID OBSERVE @ ROOF TOP LEVEL A COMBUSTIBLE DECK COVERING MORE THAN 20% OF ROOF AREA.REM:REDUCE COMBUSTIBLE RO #34845934J | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 1 STOP ALL WORK.WORK W/O PERMIT.@ TIME OF INSPECTION I DID OBSERVE @ ROOF TOP LEVEL A COMBUSTIBLE DECK BEING BUILT W/O A PERMIT.REM:STOP ALL WORK.OBTAIN PERMIT OR RESTORE PREMISES TO PRIOR LEGAL CONDITION #34845269Z | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 (MISC)27-338(J)/BC1509.9COMBUSTIBLE DECK/TERRACE EXCCEEDS 20% OF ROOF AREA @ TIME OF INSPECTION I DID OBSERVE COMBUSTIBLE DECKING COVERING MORE THAN 20% OF ROOF.REM:REDUCE COMBUSTIBLE ROOF DECK TO MAX OF 20% OF #34845270X | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 WORK W/O A PERMIT.@ TIME OF INSPECTION I DID OBSERVE @ ROOF LEVEL A DECK INSTALLED W/O A PERMIT.REM:OBTAIN PERMIT OR RESTORE PREMISES TO PRIOR LEGAL CONDITION #34845271H | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 (MISC)27.338(J)/BC1509.9COMBUSTIBLE ROOF DECK/TERRACE EXCCEDS 20% OF ROOF AREA.@ TIME OF INSPECTION I DID OBSERVE @ ROOF TOP LEVEL A COMBUSTIBLE DECK COVERING MORE THAN 20% OF ROOF AREA.REM:REDUCE COMBUSTIBLE R #34845273L | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 WORK W/O PERMIT @ TIME OF INSPECTION I DID OBSERVE @ ROOF LEVEL A DECKINSTALLED W/O PERMIT.REM:OBTAIN PERMIT OR RESTORE PREMISES TO PRIOR LEGAL CONDITION #34845935L | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 (MISC)27-338(J)/BC1509.9COMBUSTIBLE ROOF DECK/TERRAIN EXCEEDS 20% OF ROOF AREA.@ TIME OF INSPECTION I DID OBSERVE @ ROOF TOP LEVEL A COMBUSTIBLE DECK COVERING MORE THAN 20% OF ROOF AREA.REM:REDUCE COMBUSTIBLE #34845936N | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 WORK W/O PERMIT.@ TIME OF INSPECTION I DID OBSERVE @ ROOF TOP LEVEL A DECK INSTALLED W/O A PERMIT.REM:OBTAIN A PERMIT OR RESTORE PREMISES TOPRIOR LEGAL CONDITION #34845937P | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 WORK W/O PERMIT.@ TIME OF INSPECTION I DID OBSERVE @ ROOF TOP LEVEL A DECK INSTALLED W/O A PERMIT.REM:OBTAIN PERMIT OR RESTORE PREMISES TO PRIOR LEGAL CONDITION #34845938R | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 (MISC)27.338(J)/BC1509.9COMBUSTIBLE ROOF DECK/TERRACE EXCEEDS 20%OF ROOF AREA.@ TIME OF INSPECTION I DID OBSERVE @ ROOF LEVEL A COMBUSTIBLEDECK COVERING MORE THAN 20% OF ROOF AREA.REM:REDUCE COMBUSTIBLE ROOF D #34845940X | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 WORK W/O PERMIT.@ TIME OF INSPECTION I DID OBSERVE @ ROOF TOP LEVEL A DECK INSTALLED W/O A PERMIT.REM:OBTAIN PERMIT OR RESTORE PREMISES TO PRIOR LEGAL CONDITION #34845941H | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 (MISC)27-338(D)(4)/BC2405.3SKYLIGHTS SHALL BE PROTECTED ON THEIR UNDDERSIDE BY NON-COMBUSTIBLE SCREENS & SHARL BE ABLE TO SUPPORT A LOAD OF THREE HANDRAIL 1IBS OVER ANY 1'X2'AREA,GUARDRAIL ARE ACCEPTABLE @ TIME #34845942J | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 SEC. 27-338(J);1509.9. COMBUSTIBLE ROOF DECK/TERRACE EXCEEDS 20% OF ROOF AREA. AT TIME OF INSPECTION I DID OBSERVE AT ROOF LEVEL A COMBUSTIBLE DECK COVERING MORE THAN 20% OF ROOF AREA. REMEDY: REDUCE #34845272J | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 (MISC)27-338(J)/BC1509.9COMBUSTIBLE ROOF DECK/TERRACE EXCEEDS 20% OF ROOF AREA.@ TIME OF INSPECTION I DID OBSERVE @ ROOF TOP LEVEL A COMBUSTIBLE DECK COVERING MORE THAN 20% OF ROOF AREA.REM:REMOVE COMBUSTIBLE R #34845939Z | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 WORK W/O A PERMIT.