5 floors · 18,012 sq ft · built 1900 · class HH · owner of record: 125 Bowery Inc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 66 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-05-09 (Accepted). Agency page | Dec 31, 2026 in 66 days | 2 of 2 without an accepted 2026 report yet |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 3 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 797 days | Next cycle year 2028 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Sep 17, 2026 | Construction CLASS - 1 AT TIME OF INSPECTION, OBSERVED PARAPET WALL WITH LARGE CRACK ON CORNER OF EXPO 2 AT EXPO 3 SIDE. MULTIPLE CHIMNEY STACK ALSO MISSING MORTAR HOLDING THE BRICKS TOGETHER. AREA OF PARAPET/CHIMNEYS OVERHANGS PUBLI #39204491L | Dec 3, 2026 PENDING | $2,500 |
| May 30, 2026 | Unknown CLASS - 1 I OBSERVED EXTENSIONS CORD BEEN USE AS PERMANENT WIRING TO POWER SINGLE ROOMS, APPLIANCES AND LIGHT FIXTURES IN COMMERCIAL STORES.; NEC 400.12, COMPLY WITH EC CODE; FIX ALL CONDITIONS AS PER NEC AND NYC AMENDME #39190504R | Aug 6, 2026 IN VIOLATION | $1,600 |
| May 23, 2026 | Unknown CLASS - 1 I OBSERVED UNSAFE UNSUITABLE ELECTRICAL CONDITIONS THROUGHOUT GROUND, 3RD AND 5TH FLOORS, OPEN BOXES, WIRE HANGING AND EXPOSED SUBJECT TO ELECTROCUTIONS., COMPLY WITH EC; FIX ALL CONDITIONS AS PER NEC AND NYC A #39190505Z | Aug 6, 2026 IN VIOLATION | $1,600 |
| May 18, 2026 | Construction CLASS - 1 OBSERVED CUBICAL BEING INSTALLED AT 3RD FLOOR AND DEMOLISHED AT 5TH FLOOR. NO WORK ALLOWED TO CONSTRUCT OR DEMOLISH LIVING QUARTER CUBICAL SPACE. STOP THROUGHOUT ALL FLOORS OF THE PROPERTY (EXCEPT FOR EMERGENCY #39189053Z | Feb 5, 2027 PENDING | $2,500 |
| May 6, 2026 | Unknown CLASS - 1 ELECTRICAL WORK WITHOUT A PERMIT. OBSERVED ON THE 2ND 3RD 4TH FLS INSTALLATION OF A/C SPILT UNIT DUCTLESS SYSTEM AND WIRING FOR SINGLE RMS NEW EMT PIPES FEED BOXES FOR POWER THRU OUT. 27-3018(B) ALL WORK MUST B #39187492L | Feb 9, 2027 PENDING | $2,500 |
| May 6, 2026 | Unknown CLASS - 1 FAILURE TO GROUND ELECTRICAL SYSTEMS. OBSERVED IN THE BASEMENT THAT THE MAIN BUILDING WATER GROUND CLAMP IS DEUTERATED COMPLETELY CORRODED POTENTIAL FOR FIRE ELECTRICAL SHOCK. EC 250.4 250.25 GROUNDING ELECTROD #39187494P | Feb 9, 2027 PENDING | $4,800 |
| May 6, 2026 | Construction CLASS - 1 OBSERVED THROUGH OUT THE BUILDING SPRINKLER HEADS OBSTRUCTED WHICH IS CONTRARY TO CODE SECTION BC 903.3.3, REPAIR AND/REPLACE #39187524R | Feb 16, 2027 PENDING | $2,500 |
| May 6, 2026 | Construction CLASS - 1 OBSERVED IN F & R TRADING STORE IN THE BASEMENT OPEN ENDED GAS LINE AND A FUTURE ON GAS LINE. ALSO A SPRINKLER HEAD NOT INSTALLED PROPERLY. BOXES OBSTRUCTING SPRINKLER HEADS SPRAY WHICH IS CONTRARY TO CODE SECT #39187523P | Feb 16, 2027 PENDING | $2,500 |
