13 floors · 71,063 sq ft · built 1927 · class O6 · owner of record: 30 E 40th Street Jv Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 6 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 45 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 45 days | Keep the report on file (not filed with DOB) |
| Facade inspection report (Cycle 10A) Applies Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $26,250 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2027 in 97 days | No Cycle 10 report on record yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 71,063 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 166 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 166 days | Annual filing |
| Energy audit and retro-commissioning (2029) Likely applies Local Law 87 · Calendar year 2029 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 869). Agency page | Dec 31, 2029 in 1141 days | Next due 2029 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jun 17, 2024 | Construction CLASS - 2 A.C. 27-929 FAILURE TO COMPLETE INSTALLATION OF FULL SYSTEM OF AUTOMATIC SPRINKLERS & FILE FINAL SPRINKLER REPORT PREPARED BY REGISTERED DESIGN PROFESSIONAL IN OFFICE BUILDING 100 FEET OR MORE IN HEIGHT IN EXIS #37028817J | Sep 12, 2024 IN VIOLATION | $0 |
| Feb 28, 2023 | Construction CLASS - 2 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN HE #37025425R | Jun 29, 2023 DEFAULT | $0 |
| Nov 1, 2021 | Construction CLASS - 2 SEC. AC 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEMOF AUTOMATIC SPRINKLERS & FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BLDG 100 FEET OR MORE IN #37022476N | Jul 14, 2022 IN VIOLATION | $0 |
| Mar 30, 2021 | Construction CLASS - 2 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN HE #37020761N | Jul 1, 2021 DEFAULT | $0 |
| Jul 13, 2020 | Construction CLASS - 2 SEC. AC 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEMOF AUTOMATIC SPRIKLERS & FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL BY 7/1/19,IN AN OFFICE BLDG 100 FEET OR #37019812X | Jan 28, 2021 ADMIT/IN-VIO | $0 |
| Nov 15, 2019 | Construction CLASS - 2 SEC. A.C.27-929.1,FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS & FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL BY 7/1/19,IN AN OFFICE BLDG 100 FEET #37016384P | Feb 13, 2020 STIPULATION/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Dec 1, 2024 | FAILURE TO POST ENERGY GRADE/SCORE FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3 #2400212 | DOB VIOLATION - ACTIVE |
| Aug 2, 2024 | FAILURE TO BENCHMARK FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 #00085 | DOB VIOLATION - ACTIVE |
| May 2, 2024 | FAILURE TO BENCHMARK FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 #00166 | DOB VIOLATION - ACTIVE |
| Dec 1, 2021 | FAILURE TO POST ENERGY GRADE/SCORE FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3 #2100432 | DOB VIOLATION - ACTIVE |
| Sep 3, 2019 | SPRINKLER FAILED TO FILE FINAL SPRINKLER REPORT BY JULY 1, 2019 #NRF00248 | DOB VIOLATION - ACTIVE |
| May 31, 2018 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 8A TECHNICAL REPORT BY 02/21/2017 #01387 | DOB VIOLATION - ACTIVE |
| Jan 3, 2017 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST #01736 | DOB VIOLATION - ACTIVE |
| Jan 3, 2017 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST #01734 | DOB VIOLATION - ACTIVE |
| Jan 3, 2017 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST #01735 | DOB VIOLATION - ACTIVE |
| Nov 14, 2016 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST #01953 | DOB VIOLATION - ACTIVE |
| Nov 14, 2016 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST #01952 | DOB VIOLATION - ACTIVE |
| Jan 31, 2013 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 7A TECHNICAL REPORT BY 02/21/2012 #00081 | DOB VIOLATION - ACTIVE |
| Aug 16, 2005 | ZONING #MTF06RNS | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 29, 2026 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Active |
| Oct 29, 2026 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Active |
| Oct 29, 2026 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Active |
| Dec 2, 2024 | Benchmarking - LL84 FTF-EN-BENCH FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 | Active |
| Dec 1, 2024 | Energy Grade - LL33 FTP-EN-EGRDEA | Active |
| Aug 2, 2024 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| May 2, 2024 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Aug 25, 2023 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Report | Active |
| Dec 1, 2021 | Energy Grade - LL33 FTP-EN-EGRDEA | Active |
| Sep 3, 2019 | Sprinklers FTF-SP-FINAL | Active |
| May 31, 2018 | Facades FISPNRF FAILED TO FILE FISP CYCLE 8A TECHNICAL REPORT BY 02/21/2017 | Active |
| Jan 3, 2017 | Elevators ACC1 | Active |
| Jan 3, 2017 | Elevators ACC1 | Active |
| Jan 3, 2017 | Elevators ACC1 | Active |
| Nov 14, 2016 | Elevators ACC1 | Active |
| Nov 14, 2016 | Elevators ACC1 | Active |
| Jan 31, 2013 | Facades FISPNRF FAILED TO FILE FISP CYCLE 7A TECHNICAL REPORT BY 02/21/2012 | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Open |
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Open |
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 16, 2026, 2:59 AM ET. BBL 1008690049.