2 floors · 2 apartments · 5,050 sq ft · built 1933 · class S9 · owner of record: Gross, Binem
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 43 days | Keep the report on file (not filed with DOB) |
| Annual property registration Check HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 287 days | Required only if the owner doesn't live there |
| Gas piping inspection (2027 cycle) Likely applies Local Law 152 · During 2027 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 14 is on the 2027 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2027 in 408 days | Next cycle year 2027 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 1, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSION ORDER TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPARTMENT OF BUILDING FOR NOTICE OF VIOLATION # 39114684Z ISSUED ON 05/17/2024 PURSUANT TO 28-204.4. VIOLATING CONDITION #39194546N | May 25, 2027 PENDING | $3,125 |
| Mar 17, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPARTMENT OF BUILDINGS. NO CERTIFICATE OF CORRECTION ON FILE FOR VIO#39118055Y AS OF 3/17/2026., FILE A CERTIFICATE #39180658K | May 25, 2027 DEFAULT | $6,250 |
| Mar 9, 2026 | Construction CLASS - 1 UNLAWFUL ACTS. FAILURE TO COMPLY WITH COMMISSIONER'S ORDER. FOR WORK WITHOUT A PERMIT FOR VIO#39114684Z.NO PERMIT ON FILE AS OF 3/9/2026., COMPLY WITH COMMISSIONER'S ORDER #39179576Z | Jan 11, 2027 PENDING | $2,500 |
| Jun 28, 2024 | Construction CLASS - 1 UNLAWFULLY CONTINUED OF WORK WHILE ON NOTICE OF A STOP WORK ORDER. AT TIME OF INSPECTION, OBSERVED AT EXPOSURE #1 AND 2 (PARKVILLE AVE SECTION AND E. 8 ST. SECTION) EVIDENCE OF WORK CONTRARY TO STOP WORK ORDER #39118055Y | Dec 7, 2026 PENDING | $5,030 |
| May 17, 2024 | Construction CLASS - 1 WORK WITHOUT A PERMIT. OBSERVED AT PREMISES, AN ONGOING INTERIOR RENOVATION, INCLUDING CHANGE IN EGRESS. GOOGLE MAP IN 2012, SHOWS TWO LARGE DOORS AT ALTERNATE ENDS OF EXPOSURE 1 WITHOUT A STANDARD DOOR, NOW, T #39114684Z | Jul 7, 2025 IN VIOLATION | $2,500 |
| Apr 29, 2024 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPARTMENT OF BUILDINGS. AT TIME OF INSPECTION, NO CERTIFICATE OF CORRECTION FILED FOR SUMMONS #39104556P ISSUED ON 0 #39112958H | Apr 29, 2025 IN VIOLATION | $1,250 |
| Jan 29, 2024 | Construction CLASS - 2 WORK WITHOUT PERMIT. AT TIME OF INSPECTION OBSERVED AT THE EXTERIOR OPENINGS CREATED FOR APPROX. 12 WINDOWS BEEN INSTALLED ON 1ST AND 2ND FLOOR AT EXP. 1,3, AND 4. REMOVED ROLL DOWN GATES AT EXP. 4 AND ERECTED #39104556P | Apr 29, 2025 IN VIOLATION | $1,250 |
| Issued | Violation | Status |
|---|---|---|
| Apr 30, 2010 | CONSTRUCTION WORK WITHOUT PERMIT; HAVING ERECTED A NEW CMU WALL APPROX. 50' X 112'H @ REAR OF BLDG #1 EXP #4 REMEDY; STOP ALL WORK MAKE SITE SAFE, CONTACT DOB #1401WG | VIOLATION WORK WITHOUT PERMIT - ACTIVE |
| Apr 30, 2010 | CONSTRUCTION FAILURE TO MAINTAIN BUILDING WALLS OR APPURENTANCES; REMEDY; MAINTAIN BLDG WALLS, ERECT SIDEWALK SHED 2. SUBMIT ENGINEERS REPORT TO REFLECT OVERALL STRUCTURAL STABILITY DUE TO BULGING WALL AND QUESTIONABLE ROOF FRAMING 3. REMOVE LOOSE SECTIONS OF BULGING WALLS AND MAKE SITE SAFE #14WG02 | DOB VIOLATION - ACTIVE |
| Apr 30, 2010 | IMMEDIATE EMERGENCY #1718 | DOB VIOLATION - ACTIVE |
| Mar 12, 2003 | UNSAFE BUILDINGS #3189/03 | DOB VIOLATION |
| Issued | Violation | Status |
|---|---|---|
| Jan 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle D (premises is in Community District 14) | Active |
| Jan 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle D (premises is in Community District 14) | Active |
None open.