Bronx · Block 3055 · Lot 25 · 10458

2369 Lorillard Place

2 floors · 5,000 sq ft · built 1931 · class F5 · owner of record: 2369 Lorillard, Llc

6open violations
$17,500ECB/OATH penalties owed
0HPD class C (immediately hazardous)
69dto Gas piping inspection (2026 cycle)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Gas piping inspection (2026 cycle) Likely applies
Local Law 152 · During 2026
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 6 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2026
in 69 days
Due this year
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 69 days
Keep the report on file (not filed with DOB)

Open violations

ECB / OATH (6) · $17,500 owed
IssuedViolationHearingBalance
Jul 31, 2026Construction CLASS - 2
GENERAL CONTRACTOR FAILED TO FILE CERTIFICATE OF CORRECTION WITH THE DOB. NO CORRECTIVE MEASURES ON RECORD FOR VIOLATION# 03955089H ISSUED 6.05.2026. COMPLY WITH CODE FILE A CERTIFICATE OF CORRECTION...
#39557375H
Nov 20, 2026
PENDING
$1,250
Jun 5, 2026Construction CLASS - 2
I OBSERVED ACTIVE DEMOLITION WORK IN PROGRESS JOBSITE FAIL TO PROVIDE OVERHEAD PROTECTION FOR ADJACENT PROPERTIES EXP#1-2 CONNER, CONCRETE PAVEMENT EXP#2, EXP#2-3 CONNER, EXP#3-4 NO CAZ IN PLACE AND 4-1 CONNER
#39555091R
Feb 26, 2027
PENDING
$5,000
Jun 5, 2026Unknown CLASS - 2
AT THE TIME OF INSPECTION, OF A 2-STORY BUILDING FOR FULL DEMOLITION WAS ACTIVELY BEING DEMOLISHED. WINDOWS AND GLASS WERE OBSERVED REMAINING IN THE STRUCTURE WHILE DEMOLITION OPERATIONS WERE ONGOING. CONTRARY
#39555090P
Feb 26, 2027
PENDING
$2,500
Jun 5, 2026Construction CLASS - 2
I OBSERVED WORKERS AT EXP#3 CONNER PREFORMING DEMOLITION ON EXITING WALL, WORKERS WAS USING PIPE SCAFFOLDING AND STANDING ON TOP, PIPE SCAFFOLDING NOT MAINTAIN AS PER BC 3314.1 WORKER WAS APPROX. 10 FT IN AIR W
#39555092Z
Feb 26, 2027
PENDING
$5,000
Jun 5, 2026Site Safety CLASS - 1
A 2-STORY BUILDING IS UNDERGOING FULL DEMOLITION WITH WORKERS ACTIVELY, UPON REQUESTING WORKERS ONSITE FOR DOCUMENT TO KEPT ONSITE PRE SHIFT MEETING, ORIENTATION, CONSTRUCTION SUPERINTENDENT LOG AND APPROVED DO
#39555089H
Feb 26, 2027
$2,500
Jun 2, 2026Construction CLASS - 2
FULL DEMOLITION OF A 2 STORY BUILDING CLOSED SITE CONSTRUCTION JOBSITE FENCE IN PLACE 8 FT IN HEIGHT PERMIT# X01385717. BUILDING PARTIALLY DEMOLISHED. OBSERVED MISSING JOBSITE INFORMATION PANEL ON FENCE AT EXP#
#39554875K
Feb 5, 2027
PENDING
$1,250
DOB (0)

None open.

DOB NOW Safety (1)
IssuedViolationStatus
Oct 31, 2025Gas Piping - LL152 FTF-PL-PER
Cycle 1, Sub-cycle C (premises is in Community District 6)
Active
HPD (0)

None open.

Issued in the last 120 days

DateSourceWhatNow
Jul 31, 2026ECBConstruction: GENERAL CONTRACTOR FAILED TO FILE CERTIFICATE OF CORRECTION WITH THE DOB. NO CORRECTIVE MEASURES ON RECORD FOR VIOLATION# 03955089H ISSUED 6.05.2026. COMPLY WITH CODE FILE A CERTIFICATE OF CORRECTION...Open

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Oct 23, 2026, 11:40 AM ET. BBL 2030550025.

Look up another building