| May 6, 2026 | Construction CLASS - 1 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.ATOI I WAS GRANTED ACCESS TO SUBJECT LOCATION WHERE I OBSERVED CONCRET CEILING JOIST AT BASEMENT EXPOSURE 1 IN NEED OF REPAIR ALSO WOODEN CEILING JOIST AT 2 #39187511H | Feb 25, 2027 PENDING | $2,500 |
| May 6, 2026 | Construction CLASS - 1 OBSERVED ON THE FOURTH FLOOR SPRINKLER HEAD INSTALLED BACKWARDS. IN THE BATHROOM SINKS DOESN'T CLOSE. ON THE FIFTH FLOOR RADIATOR IS NOT SUPPORT PROPERLY AND SPRINKLER HEAD DAMAGED WHICH IS CONTRARY TO CODE SEC #39187525Z | Feb 16, 2027 PENDING | $2,500 |
| May 6, 2026 | Unknown CLASS - 1 FAILURE TO PROVIDE/MAINTAIN SUFFICIENT ACCESS/WORK SPACE ABOUT ELECTRICAL EQUIPMENT. OBSERVED IN THE BASEMENT THAT THE SERVICE EQUIPMENT IS BLOCKED AND COVERED WITH BOXES AND COMBUSTIBLE MATERIALS. POTENTINAL F #39187495R | Feb 9, 2027 PENDING | $1,600 |
| May 6, 2026 | Unknown CLASS - 1 UNAPPROVED/UNSAFE/UNSUITABLE ELECTRICAL EQUIPMENT, APPARATUS, MATERIALS, DEVICES, APPLIANCES OR WIRING IN USE. OBSERVED IN BATH RMS ON 3RD 4TH 5TH FLS NO GFCI INSTALLED WHERE SINKS ARE LOCATED. ALSO EXPOSED WIR #39187493N | Feb 9, 2027 PENDING | $1,600 |
| May 6, 2026 | Construction CLASS - 1 OBSERVED IN THE BASEMENT BOILER ROOM BEING USED AS A STORAGE ROOM. ALSO, STORAGE AROUND GAS METER LOCATED IN CHINESE RESTAURANT. IN BASEMENT USING JIM CAPS ON WASTE LINES. THROUGHOUT THE BUILDING PIPE PENETRATI #39187526K | Feb 16, 2027 PENDING | $2,500 |
| Apr 14, 2026 | Construction CLASS - 1 OBSERVED THE DROP LADDER LANDING AREA TO THE EXTERIOR FIRE ESCAPE ON BOWERY ST SIDE OF THE BUILDING IS OBSTRUCTED BY A SECURED TARP AT AWNING & VENDOR ITEMS AT SIDEWALK., REPAIR AND/REPLACE #39184514J | Feb 25, 2027 PENDING | $2,500 |
| Apr 14, 2026 | Construction CLASS - 2 OBSERVED APPROX. 85% OF THE EXISTING CUBICLES USED AS SLEEPING QUARTERS WAS REMOVED FROM THE 4TH & 5TH FLOOR WITHOUT A PERMIT., OBTAIN ALL PERMITS; CONTACT OBMSWO@BUILDINGS.NYC.GOV FOR RE-INSPECTION. #39186914H | Feb 25, 2027 PENDING | $1,250 |
| Apr 14, 2026 | Construction CLASS - 2 OBSERVED APPROX. 85% OF THE CUBICLES AT 4TH & 5TH FLOOR WAS COMPLETELY REMOVED CONTRARY TO C OF O # 35211. FLOOR IS OCCUPIED & NO ACTIVE PERMIT ON FILE FOR CHANGE OF USE. STOP ALL WORK AT 4TH & 5TH FLOOR ONLY. #39184486L | Feb 25, 2027 PENDING | $1,250 |
| Apr 14, 2026 | Construction CLASS - 2 OBSERVED DEBRIS STORED AT INTERIOR OF 4TH FLOOR, BATHROOM CEILING REMOVED AT 3RD & 4TH FLOOR EXPOSING THE WOODEN FLOORING JOIST. FLOORS ARE OCCUPIED., REPAIR AND/OR REPLACE #39184515L | Feb 25, 2027 PENDING | $1,250 |
| Sep 11, 2025 | Construction CLASS - 1 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER; OBSERVED CEILINGS ON 2ND, 3RD, AND 4TH FLOORS REMOVED IN COMMON BATHROOMS, W/ CEILING JOISTS SUPPORTED BY 4X4'S AND SCREWED ON 2X4'S ATTACHED TO 4X4 BEAMS. #39160034Y | Jan 8, 2026 DEFAULT | $25,000 |
