Manhattan · Block 1275 · Lot 59 · 10017

292 Madison Avenue

24 floors · 170,230 sq ft · built 1923 · class O4 · owner of record: 292 Madison Investor Llc

10open violations
$12,617ECB/OATH penalties owed
0HPD class C (immediately hazardous)
58dto Annual boiler inspection (2 boilers)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 58 days
Keep the report on file (not filed with DOB)
Annual boiler inspection (2 boilers) Applies
Boiler inspection · By December 31 each year
What this is

Boilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2024-03-06 (Accepted). Agency page

Dec 31, 2026
in 58 days
2 of 2 without an accepted 2026 report yet
Facade inspection report (Cycle 10A) Applies
Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027
What this is

Buildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $31,250 in late-filing or failure-to-file penalties. Agency page

Feb 21, 2027
in 110 days
No Cycle 10 report on record yet
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 170,230 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 179 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 179 days
Annual filing
Gas piping inspection (2029 cycle) Likely applies
Local Law 152 · During 2029
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 5 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2029
in 1154 days
Next cycle year 2029
Energy audit and retro-commissioning (2035) Likely applies
Local Law 87 · Calendar year 2035
What this is

Buildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 1275). Agency page

Dec 31, 2035
in 3345 days
Next due 2035

Open violations

ECB / OATH (10) · $12,617 owed
IssuedViolationHearingBalance
Oct 13, 2026Construction CLASS - 2
24 STORY ALT2 FACADE WORK ACTIVE SITE, OBSERVED WORK CONTRARY TO SUPPORTED SCAFFOLD STAIR TOWER ON 19 FL EXP#4. NO DETAILS FOR MANUAL HOIST PULLEY, NO DETAILS FOR STAIR ACCESS TO SCAFFOLD ON PLANS, TIEBACKS NOT
#39560508J
Dec 17, 2026
PENDING
$1,250
Oct 13, 2026Construction CLASS - 2
24 STORY ALT2 FACADE WORK ACTIVE SITE, OBSERVED WORK CONTRARY TO SSP/CODE INADEQUATE ROOF PROTECTION OF ADJOINING PROPERTIES AT EXP#2,3. ROOF PROTECTION NOT FULLY EXTENDED 20 FT OVER PARAPET WALL/MISSING PROTEC
#39560507H
Dec 17, 2026
PENDING
$1,250
Oct 13, 2026Construction CLASS - 2
24 STORY ALT2 FACADE WORK ACTIVE SITE. UPON REQUEST TO CONTRACTOR ONSITE FOR REQUIRED DOCUMENTS. I ASKED FOR 6 MONTH SHED INSPECTION INSTALLATION LETTER, SUPPORTED SCAFFOLD INSTALLATION LETTER. NONE PROVIDED/RE
#39560509L
Dec 17, 2026
PENDING
$1,250
Oct 13, 2026Construction CLASS - 2
24 STORY ALT2 FACADE WORK ACTIVE SITE.OBSERVED WORKER'S ON SUSPENDED SCAFFOLDS AT EXP#1,4. UPON REQUEST TO QPSS/ RIGGER FOREMAN ONSITE, FOR VALID 32 HR SUSPENDED SCAFFOLD SUPERVISOR TRAINING CARD OR 8 HR REFRES
#39560504M
Dec 17, 2026
PENDING
$1,250
Oct 13, 2026Construction CLASS - 2
24 STORY ALT2 FACADE WORK ACTIVE SITE. OBSERVED WOODEN STRUCTURE ON TOP OF SIDEWALK SHED AT EXP#4, AS PER CONTRACTOR USED FOR PROTECTION OF COPING/CORNICE. ALSO ON 19TH FL OBSERVED BLACK NETTING ATTACHED TO FAC
#39560506X
Dec 17, 2026
PENDING
$1,250
Oct 13, 2026Unknown CLASS - 2
24 STORY ALT2 FACADE WORK ACTIVE SITE IN A COMMERCIAL BUILDING. UPON REQUEST TO SUPER OF BUILDING/CONTRACTOR FOR OPP PLANS ONSITE, NONE PROVIDED/READILY AVAILABLE FOR INSPECTION 3303.10. OBSERVED ON 25 FL OFFIC
#39560511K
Dec 17, 2026
PENDING
$2,500
Oct 13, 2026Construction CLASS - 2
24 STORY ALT2 FACADE WORK ACTIVE SITE PERMIT#M01303988. WORK ON SUSPENDED SCAFFOLD, UPON REQUEST TO QPSS/RIGGER FOREMAN FOR REQUIRED DOCUMENTS AS PER CODE. NO 3RD PERSON LETTER F/ENGINEER ON SCAFFOLD EXP#1. NO
#39560505Y
Dec 17, 2026
PENDING
$1,250
Oct 13, 2026Construction CLASS - 2
24 STORY ALT2 FACADE WORK ACTIVE SITE, OBSERVED WORK CONTRARY TO SIDEWALK SHED PLANS/CODE. PERMIT#M01003530, SHED NOT FULLY EXTENDED OVER ADJOINING PROPERTY MAIN ENTRANCE AT EXP#2 AS PER 3307.6.3/3309.13. SHED
#39560510Z
Dec 17, 2026
PENDING
$1,250
Jul 15, 2026Construction CLASS - 2
FAILURE TO MAINTAIN/DISPLAY ON SITE DOCUMENTS REQUIRED BY BC CHAPTER 33. AT THE TIME OF INSPECTION, ACTIVE CONSTRUCTION WORK WAS OBSERVED ATTHE 27-STORY BUILDING. WORKERS WERE PERFORMING FACADE WORK. NO STRUCTU
#39556626Z
Oct 8, 2026
IN VIOLATION
$1,250
May 22, 2014Construction CLASS - 1
WORK DOES NOT CONFORM TO APPROVED CONT.DOCS &/OR APPROVED AMENDMENTS.NOTED AT TIME OF INSPEC.FOR FACADE WORK PLAN SHOWS CURTAIN WALL DESIGN WHERE AS NOW PRE-EXISTING MASONRY ORCHES & EXISTING FACADE STONE BEING
#35092198N
Jul 10, 2014
IN VIOLATION
$117
DOB (2)
IssuedViolationStatus
Jun 18, 1997CONSTRUCTION

