5 floors · 98,000 sq ft · built 1998 · class W1 · owner of record: Nyc Department Of Education
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 66 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 98,000 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 187 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 187 days | Annual filing |
| Energy audit and retro-commissioning (2028) Likely applies Local Law 87 · Calendar year 2028 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 3278). Agency page | Dec 31, 2028 in 797 days | Next due 2028 |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 7 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1162 days | Next cycle year 2029 |
| Annual boiler inspection (3 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-04-27 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jun 18, 2026 | Construction CLASS - 2 REISSUE#35721010L FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:AT EXIT 3 CAFETERIA WATER PENETRATIONS HAVE CAUSED WATER DAMAGE TO THE WALLS IN SEVERAL AREAS.REM:REPAIR AND/OR REPLACE. #35731933Z | Aug 7, 2026 POP/IN-VIO | $0 |
| Jun 18, 2026 | Construction CLASS - 2 REISSUE#35721008M FAILURE TO MAINTAIN BUILDING WALL(S)OR APPURTENANCESNOTED:ON ROOF THERE IS SEVERAL AREAS THAT HAVE FLASHING IN DISREPAIR OR MISSING ALL TOGETHER.REM:MAINTAIN EXTERIOR WALL. #35731934K | Aug 7, 2026 POP/IN-VIO | $0 |
| Jun 18, 2026 | Construction CLASS - 2 REISSUE#35721007K EXIT DOOR NOT SELF-CLOSING.NOTED:ON 1ST FLR-EXTERIOREXIT 4 DOES NOT SELF-CLOSE PROPERLY WHEN TESTED.REM:REPAIR/REPLACE DOOR. #35731935M | Aug 7, 2026 POP/IN-VIO | $0 |
| Jul 24, 2025 | Construction CLASS - 2 REISSUE #35692295Y. EXIT DOOR NOT SELF-CLOSING. NOTED: OBSERVED AT 1STFLR CORRIDOR BY 111, M111, CORRIDOR BY 112M CORRIDOR BY 106, AUDITORIUM STAGE RIGHT DOORS ARE NOT CLOSING CORRECTLY. 3RD FLR, STAIRCASE(B) E #35721007K | Aug 22, 2025 POP/IN-VIO | $0 |
| Jul 24, 2025 | Construction CLASS - 2 REISSUE #35692294M. FAILURE TO MAINTAIN BUILDING WALL(S) AND APPURTENANCES. NOTED: MISSING BRICK OVER EXIT 1. ROOF PARAPET MISPLACE/LOOSE FLASHING. REMEDY: MAINTAIN EXTERIOR WALL. #35721008M | Aug 22, 2025 POP/IN-VIO | $0 |
| Jul 24, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: WATER PENETRATION ON INTERIOR WALLS IN CAFETERIA AT EXIT 3 ON FIRST FLOOR. REMEDY: REPAIR AND/OR REPLACE. #35721010L | Aug 22, 2025 POP/IN-VIO | $0 |
| Mar 21, 2022 | Boilers CLASS - 2 AUTOMAT FEED WATER MODULATING VALVE DEFECTIVE, CORRODED AND LEAKING, BLRS 01, 02, AND 03-SMOKE ALARMS DEFECTIVE AND EXPOSED ELECTRICAL BLRS, 01, 02 AND 03-NO GUARDS AT WATER LEVEL GLASSES-FUEL OIL STORED IN BOI #39058472N | Mar 29, 2022 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #07919 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #07921 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #07920 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2018 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2018 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 26, 2026, 12:29 AM ET. BBL 2032780014.