| Aug 4, 2025 | Construction CLASS - 1 ATOI OBSERVED CEILINGS ON SECOND, THIRD AND FOURTH FLOOR REMOVED IN COMMON BATHROOMS. COMPROMISED CEILING JOISTS SUPPORTED BY 4X4 BEAMS AND SCREWED ON 2X4'S ATTACHED TO 4X4 BEAMS. 2X4 TOP PLATES ARE LAID FLAT T #39155953Z | Mar 1, 2027 PENDING | $2,530 |
| Issued | Violation | Status |
|---|---|---|
| Sep 17, 2026 | CONSTRUCTION OBSERVED PARAPET WALL AT ROOF CORNER OF EXPO 2/3 WITH LARGE CRACK AND ALSO MUTIPLE CHIMNEYS AT EXPO 2 WITH MISSING MORTAR. CONDTIONS ARE EXISITNG OVER PUBLIC SIDEWALK AND OVER STORES CAUSING OVERHEAD HAZARD. ENGINEERS REPORT FOR STRUCTURAL STABILITY REQUIRED. #26-02227 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #01899 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #01898 | DOB VIOLATION - ACTIVE |
| Sep 11, 2025 | CONSTRUCTION ENGINEERS REPORT(STRUCTURAL STABILITY) REQUESTED DUE TO CEILINGS ON 2ND, 3RD, AND 4TH FLOORS REMOVED IN COMMON BATHROOMS, WITH CEILING JOISTS SUPPORTED BY 4X4'S AND SCREWED ON 2X4'S ATTACHED TO 4X4 BEAMS. 2X4 TOP PLATES HAVE ALSO BEEN LAID FLAT MAKING IT INADEQUATE FOR LOAD DISTRIBUTION. #25-02119 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION #40952 | DOB VIOLATION - ACTIVE |
| Jan 1, 2009 | LOCAL LAW 62/91 - BOILERS #03584 | DOB VIOLATION - ACTIVE |
| Jan 1, 2009 | LOCAL LAW 62/91 - BOILERS #03583 | DOB VIOLATION - ACTIVE |
| Jan 3, 2008 | LOCAL LAW 62/91 - BOILERS #03492 | DOB VIOLATION - ACTIVE |
| Jan 3, 2008 | LOCAL LAW 62/91 - BOILERS #03491 | DOB VIOLATION - ACTIVE |
| Jan 19, 2007 | LOCAL LAW 62/91 - BOILERS #03574 | DOB VIOLATION - ACTIVE |
| Jan 19, 2007 | LOCAL LAW 62/91 - BOILERS #03575 | DOB VIOLATION - ACTIVE |
| Jan 6, 2006 | LOCAL LAW 62/91 - BOILERS #03406 | DOB VIOLATION - ACTIVE |
| Jan 6, 2006 | LOCAL LAW 62/91 - BOILERS #03405 | DOB VIOLATION - ACTIVE |
| Jan 31, 2005 | LOCAL LAW 62/91 - BOILERS #03964 | DOB VIOLATION - ACTIVE |
| Jan 31, 2005 | LOCAL LAW 62/91 - BOILERS #03963 | DOB VIOLATION - ACTIVE |
| Mar 19, 2003 | LOCAL LAW 62/91 - BOILERS #00443 | DOB VIOLATION - ACTIVE |
| Mar 26, 2002 | LOCAL LAW 62/91 - BOILERS #00484 | DOB VIOLATION - ACTIVE |
| Feb 27, 2001 | LOCAL LAW 62/91 - BOILERS #00453 | DOB VIOLATION - ACTIVE |
| Feb 7, 2000 | LOCAL LAW 62/91 - BOILERS #00436 | DOB VIOLATION - ACTIVE |
| Jul 13, 1999 | CONSTRUCTION #MTF03FE | DOB VIOLATION - ACTIVE |
| Jul 13, 1999 | CONSTRUCTION #MTF02FE | DOB VIOLATION - ACTIVE |
| Jul 13, 1999 | CONSTRUCTION #MTF01FE | DOB VIOLATION - ACTIVE |
