5 floors · 8 apartments · 9,349 sq ft · built 2009 · class C1 · owner of record: North 7th Street, Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 61 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 61 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 77 days | Annual |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 305 days | Registered through 2027-09-01 |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 1 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 792 days | Next cycle year 2028 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Dec 28, 2022 | Construction CLASS - 1 UNSAFE STORAGE OF COMBUSTIBLE MATERIAL AND EQUIPMENT. AT TIME OF INSPECTION OBSERVED PLASTIC RED CONTAINER FILLED WITH FLAMMABLE/COMBUSTIBLE LIQUIDS BEING TRANSPORTED IN A PLASTIC VESSEL, STORED INSIDE STRUCTUR #39076523N | Apr 8, 2024 IN VIOLATION | $2,500 |
| Dec 28, 2022 | Construction CLASS - 2 FAILURE TO SAFE GUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTION OPERATIONS. AT TIME OF INSPECTION OBSERVED ONGOING WORK WHERE GAS POWERED MASONRY HANDHELD SAW IN USE WITHOUT PROPER VENTILATION. AT TIME #39076521J | Apr 8, 2024 IN VIOLATION | $5,000 |
| Dec 28, 2022 | Construction CLASS - 1 FAILURE TO INSTITUTE/MAINTAIN SAFETY MEASURES: UNSAFE EQUIPMENT. AT TIME OF INSPECTION OBSERVED AN APPROXIMATE 8" MASONRY CUTTING GRINDER POWERED AN DIN USE WITH PROTECTIVE GUARD REMOVED, CREATING AN IMMEDIATE #39076522L | Apr 8, 2024 IN VIOLATION | $2,500 |
| Aug 18, 2022 | Construction CLASS - 2 WORK WITHOUT A PERMIT-INTERIOR GARAGE I OBSERVED AT THE GARAGE LEVEL WITHIN THE BLDG,NEW STEEL FRAMED WALLS FOR PARTITIONS AND A NEW SECOND FLOOR NEW STEEL BEAM ON THE FIRST FLOOR,NEW ELECTRICAL WORK TO INCLUDE #35358529Y | Feb 15, 2023 IN VIOLATION | $625 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 1) | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 31, 2026, 12:05 PM ET. BBL 3023310007.