Brooklyn · Block 7247 · Lot 245 · 11224

2890 Shell Road

1 floors · built 1931 · class G7 · owner of record: Bh Shell Road Llc

5open violations
$22,500ECB/OATH penalties owed
0HPD class C (immediately hazardous)
1166dto Gas piping inspection (2029 cycle)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 70 days
Keep the report on file (not filed with DOB)
Gas piping inspection (2029 cycle) Likely applies
Local Law 152 · During 2029
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 13 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2029
in 1166 days
Next cycle year 2029

Open violations

ECB / OATH (2) · $22,500 owed
IssuedViolationHearingBalance
Oct 5, 2026Construction CLASS - 1
UNLAWFULLY CONTINUE TO WORK WHILE ON NOTICE OF A STOP WORK ORDER: AT THE TIME OF INSPECTION, OBSERVED AT EXPOSURE 1, ERECTED CANOPY CONSISTING OF METAL FRAME AND CORRUGATED ROOF STRUCTURE, WHILE UNDER NOTICE OF
#39207160K
Dec 16, 2026
PENDING
$10,000
Mar 31, 2021Construction CLASS - 1
WORK WITHOUT A PERMIT AT TIME OF INSPECTION OBSERVED NEW METAL STRUCTURE HAS BEEN CREATED APPROX. 30' X 20' NEW WALLS AND ROOF MADE WITH CORRIGATED METAL SHEETS.INFILLED WITH CMU BLOCKS APPROX. 4' HEIGHT AND 15
#35560132P
Aug 11, 2021
DEFAULT
$12,500
DOB (2)
IssuedViolationStatus
Feb 15, 2019CONSTRUCTION

#CN1310RA
DOB VIOLATION - ACTIVE
Dec 11, 2015CONSTRUCTION
FAILURE TO CORRECT UNLAWFUL ARTERIAL ROOF SIGN STRUCTURE THAT EXCEEDS SURFACE AREA LIMITS IN AN M1-2 ZONE UE UNDER ACCESSORY SIGN & STRUCTUR E PERMITS SG3000848849 ALT300848830 WAS DISCONTINUED AS PER ZR52-61 AS SIGN STRUCTURE WAS VACANT/USED TO DISPLAY ADVERTISING FOR MORE THAN 2 YEARS ANY POTENTIA
#STF12VZ
DOB VIOLATION - ACTIVE
DOB NOW Safety (1)
IssuedViolationStatus
Sep 18, 2025Gas Piping - LL152 FTF-PL-PER
Cycle 1, Sub-cycle B (premises is in Community District 13)
Active
HPD (0)

None open.

Issued in the last 120 days

DateSourceWhatNow
Oct 5, 2026ECBConstruction: UNLAWFULLY CONTINUE TO WORK WHILE ON NOTICE OF A STOP WORK ORDER: AT THE TIME OF INSPECTION, OBSERVED AT EXPOSURE 1, ERECTED CANOPY CONSISTING OF METAL FRAME AND CORRUGATED ROOF STRUCTURE, WHILE UNDER NOTICE OFOpen

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Oct 22, 2026, 4:20 AM ET. BBL 3072470245.