| Mar 16, 1999 | LOCAL LAW 62/91 - BOILERS #00432 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Jul 30, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jul 30, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jul 8, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jul 8, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jun 15, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jun 15, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jun 15, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jun 15, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jun 15, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jun 15, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jun 15, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jun 15, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jun 15, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 3) | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jan 1, 2009 | Boiler LL6291 | Active |
| Jan 1, 2009 | Boiler LL6291 | Active |
| Jan 3, 2008 | Boiler LL6291 | Active |
| Jan 3, 2008 | Boiler LL6291 | Active |
| Jan 19, 2007 | Boiler LL6291 | Active |
| Jan 19, 2007 | Boiler LL6291 | Active |
| Jan 6, 2006 | Boiler LL6291 | Active |
| Jan 6, 2006 | Boiler LL6291 | Active |
| Jan 31, 2005 | Boiler LL6291 | Active |
| Jan 31, 2005 | Boiler LL6291 | Active |
| Mar 19, 2003 | Boiler LL6291 | Active |
| Mar 26, 2002 | Boiler LL6291 | Active |
| Feb 27, 2001 | Boiler LL6291 | Active |
| Feb 7, 2000 | Boiler LL6291 | Active |
| Mar 16, 1999 | Boiler LL6291 | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Nov 22, 2024 | I | §27-2107 ADM CODE OWNER FAILED TO FILE A VALID REGISTRATION STATEMENT WITH THE DEPARTMENT AS REQUIRED BY ADM CODE §27-2097 AND IS THEREFORE SUBJECT TO CIVIL PENALTIES, PROHIBITED FROM CERTIFYING VIOLATIONS, AND DENIED THE RIGHT TO RECOVER POSSESSION OF PREMISES FOR NONPAYMENT OF RENT UNTIL A VALID R | — |
| Nov 17, 2025 | I | §27-2107 ADM CODE OWNER FAILED TO FILE A VALID REGISTRATION STATEMENT WITH THE DEPARTMENT AS REQUIRED BY ADM CODE §27-2097 AND IS THEREFORE SUBJECT TO CIVIL PENALTIES, PROHIBITED FROM CERTIFYING VIOLATIONS, AND DENIED THE RIGHT TO RECOVER POSSESSION OF PREMISES FOR NONPAYMENT OF RENT UNTIL A VALID R | — |
| May 19, 2026 | B | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE SPRING BALANCE AT 4TH WINDOW FROM WEST AT NORTH WALL AT PUBLIC HALL, 4th STORY | Jun 23, 2026 |
| May 19, 2026 | B | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE SPRING BALANCE AT 8TH WINDOW FROM NORTH AT EAST WALL AT PUBLIC HALL, 4th STORY | Jun 23, 2026 |
| May 19, 2026 | A | § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT THE CEILING AT PUBLIC HALL, 4th STORY | Aug 22, 2026 |
| May 19, 2026 | B | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE FIRE RETARDANT MATERIAL AT CEILING AT PUBLIC HALL, 4th STORY | Jun 23, 2026 |
