2 floors · 5 apartments · 3,128 sq ft · built 1931 · class C2 · owner of record: 3069 Barker Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | Registration expired 2026-09-01 |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 65 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 65 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 81 days | Annual |
| Gas piping inspection (2027 cycle) Likely applies Local Law 152 · During 2027 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 12 is on the 2027 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2027 in 430 days | Next cycle year 2027 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Sep 25, 2026 | Site Safety CLASS - 1 AT THE TIME OF INSPECTION OF ON-GOING CONSTRUCTION OF 13 STORY BUILDING IN FOUNDATION PHASE REBAR INSTALLATION, OBSERVED EXCAVATION PARTIALLY COMPLETE AND SUPPORT OF EXCAVATION (SOE) STEEL CASING PILE INSTALLED #39559677M | Dec 4, 2026 PENDING | $2,500 |
| Sep 25, 2026 | Construction CLASS - 1 AT THE TIME OF INSPECTION OF ON-GOING CONSTRUCTION OF 13 STORY BUILDING ON FOUNDATION PHASE INSTALLATION OF REBAR ON PROGRESS, OBSERVED INCOMPLETE EXCAVATION AND SOE AT EXP#1 NO SLOPE OF 1:1 AND SUPPORT OF EXCA #39559676K | Dec 4, 2026 PENDING | $2,500 |
| Sep 25, 2026 | Construction CLASS - 1 DURING THE INSPECTION OF THE CONSTRUCTION OF 13-STORY NB OBSERVED EXCAVATION/ EARTHWORK FOR BUILDING FOUNDATION UPON CHECKING ON DOB INSPECTION, NO EARTHWORK NOTIFICATION WAS RECEIVED. CONTRARY TO CODE BC 3304. #39559678Y | Dec 4, 2026 PENDING | $2,500 |
None open.
None open.
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Mar 11, 2020 | B | Apt BASEME · § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE ... REGLAZE PORCELAIN BATHTUB IN THE BATHROOM LOCATED AT APT BASEME, 1st APARTMENT FROM SOUTH AT WEST | Apr 15, 2020 |
| Date | Source | What | Now |
|---|---|---|---|
| Sep 25, 2026 | ECB | Site Safety: AT THE TIME OF INSPECTION OF ON-GOING CONSTRUCTION OF 13 STORY BUILDING IN FOUNDATION PHASE REBAR INSTALLATION, OBSERVED EXCAVATION PARTIALLY COMPLETE AND SUPPORT OF EXCAVATION (SOE) STEEL CASING PILE INSTALLED | Open |
| Sep 25, 2026 | ECB | Construction: AT THE TIME OF INSPECTION OF ON-GOING CONSTRUCTION OF 13 STORY BUILDING ON FOUNDATION PHASE INSTALLATION OF REBAR ON PROGRESS, OBSERVED INCOMPLETE EXCAVATION AND SOE AT EXP#1 NO SLOPE OF 1:1 AND SUPPORT OF EXCA | Open |
| Sep 25, 2026 | ECB | Construction: DURING THE INSPECTION OF THE CONSTRUCTION OF 13-STORY NB OBSERVED EXCAVATION/ EARTHWORK FOR BUILDING FOUNDATION UPON CHECKING ON DOB INSPECTION, NO EARTHWORK NOTIFICATION WAS RECEIVED. CONTRARY TO CODE BC 3304. | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)