Brooklyn · Block 736 · Lot 50 · 11220

267 45 Street

1 floors · 3,700 sq ft · built 1958 · class E1 · owner of record: 269 Property Llc

75open violations
$0ECB/OATH penalties owed
0HPD class C (immediately hazardous)
1163dto Gas piping inspection (2029 cycle)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 67 days
Keep the report on file (not filed with DOB)
Gas piping inspection (2029 cycle) Likely applies
Local Law 152 · During 2029
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 7 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2029
in 1163 days
Next cycle year 2029

Open violations

ECB / OATH (4)
IssuedViolationHearingBalance
Oct 24, 2013Plumbing CLASS - 1
FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER: LACK OF A SYSTEM OFAUTOMATIC SPRINKLES WHERE REQUIRED PER BC 903.2. NO SPRINKLER SYSTEM (AUTOMATIC) INSTALLED WHERE MORE THAN 2 CLOTHES DRYING MACHINES ARE
#35017692Z
Dec 17, 2013
IN VIOLATION
$0
Oct 24, 2013Construction CLASS - 1
OCCUPANCY CONTRARY TO THAT ALLOWED BY THE C/O. C/O #3004112 ISSUED 2. 21.97 INDICATES PREMISES IS AN AUTO REPAIR SHOP W/STORAGE, WELDING ANDPAINTING OF AUTOMOBILES, TRUCKS, MOTORCYCLES OR TRAILERS. AT TIME OF
#35017691R
Dec 16, 2013
IN VIOLATION
$0
Dec 11, 2006Boilers Non-Hazardous
18B,48B,50A.50A BOTTOM BLOWDOWN VALVE LEAKING.
#32050359K
Nov 26, 2007
WRITTEN OFF
$0
Dec 1, 2006Boilers Non-Hazardous
18B,50A,48B,50B.50A FEED LINE VALVE LEAKING.50B REPLACE STEAM GAUGE W/"0 TO 300" TYPE
#32050360H
Nov 26, 2007
WRITTEN OFF
$0
DOB (36)
IssuedViolationStatus
Nov 14, 2025HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
#01133
DOB VIOLATION - ACTIVE
Nov 14, 2025HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
#00323
DOB VIOLATION - ACTIVE
Nov 14, 2025HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
#01134
DOB VIOLATION - ACTIVE
Nov 14, 2025HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
#00324
DOB VIOLATION - ACTIVE
Sep 23, 2024HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION
#00337
DOB VIOLATION - ACTIVE
Sep 23, 2024HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION
#01203
DOB VIOLATION - ACTIVE
Sep 23, 2024HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION
#01202
DOB VIOLATION - ACTIVE
Sep 23, 2024HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION
#00336
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION
#00934
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION
#00970
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION
#02096
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION
#02150
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
#03314
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
#03345
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
#04456
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
#04492
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION
#04090
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION
#04536
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION
#00989
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION
#01030
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION
#02193
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION
#02251
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION
#02947
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION
#03385
DOB VIOLATION - ACTIVE
Apr 25, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION
#01858
DOB VIOLATION - ACTIVE
Apr 25, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION
#01857
DOB VIOLATION - ACTIVE
Apr 25, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION
#00728
DOB VIOLATION - ACTIVE
Apr 25, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION
#00727
DOB VIOLATION - ACTIVE
Sep 14, 2022STRUCTURALLY COMPROMISED BUILDING
FAILURE TO SUBMIT AN ACCEPTABLE INSPECTN RPT FOR STRUCTURALLY COMPROMISED BLDG.
#00044
DOB VIOLATION - ACTIVE
Mar 16, 2020HIGH PRESSURE BOILER
VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION
#00800
DOB VIOLATION - ACTIVE
Mar 16, 2020HIGH PRESSURE BOILER
VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION
#00799
DOB VIOLATION - ACTIVE
Mar 16, 2020HIGH PRESSURE BOILER
VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION
#00838
DOB VIOLATION - ACTIVE
Mar 16, 2020HIGH PRESSURE BOILER
VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION
#00837
DOB VIOLATION - ACTIVE
Dec 11, 2019CONSTRUCTION
DUE TO FIRE
#CER01SM
DOB VIOLATION - ACTIVE
Jan 29, 2014FAIL TO CERTIFY CLASS 1
FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
#00165
DOB VIOLATION - ACTIVE
Jan 29, 2014FAIL TO CERTIFY CLASS 1
FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
#00166
DOB VIOLATION - ACTIVE
DOB NOW Safety (35)
IssuedViolationStatus
Nov 14, 2025Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
Active
Nov 14, 2025Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
Active
Nov 14, 2025Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
Active
Nov 14, 2025Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
Active
Sep 23, 2024Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION
Active
Sep 23, 2024Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION
Active
Sep 23, 2024Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION
Active
Sep 23, 2024Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION
Active
Apr 25, 2023Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Apr 25, 2023Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Apr 25, 2023Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Apr 25, 2023Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Sep 14, 2022Structurally Compromised Buildings FTF-SC-INITL
Active
Mar 16, 2020Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Mar 16, 2020Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Mar 16, 2020Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Mar 16, 2020Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Jan 29, 2014AEUHAZ FTC-AEU-HAZ
Active
Jan 29, 2014AEUHAZ FTC-AEU-HAZ
Active
HPD (0)

None open.

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Oct 25, 2026, 12:53 AM ET. BBL 3007360050.