| May 19, 2026 | C | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE PORCELAIN ENAMEL WASH BASIN 1ST FROM WEST AT COMMUNITY BATHROOM, 4th STORY | May 25, 2026 |
| May 19, 2026 | A | § 27-2011 ADM CODE CLEANSE TO THE SATISFACTION OF THIS DEPARTMENT THE CERAMIC TILE FLOOR AT COMMUNITY BATHROOM, 4th STORY | Aug 22, 2026 |
| May 19, 2026 | C | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE WOOD FLOOR ''MISSING APPROX 12 SQ FEET AT B-ROOM 61'' LOCATED AT B-ROOM, 3rd STORY, 2nd B-ROOM FROM NORTH AT EAST | May 25, 2026 |
| May 19, 2026 | A | § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT THE CEILING AT COMMUNITY BATHROOM, 4th STORY | Aug 22, 2026 |
| May 19, 2026 | B | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE FIRE RETARDANT MATERIAL AT CEILING AT COMMUNITY BATHROOM, 4th STORY | Jun 23, 2026 |
| May 19, 2026 | B | § 27-2005 ADM CODE & 309 M/D LAW ABATE THE NUISANCE CONSISTING OF WALLS ERECTED WITH SHEETROCK AND STUDS OBSTRUCTION EGRESS AT FIRE ESCAPE AT BUILDING FRONT AT PUBLIC HALL, 3rd STORY | Jun 23, 2026 |
| May 19, 2026 | C | § 27-2037, 2038 HMC: PROVIDE A SAFE AND ADEQUATE SUPPLY OF ELECTRIC SERVICE TO THE FIXTURES AT CEILING AT COMMUNITY BATHROOM, 4th STORY | May 25, 2026 |
| May 12, 2026 | B | Apt 189 · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR AT NORTH WALL IN THE ROOM LOCATED AT B-ROOM 189, 5th STORY, 2nd B-ROOM FROM WEST AT NORTH | Jun 16, 2026 |
| May 12, 2026 | C | Apt 97 · § 27-2005, 2006, 2037 HMC: PROPERLY REPAIR AND ABATE UNSAFE ELECTRIC WIRING CONDITION CONSISTING OF EXOPESED ELECTRIC WIRES IN THE ROOM LOCATED AT B-ROOM 97, 4th STORY, 2nd B-ROOM FROM WEST AT NORTH | May 18, 2026 |
| May 12, 2026 | C | Apt 80 · § 27-2005, 27-2007, 27-2041.1 HMC, §238, § 309; § 107 (2) ( C) MDL AND 28 RCNY §25-171: REPLACE OR REPAIR THE SELF-CLOSING DOORS THAT IS MISSING OR DEFECTIVE DOOR AT ENTRANCE IN THE ROOM LOCATED AT B-ROOM 80, 3rd STORY, 8th B-ROOM FROM EAST AT SOUTH | May 26, 2026 |
| May 4, 2026 | B | § 27-2005, 2006, 2037 HMC: PROPERLY REPAIR AND ABATE UNSAFE ELECTRIC WIRING CONDITION CONSISTING OF LIGHT FIXTURES HANGING FROM EXPOSED WIRING AT CEILING THROUGHOUT OPEN AREAS AT 4TH AND 5TH STORIES | Jun 8, 2026 |
| Apr 29, 2026 | A | (A) § HMC:FILE ANNUAL BEDBUG REPORT IN ACCORDANCE WITH HPD RULE AS DESCRIBED ON THE BACK OF THIS NOTICE OF VIOLATION OR AS DESCRIBED ON HPDS WEBSITE, WWW.NYC.GOV\HPD, SEARCH BED BUGS. | Aug 2, 2026 |
| Apr 17, 2026 | C | § 27-2005 ADM CODE FIRE ESCAPE DEFECTIVE. REPLACE WITH NEW THE BROKEN, DEFECTIVE AND/OR MISSING KNEE BRACE (SUPPORT BRACKET) UNDER 2ND STORY BALCONY AT BUILDING FRONT AT FIRE ESCAPE | Apr 23, 2026 |
| Apr 17, 2026 | C | § 12 M/D LAW DISCONTINUE THE STORAGE OF COMBUSTIBLE MATERIAL CONSISTING ON OF AN EXCESSIVE AMOUNT OF BOXES AND A PROPANE TANK AT BOILER ROOM | Apr 23, 2026 |