@ TIME OF INSPECTION I DID OBSERVE ROOF TOP LEVEL A DECK INSTALLED W/O A PERMIT.REM:OBTAIN PERMIT OR RESTORE PREMISES TO PRIOR LEGAL CONDITION #34845274N | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 WORK W/O A PERMIT @ TIME OF INSPECTION I DID OBSERVE @ ROOF LEVEL A DECK INSTALLED W/O A PERMIT.REM:OBTAIN PERMIT OR RETORE PREMISES TO PRIOR LEGAL CONDITION #34845925H | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 WORK W/O A PERMIT.@ TIME OF INSPECTION I DID OBSERVE @ ROOF TOP LEVEL A DECK INSTALLED W/O A PERMIT.REM:OBTAIN PERMIT OR RESTORE PREMISES TO PRIOR LEGAL CONDITION #34845929P | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 WORK W/O PERMIT.@ TIME OF INSPECTION I DID OBSERVE @ ROOF LEVEL A DECKINSTALLED W/O A PERMIT.REM:OBTAIN PERMIT OR RESTORE PREMISES TO PRIOR LEGAL CONDITION #34845930M | Jun 2, 2011 WRITTEN OFF | $0 |
| Aug 12, 2010 | Construction CLASS - 2 WORK W/O A PERMIT.@ TIME OF INSPECTION I DID OBSERVE @ ROOF TOP LEVEL A DECK INSTALLED W/O PERMIT.REM:OBTAIN PERMIT OR RESTORE PREMISES TO PRIOR LEGAL CONDITION #34845933H | Jun 2, 2011 WRITTEN OFF | $0 |
| Issued | Violation | Status |
|---|---|---|
| May 2, 2017 | FAILURE TO BENCHMARK FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 #00857 | DOB VIOLATION - ACTIVE |
| May 3, 2012 | FAILURE TO BENCHMARK FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 #02503 | DOB VIOLATION - ACTIVE |
| Jan 1, 2012 | FAILURE TO BENCHMARK FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 #02273 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| May 2, 2017 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| May 3, 2012 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| Jan 1, 2012 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Sep 8, 2017 | B | Apt 1 · § 27-2005 HMC:TRACE AND REPAIR THE SOURCE AND ABATE THE NUISANCE CONSISTING OF MOLD ... LOWER LEVEL (STORAGE AREA) IN THE 1st ROOM FROM NORTH AT WEST LOCATED AT APT 1, 1st STORY, 1st APARTMENT FROM WEST AT NORTH | Oct 13, 2017 |
| Aug 15, 2017 | B | Apt 1 · § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK OVER CEILING IN BASEMENT IN THE 1st ROOM FROM NORTH LOCATED AT APT 1 LOWER LEVEL | Sep 19, 2017 |
| Aug 15, 2017 | B | Apt 1 · § 27-2005 ADMIN. CODE: REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN UNIFORM COLOR CEILING IN THE 1st ROOM FROM NORTH LOCATED AT APT 1 LOWER LEVEL | Sep 19, 2017 |
| Aug 15, 2017 | B | Apt 1 · § 27-2010,2011,2012 ADMIN. CODE: CLEANSE AND DISINFECT TO THE SATISFACTION OF THIS DEPARTMENT AFTER REMOVING THE WATER FROM FLOOR IN METER ROOM BASEMENT LOCATED AT APT 1 LOWER LEVEL, 1st STORY | Sep 19, 2017 |
| Apr 2, 2015 | B | Apt UPPER · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR CEILING IN THE PRIVATE HALLWAY LOCATED AT APT UPPER LOWER LEVEL, 1st STORY, 1st APARTMENT FROM WEST AT NORTH | May 7, 2015 |
| Apr 2, 2015 | B | Apt UPPER · § 27-2005 ADM CODE REPAIR THE ROOF SO THAT IT WILL NOT LEAK AT CEILING IN THE ENTIRE APARTMENT LOCATED AT APT UPPER, 1st APARTMENT FROM WEST AT NORTH | May 7, 2015 |
| Apr 2, 2015 | B | Apt UPPER · § 27-2005, 2007 ADM CODE ARRANGE AND MAKE SELF-CLOSING THE DOORS AT THE ENTRANCE TO APARTMENT LOCATED AT APT UPPER LOWER LEVEL, 1st STORY, 1st APARTMENT FROM WEST AT NORTH | May 7, 2015 |
| Apr 2, 2015 | B | Apt UPPER · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR ALL WALLS AND CEILING IN THE 1st BATHROOM FROM EAST LOCATED AT APT UPPER UPPER LEVEL, 1st STORY, 1st APARTMENT FROM WEST AT NORTH | May 7, 2015 |
| Apr 2, 2015 | B | Apt UPPER · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR ALL WALLS AND CEILING IN THE 2nd BATHROOM FROM EAST LOCATED AT APT UPPER UPPER LEVEL, 1st STORY, 1st APARTMENT FROM WEST AT NORTH | May 7, 2015 |
| Apr 2, 2015 | B | Apt UPPER · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR CEILING IN THE PRIVATE HALLWAY LOCATED AT APT UPPER UPPER LEVEL, 1st STORY, 1st APARTMENT FROM WEST AT NORTH | May 7, 2015 |