4 floors · 113,500 sq ft · built 1957 · class W1 · owner of record: Nyc Department Of Education
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 58 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (3 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-12-18 (Accepted). Agency page | Dec 31, 2026 in 58 days | 3 of 3 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 113,500 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 179 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 179 days | Annual filing |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 1 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 789 days | Next cycle year 2028 |
| Energy audit and retro-commissioning (2033) Likely applies Local Law 87 · Calendar year 2033 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 343). Agency page | Dec 31, 2033 in 2615 days | Next due 2033 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jan 23, 2026 | Construction CLASS - 2 RE-ISSUE #35691773P FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. ILLUMINATION FOR EXITS, EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1; 27-381. AT THE TIME OF INSPECTION, THE FOLLOWING EMERGENCY #35724883Y | Feb 13, 2026 POP/IN-VIO | $0 |
| Jan 23, 2026 | Construction CLASS - 2 RE-ISSUE 35691772N. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. AT THE TIME OF INSPECTION, FIRE PROOF, SELF-CLOSING DOORS IN THE FOLLOWING LOCATIONS WERE NOT SELF-CLOSING:-CLOSING DOOR THAT LEADS TO #35724884X | Feb 13, 2026 POP/IN-VIO | $0 |
| Jan 23, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NO FIRE STOPPING PER BC 712.3; 27-345. AT THE TIME OF INSPECTION THE ELECTRICAL METERROOM HAD MULTIPLE HOLE PENETRATIONS. REMEDY: PROVIDE/MAINTAIN FIRE STO #35724886J | Feb 13, 2026 POP/IN-VIO | $0 |
| Jan 23, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. AT THE TIME OF INSPECTION, MULTIPLE CRACKS IN CMU BLOCKS IN BULKHEAD 3 AND 4 OBSERVED. REMEDY: REPAIR AND/OR REPLACE. #35724885H | Feb 13, 2026 POP/IN-VIO | $0 |
| Mar 7, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.ILLUMINATION FOREXITS,EXIT DISCHARGES AND PUBLIC CORRIDORS.EMERGENCY LIGHTS WITH BATTERY BACK UP POWER NOT WORKING WHEN TESTED.1ST FL BOX#7,CAFETERIA 2 LIGH #35691773P | May 13, 2025 POP/IN-VIO | $0 |
| Mar 7, 2025 | Construction CLASS - 2 REISSUE#35663184Z FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED INTERIOR FPSC DOORS NOT CLOSING PROPERLY AT 3RD FL STAIR E ROOM#339 & CORRIDOR SMOKE DOOR BY#312.2ND FL ROOM#239.1ST FL CAFETERIA EN #35691772N | May 13, 2025 POP/IN-VIO | $0 |
| Jan 12, 2023 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.DOORS FOR CLASSROOMS ON 1ST, 2ND, 3RD & 4TH FLS DON'T SELF CLOSE.REMEDY:REPAIR AND/OR REPLACE. #35663184Z | May 9, 2023 POP/IN-VIO | $0 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2018 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 3, 2026, 9:30 AM ET. BBL 4003430001.