| Apr 17, 2026 | C | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE FIRE RETARDANT MATERIAL AT CEILING AT COMMUNITY BATHROOM, 4th STORY | Apr 23, 2026 |
| Mar 23, 2026 | C | Apt 81 · § 27-2029 ADM CODE PROVIDE AN ADEQUATE SUPPLY OF HEAT FOR THE APARTMENT IN THE 1st ROOM FROM NORTH LOCATED AT B-ROOM 81, 3rd STORY, 1st B-ROOM FROM EAST AT SOUTH | Mar 20, 2026 |
| Mar 23, 2026 | C | Apt 189 · § 27-2029 ADM CODE PROVIDE AN ADEQUATE SUPPLY OF HEAT FOR THE APARTMENT IN THE 1st ROOM FROM NORTH LOCATED AT B-ROOM 189, 5th STORY, 3rd B-ROOM FROM WEST AT NORTH | Mar 20, 2026 |
| Mar 23, 2026 | C | § 27-2033 ADM CODE PROVIDE READY ACCESS TO BUILDINGS HEATING SYSTEM DOOR LEADING TO BOILER ROOM AT BASEMENT LOCKED | Mar 29, 2026 |
| Mar 16, 2026 | C | Apt 189 · § 27-2029 ADM CODE PROVIDE AN ADEQUATE SUPPLY OF HEAT FOR THE APARTMENT IN THE 1st ROOM FROM NORTH LOCATED AT B-ROOM 189, 5th STORY, 2nd B-ROOM FROM EAST AT SOUTH | Mar 16, 2026 |
| Sep 23, 2025 | A | § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT AT CEILING AT COMMUNITY BATHROOM, 5th STORY | Dec 27, 2025 |
| Sep 23, 2025 | C | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE FIRE RETARDANT MATERIAL AT CEILING AT COMMUNITY BATHROOM, 3rd STORY | Sep 29, 2025 |
| Sep 23, 2025 | B | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE FIRE RETARDANT MATERIAL AT ALL WALLS AT PUBLIC HALL, 4th STORY | Oct 28, 2025 |
| Sep 23, 2025 | A | § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT AT CEILING AT COMMUNITY BATHROOM, 4th STORY | Dec 27, 2025 |
| Sep 23, 2025 | B | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE FIRE RETARDANT MATERIAL AT SOUTH WALL AT PUBLIC HALL STAIRS, 5th STORY | Oct 28, 2025 |
| Sep 23, 2025 | A | § 27-2011 ADM CODE CLEANSE TO THE SATISFACTION OF THIS DEPARTMENT THE FLOOR AT PUBLIC HALL, 5th STORY | Dec 27, 2025 |
| Sep 23, 2025 | C | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE VINYL FLOOR TILES AT PUBLIC HALL, 3rd STORY | Sep 29, 2025 |
| Sep 23, 2025 | B | § 27-2026 ADM CODE REPAIR THE FLUSHING APPARATUS AND MAINTAIN SAME SO AS TO FLUSH EFFECTIVELY THE WATER CLOSET .. AT COMMUNITY BATHROOM, 5th STORY | Oct 28, 2025 |
| Sep 23, 2025 | B | § 27-2026 ADM CODE REPAIR THE LEAKY AND/OR DEFECTIVE FAUCETS AT WASH BASIN AT COMMUNITY BATHROOM, 5th STORY | Oct 28, 2025 |
| Sep 23, 2025 | C | 567 (C) § 27-2017, 27-2017.1, 27-2017.4, 27-2017.5, 27-2017.8, 27-2019, 27-2021 HMC: ABATE THE NUISANCE CONSISTING OF EVIDENCE OF RATS AND ALL UNDERLYING CAUSES CREATING THE PEST INFESTATIONS, BY USING INTEGRATED PEST MANAGEMENT (IPM), ELIMINATE ALL BURROW ENTRY AND PASSAGEWAYS, PEST NESTS, HOLES, G | Oct 19, 2025 |
