| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 47 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 37,372 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 168 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 168 days | Annual filing |
| Annual property registration Check HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 291 days | Required only if the owner doesn't live there |
| Facade inspection report (Cycle 10B) Applies Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. Agency page | Feb 21, 2028 in 464 days | No Cycle 10 report on record yet |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 5 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1143 days | Next cycle year 2029 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 17, 2024 | Construction CLASS - 2 OCCUPANCY CONTRARY TO THAT ALLOWED BY THE CERTIFICATE OF OCCUPANCY. ROOF IS ARRANGED FOR RECREATION AND COMMERCIAL OCCUPANCY IN CONJUNCTION WITH 7TH FLOOR CAFE, THIS OCCUPANCY TYPE IS NOT AUTHORIZED BY DOB WITH #39119421J | Sep 26, 2024 DEFAULT | $6,250 |
| May 26, 2021 | Construction CLASS - 2 WORK WITHOUT PERMIT.NOTE:OBSERVED STONE TILES APROX 3FT X 3FT INSTALLED AND PILES OF SOME STONE TILES STORED ON ROOF WITHOUT PLANS ON SITE TO ATTEST TO ADDED WEIGHT ON ROOF.CONTACT DEPARTMENT OF BUILDINGS FOR F #35536985R | Aug 12, 2021 IN VIOLATION | $625 |
| Sep 6, 2019 | Construction CLASS - 1 FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING. AT TIME OF INSPECTION OF EXISTING 7 STY BLDG,I OBSERVED WORKERS WORKING IN THE BASEMENT. IN THE BASEMENT PILES OF CONSTRUCTION MATERIALS WERE INADEQUATELY MANAGED. THI #35453205N | Nov 7, 2019 IN VIOLATION | $2,500 |
| Feb 11, 2019 | Construction CLASS - 1 SEC. 3303.9 FAILURE TO MAINTAIN REQUIRED MEANS OF EGRESS. AT TIME OF INSPECTION ON AN ALT-1 PROPOSED 7 STY BLDG ACTIVE JOB SITE CURRENTLY ONTHE 6TH FL LEVEL ERECTING STEEL METAL DECK,IT WAS OBSERVED ON EXP#2 #35385812N | Jun 6, 2019 IN VIOLATION | $2,500 |
| Feb 11, 2019 | Construction CLASS - 1 SEC. 3301.4 INSPECTIONS-ON TEMPORARY EQUIPMENTS AT TIME OF INSPECTION ON AN ALT-1 PROPOSED 7 STY BLDG ACTIVE JOB SITE CURRRENTLY ON THE 6TH FL LEVEL PUTTING UP STEEL METAL DECK,IT WAS OBSERVED AS NOTED THAT ALL #35385813P | Jun 6, 2019 IN VIOLATION | $625 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Oct 29, 2026 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Active |
| Aug 29, 2025 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Report | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Open |