10 floors · 74,365 sq ft · built 2011 · class O6 · owner of record: Newtown Property Holdings, Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 46 days | Keep the report on file (not filed with DOB) |
| Facade inspection report (Cycle 10A) Applies Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $388,000 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2027 in 98 days | No Cycle 10 report on record yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 74,365 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 167 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 167 days | Annual filing |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 1 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 777 days | Next cycle year 2028 |
| Energy audit and retro-commissioning (2029) Likely applies Local Law 87 · Calendar year 2029 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 619). Agency page | Dec 31, 2029 in 1142 days | Next due 2029 |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-06-16 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 6, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPARTMENT OF BUILDINGS. OBSERVED RESPONDENT HAS FAILED TO COMPLY AND FILE A CERTIFICATE OF CORRECTION WITH THE DOB F #39194891Y | Sep 15, 2026 DEFAULT | $6,250 |
| Feb 17, 2026 | Construction CLASS - 2 WORK WITHOUT A PERMIT. NOTE: OBSERVED HEAVY DUTY CANOPY/SHED APPROX. 25 FT X 40 FT SUPPORTED BY STEEL POSTS HAS BEEN ERECTED AT REAR OF THIS LOCATION WITHOUT A PERMIT OR DOB APPROVAL., OBTAIN ALL PERMITS #39177429J | Apr 28, 2026 DEFAULT | $6,250 |
| Dec 9, 2022 | Local Law CLASS - 2 FAILURE TO SUBMIT ACCEPTABLE REQUIRED CYCLE 8A & 9A REPORT OF CRITICALEXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL & APPURTENANCES RE QUIRED BY 28-302.4 FOR CONTROL #918395.REMEDY:SUBMIT ACCEPTABLE REQUIR #37025213P | Mar 21, 2023 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Feb 22, 2022 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022 #02339 | DOB VIOLATION - ACTIVE |
| Sep 6, 2019 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST #07951 | DOB VIOLATION - ACTIVE |
| Sep 6, 2019 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST #07952 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 29, 2026 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2025 Cat1 Test Affirmation of Correction | Active |
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 1) | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Feb 22, 2022 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022 | Active |
| Sep 6, 2019 | Elevators ACC1 | Active |
| Sep 6, 2019 | Elevators ACC1 | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Affirmation of Correction | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 15, 2026, 9:15 PM ET. BBL 4006190014.