| Sep 23, 2025 | A | § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT AT SOUTH WALL AT PUBLIC HALL STAIRS, 5th STORY | Dec 27, 2025 |
| Sep 23, 2025 | C | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE FIRE RETARDANT MATERIAL AT CEILING AT COMMUNITY BATHROOM, 4th STORY | Sep 29, 2025 |
| Sep 23, 2025 | B | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE FIRE RETARDANT MATERIAL AT ALL WALLS AT COMMUNITY BATHROOM, 4th STORY | Oct 28, 2025 |
| Sep 23, 2025 | A | § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT ALL WALLS AT COMMUNITY BATHROOM, 4th STORY | Dec 27, 2025 |
| Sep 23, 2025 | A | § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT AT ALL WALLS AT PUBLIC HALL, 4th STORY | Dec 27, 2025 |
| Sep 23, 2025 | C | 567 (C) § 27-2017, 27-2017.1, 27-2017.4, 27-2017.5, 27-2017.8, 27-2019, 27-2021 HMC: ABATE THE NUISANCE CONSISTING OF EVIDENCE OF RATS AND ALL UNDERLYING CAUSES CREATING THE PEST INFESTATIONS, BY USING INTEGRATED PEST MANAGEMENT (IPM), ELIMINATE ALL BURROW ENTRY AND PASSAGEWAYS, PEST NESTS, HOLES, G | Oct 19, 2025 |
| Sep 23, 2025 | A | § 27-2011 ADM CODE CLEANSE TO THE SATISFACTION OF THIS DEPARTMENT THE FLOORS AT PUBLIC HALL, 4th STORY | Dec 27, 2025 |
| Sep 23, 2025 | A | § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT AT CEILING AT COMMUNITY BATHROOM, 3rd STORY | Dec 27, 2025 |
| Sep 8, 2025 | B | § 27-2017.3 HMC: TRACE AND REPAIR THE SOURCE AND ABATE THE VISIBLE MOLD CONDITION... LESS THAN 10 SQ FEET AT CEILING AT COMMUNITY BATHROOM, 5th STORY ORIGINAL VIOLATION 17883367 ISSUED 30-APR-25 HAS BEEN UPGRADED TO CLASS B PER ADMINISTRATIVE CODE 27-2017.3a(3)(a) or (b). | Oct 13, 2025 |
| Aug 5, 2025 | B | § 27-2026 ADM CODE REPAIR THE LEAKY AND/OR DEFECTIVE FAUCETS AT WASH BASIN SINK AT COMMUNITY BATHROOM, 4th STORY | Sep 9, 2025 |
| Aug 5, 2025 | C | § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR AT CEILING AT COMMUNITY BATHROOM, 3rd STORY | Aug 11, 2025 |
| Aug 5, 2025 | C | § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR AT CEILING AT COMMUNITY BATHROOM, 4th STORY | Aug 11, 2025 |
| Jun 10, 2025 | C | § 27-2033 ADM CODE PROVIDE READY ACCESS TO BUILDINGS HEATING SYSTEM DOOR LOCK TO BASEMENT | Jun 16, 2025 |
| Jun 5, 2025 | C | 567 (C) § 27-2017, 27-2017.1, 27-2017.4, 27-2017.5, 27-2017.8, 27-2019, 27-2021 HMC: ABATE THE NUISANCE CONSISTING OF EVIDENCE OF RATS AND ALL UNDERLYING CAUSES CREATING THE PEST INFESTATIONS, BY USING INTEGRATED PEST MANAGEMENT (IPM), ELIMINATE ALL BURROW ENTRY AND PASSAGEWAYS, PEST NESTS, HOLES, G | Jul 1, 2025 |
| Jun 5, 2025 | A | § 27-2011 ADM CODE CLEANSE TO THE SATISFACTION OF THIS DEPARTMENT THE ... AT COMMUNITY BATHROOM, 4th STORY | Sep 8, 2025 |
| Jun 5, 2025 | B | § 27-2026 ADM CODE REPAIR THE FLUSHING APPARATUS AND MAINTAIN SAME SO AS TO FLUSH EFFECTIVELY THE WATER CLOSET AT ALL WATER CLOSETS AT COMMUNITY BATHROOM, 4th STORY | Jul 10, 2025 |