#05C03
VIOLATION UNSERVED ECB-WORK WITHOUT PERMIT-ACTIVE
Jun 18, 1997CONSTRUCTION

#05C3
VIOLATION UNSERVED ECB-ACTIVE
DOB NOW Safety (0)

None open.

HPD (0)

None open.

Issued in the last 120 days

DateSourceWhatNow
Oct 13, 2026ECBConstruction: 24 STORY ALT2 FACADE WORK ACTIVE SITE, OBSERVED WORK CONTRARY TO SUPPORTED SCAFFOLD STAIR TOWER ON 19 FL EXP#4. NO DETAILS FOR MANUAL HOIST PULLEY, NO DETAILS FOR STAIR ACCESS TO SCAFFOLD ON PLANS, TIEBACKS NOTOpen
Oct 13, 2026ECBConstruction: 24 STORY ALT2 FACADE WORK ACTIVE SITE, OBSERVED WORK CONTRARY TO SSP/CODE INADEQUATE ROOF PROTECTION OF ADJOINING PROPERTIES AT EXP#2,3. ROOF PROTECTION NOT FULLY EXTENDED 20 FT OVER PARAPET WALL/MISSING PROTECOpen
Oct 13, 2026ECBConstruction: 24 STORY ALT2 FACADE WORK ACTIVE SITE. UPON REQUEST TO CONTRACTOR ONSITE FOR REQUIRED DOCUMENTS. I ASKED FOR 6 MONTH SHED INSPECTION INSTALLATION LETTER, SUPPORTED SCAFFOLD INSTALLATION LETTER. NONE PROVIDED/REOpen
Oct 13, 2026ECBConstruction: 24 STORY ALT2 FACADE WORK ACTIVE SITE.OBSERVED WORKER'S ON SUSPENDED SCAFFOLDS AT EXP#1,4. UPON REQUEST TO QPSS/ RIGGER FOREMAN ONSITE, FOR VALID 32 HR SUSPENDED SCAFFOLD SUPERVISOR TRAINING CARD OR 8 HR REFRESOpen
Oct 13, 2026ECBConstruction: 24 STORY ALT2 FACADE WORK ACTIVE SITE. OBSERVED WOODEN STRUCTURE ON TOP OF SIDEWALK SHED AT EXP#4, AS PER CONTRACTOR USED FOR PROTECTION OF COPING/CORNICE. ALSO ON 19TH FL OBSERVED BLACK NETTING ATTACHED TO FACOpen
Oct 13, 2026ECBUnknown: 24 STORY ALT2 FACADE WORK ACTIVE SITE IN A COMMERCIAL BUILDING. UPON REQUEST TO SUPER OF BUILDING/CONTRACTOR FOR OPP PLANS ONSITE, NONE PROVIDED/READILY AVAILABLE FOR INSPECTION 3303.10. OBSERVED ON 25 FL OFFICOpen
Oct 13, 2026ECBConstruction: 24 STORY ALT2 FACADE WORK ACTIVE SITE PERMIT#M01303988. WORK ON SUSPENDED SCAFFOLD, UPON REQUEST TO QPSS/RIGGER FOREMAN FOR REQUIRED DOCUMENTS AS PER CODE. NO 3RD PERSON LETTER F/ENGINEER ON SCAFFOLD EXP#1. NOOpen
Oct 13, 2026ECBConstruction: 24 STORY ALT2 FACADE WORK ACTIVE SITE, OBSERVED WORK CONTRARY TO SIDEWALK SHED PLANS/CODE. PERMIT#M01003530, SHED NOT FULLY EXTENDED OVER ADJOINING PROPERTY MAIN ENTRANCE AT EXP#2 AS PER 3307.6.3/3309.13. SHEDOpen
Sep 9, 2026DOB SafetyAEUHAZ: Closed
Jul 15, 2026ECBConstruction: FAILURE TO MAINTAIN/DISPLAY ON SITE DOCUMENTS REQUIRED BY BC CHAPTER 33. AT THE TIME OF INSPECTION, ACTIVE CONSTRUCTION WORK WAS OBSERVED ATTHE 27-STORY BUILDING. WORKERS WERE PERFORMING FACADE WORK. NO STRUCTUClosed
Jul 15, 2026ECBUnknown: MISCELLANEOUS VIOLATIONS. AT THE TIME OF INSPECTION OF A 27 STORY BUILDING I OBSERVED UNSAFE SUSPENDED SCAFFOLD OPERATIONS. WORKERS OPERATING SUSPENDED SCAFFOLDS AT EXP 1 AND 2 SEEN WORKER AT DIFFERENT LEVELS SClosed

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Nov 3, 2026, 7:08 PM ET. BBL 1012750059.