7 floors · 104,001 sq ft · built 1926 · class RB · owner of record: Unavailable Owner
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 43 days | Keep the report on file (not filed with DOB) |
| Energy audit and retro-commissioning (2026) Likely applies Local Law 87 · Calendar year 2026 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 166). Agency page | Dec 31, 2026 in 43 days | Due this year |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 104,001 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 164 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 164 days | Annual filing |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 2 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1139 days | Next cycle year 2029 |
| Facade inspection report (Cycle 10A) Applies Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $1,764,000 in late-filing or failure-to-file penalties. Agency page | On file | Cycle 10 filing on record: SAFE (2026-10-23) |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Apr 10, 2023 | Construction CLASS - 2 FAILURE TO COMPLY WITH DOT REGULATIONS AS PER 34 RCNY 2-05 AND ADMIN CODE PROVISIONS 19-107, 19-108 OR 19-121. OBSERVED A STREET ENCLOSURE AT EXP#1 W/ A VEHICLE AND A DEBRIS CONTAINER PLACED INSIDE OF IT. THE #39515168J | Oct 6, 2023 IN VIOLATION | $1,250 |
| Apr 10, 2023 | Construction CLASS - 2 OBSERVED A SIDEWALK SHED (SWS) AT EXP#1 WITH THE SWS POSTS AT THE ADJ EXP#2 PROPERTY DRIVEWAY NOT SECURED AGAINST DISPLACEMENT AND/OR MARKED W/ HIGH VISIBILITY MARKINGS, PER CODE. ALSO OBSERVED 1 RED STANDPIPE #39515167H | Oct 6, 2023 IN VIOLATION | $2,400 |
| Oct 21, 2022 | Construction CLASS - 1 AT THE TIME OF MY INSPECTION OBSERVED SUPPORTED SCAFFOLD AT EXP#3 AND 4 WITH FOLLOWING VIOLATION CONDITION: 1. NOT FULLY PLANKED PLATFORM 2. MISSING GUARDRAIL SYSTEM 3. PLANKS NOT TIED DOWN 4. NO NETTING. STOP #39507968H | Apr 26, 2023 IN VIOLATION | $2,500 |
| Jun 7, 2022 | Construction CLASS - 1 AFTER REVIEWED DOB APPROVED DRAWINGS FOR SUPPORTED SCAFFOLD REVEALED THAT SCAFFOLD DOES NOT CONFORM DRAWINGS (AT EXP#3 FRAME SHOULD BE INSTALLED ON DOUBLE W8X10 BEAMS AND PARAPET. BEAMS HAVE TO BE INSTALL ON 2 #39501981P | Jan 19, 2023 IN VIOLATION | $625 |
| Jun 7, 2022 | Construction CLASS - 1 AT THE TIME OF MY INSPECTION OBSERVED SUPPORTED SCAFFOLD ON SIDEWALK SHED AT EXP#1, 2 AND 3. UPON REQUEST LOAD IMPOSED LETTER FROM REGISTERED DESIGN PROFESSIONAL NONE WERE PROVIDED. THIS IS CREATE AN UNSAFE CON #39501983Z | Jan 19, 2023 IN VIOLATION | $625 |
| Apr 13, 2022 | Construction CLASS - 1 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROVED AMENDMENTS NOTE AT TIME OF INSPECTION OF 14 STORY NEW BUILDING CONSTRUCTION WORK IN PROGRESS OBSERVED AT EXP #2 OVERHEAD PROTECTION MADE #35645292R | Jan 11, 2023 IN VIOLATION | $625 |
| Jun 1, 2021 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 7A AND 8A REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#809053.REMEDY:SUBMIT ACCEPTABLE #37021826J | Mar 2, 2022 IN VIOLATION | $0 |
| Jun 21, 2018 | Construction CLASS - 1 FAILURE TO MAINTAIN BLDG EXTERIOR WALLS/FACADES & APPURTENANCES.SOUTH ELEVATION EXP#1 :BROKEN WINDOW GLASS @3RD FL.CRACK DECORATIVE STONE @ROOF,CORNICE NORTH ELEVATION EXP#3:VERTICAL CRACKS @PARAPET WALL & SPAL #35319082P | Aug 20, 2018 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Feb 22, 2022 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022 #01007 | DOB VIOLATION - ACTIVE |
| May 12, 2020 | ELEVATOR #9027/679290 | DOB VIOLATION - ACTIVE |
| May 12, 2020 | ELEVATOR #9027/679291 | DOB VIOLATION - ACTIVE |
| May 22, 2019 | ELEVATOR #9027/653124 | DOB VIOLATION - ACTIVE |
| May 22, 2019 | ELEVATOR #9027/653123 | DOB VIOLATION - ACTIVE |
| Jun 4, 2018 | ELEVATOR #9027/629837 | DOB VIOLATION - ACTIVE |
| Jun 4, 2018 | ELEVATOR #9027/629836 | DOB VIOLATION - ACTIVE |
| May 31, 2018 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 8A TECHNICAL REPORT BY 02/21/2017 #00593 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Sep 18, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle B (premises is in Community District 2) | Active |
| Feb 22, 2022 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022 | Active |
| May 31, 2018 | Facades FISPNRF FAILED TO FILE FISP CYCLE 8A TECHNICAL REPORT BY 02/21/2017 | Active |
| Jan 31, 2013 | Facades FISPNRF FAILED TO FILE FISP CYCLE 7A TECHNICAL REPORT BY 02/21/2012 | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 18, 2026, 10:38 AM ET. BBL 3001667501.