| Jun 4, 2025 | A | (A) § HMC:FILE ANNUAL BEDBUG REPORT IN ACCORDANCE WITH HPD RULE AS DESCRIBED ON THE BACK OF THIS NOTICE OF VIOLATION OR AS DESCRIBED ON HPDS WEBSITE, WWW.NYC.GOV\HPD, SEARCH BED BUGS. | Sep 7, 2025 |
| May 9, 2025 | A | § 27-2011 ADM CODE CLEANSE TO THE SATISFACTION OF THIS DEPARTMENT THE FLOOR AT PUBLIC HALL, 4th STORY | Aug 12, 2025 |
| May 9, 2025 | C | § 27-2005 ADM CODE FIRE ESCAPE DEFECTIVE. PROPERLY SECURE BOTTOM FACIA PLATE AT STACK AT BUILDING FRONT AT FIRE ESCAPE, 2nd STORY | May 15, 2025 |
| May 9, 2025 | A | § 27-2011 ADM CODE CLEANSE TO THE SATISFACTION OF THIS DEPARTMENT THE FLOOR AT PUBLIC HALL, 3rd STORY | Aug 12, 2025 |
| Feb 24, 2025 | A | § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT AT ALL WALLS AND CEILING AT COMMUNITY BATHROOM, 3rd STORY | May 30, 2025 |
| Feb 24, 2025 | B | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE FIRE RETARDENTS MATERIALS AT ALL WALLS AND CEILING AT COMMUNITY BATHROOM, 3rd STORY | Mar 31, 2025 |
| Feb 24, 2025 | C | § 27-2005 ADM CODE FIRE ESCAPE DEFECTIVE. PROPERLY SECURE AT FRONT BOTTOM FACIA PLATE AT FIRE ESCAPE, 2nd STORY | Mar 2, 2025 |
| Apr 1, 2024 | A | (A) § HMC:FILE ANNUAL BEDBUG REPORT IN ACCORDANCE WITH HPD RULE AS DESCRIBED ON THE BACK OF THIS NOTICE OF VIOLATION OR AS DESCRIBED ON HPDS WEBSITE, WWW.NYC.GOV\HPD, SEARCH BED BUGS. | Jul 5, 2024 |
| Nov 2, 2023 | C | Apt 40 · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES LOCATED AT B-ROOM 40, 3rd STORY | Nov 28, 2023 |
Showing 60 of 79. Full list on the agency site.
| Date | Source | What | Now |
|---|---|---|---|
| Sep 18, 2026 | DOB | IMMEDIATE EMERGENCY: REMEDY: INSTALLATION OF SIDEWALK SHED AT EXPO 2 (LOCATED AT 237-241 GRAND.STREET) APPROXIMATELY 75 LINEAR FEET + ADDITIONAL.ADJACENT PROPERTY 5 LINEAR.FEET TOTAL = 80 LINEAR FEET | Closed |
| Sep 17, 2026 | DOB | CONSTRUCTION: OBSERVED PARAPET WALL AT ROOF CORNER OF EXPO 2/3 WITH LARGE CRACK AND ALSO MUTIPLE CHIMNEYS AT EXPO 2 WITH MISSING MORTAR. CONDTIONS ARE EXISITNG OVER PUBLIC SIDEWALK AND OVER STORES CAUSING OVERHEAD HAZARD. ENGINEERS REPORT FOR STRUCTURAL STABILITY REQUIRED. | Open |
| Sep 17, 2026 | ECB | Construction: AT TIME OF INSPECTION, OBSERVED PARAPET WALL WITH LARGE CRACK ON CORNER OF EXPO 2 AT EXPO 3 SIDE. MULTIPLE CHIMNEY STACK ALSO MISSING MORTAR HOLDING THE BRICKS TOGETHER. AREA OF PARAPET/CHIMNEYS OVERHANGS PUBLI | Open |
| Jul 30, 2026 | DOB Safety | AEUHAZ: | Open |
| Jul 30, 2026 | DOB Safety | AEUHAZ: | Open |
| Jul 8, 2026 | DOB Safety | AEUHAZ: | Open |
| Jul 8, 2026 | DOB Safety | AEUHAZ: | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 26, 2026, 11:02 AM ET. BBL 1003040016.