Manhattan · Block 875 · Lot 1 · 10003

235 Park Avenue South

12 floors · 67,376 sq ft · built 1921 · class O6 · owner of record: 235 Park Avenue South, Llc

42open violations
$10,000ECB/OATH penalties owed
0HPD class C (immediately hazardous)
42dto Annual boiler inspection (1 boiler)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 42 days
Keep the report on file (not filed with DOB)
Annual boiler inspection (1 boiler) Applies
Boiler inspection · By December 31 each year
What this is

Boilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-11-21 (Accepted). Agency page

Dec 31, 2026
in 42 days
1 of 1 without an accepted 2026 report yet
Facade inspection report (Cycle 10A) Applies
Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027
What this is

Buildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $76,500 in late-filing or failure-to-file penalties. Agency page

Feb 21, 2027
in 94 days
No Cycle 10 report on record yet
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 67,376 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 163 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 163 days
Annual filing
Gas piping inspection (2029 cycle) Likely applies
Local Law 152 · During 2029
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 5 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2029
in 1138 days
Next cycle year 2029
Energy audit and retro-commissioning (2035) Likely applies
Local Law 87 · Calendar year 2035
What this is

Buildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 875). Agency page

Dec 31, 2035
in 3329 days
Next due 2035

Open violations

ECB / OATH (3) · $10,000 owed
IssuedViolationHearingBalance
Jun 17, 2024Construction CLASS - 2
A.C. 27-929 FAILURE TO COMPLETE INSTALLATION OF FULL SYSTEM OF AUTOMATIC SPRINKLERS & FILE FINAL SPRINKLER REPORT PREPARED BY REGISTERED DESIGN PROFESSIONAL IN OFFICE BUILDING 100 FEET OR MORE IN HEIGHT IN EXIS
#37028822Y
Oct 10, 2024
DEFAULT
$10,000
Feb 28, 2023Construction CLASS - 2
27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN HE
#37025420H
Jun 29, 2023
DEFAULT
$0
Dec 10, 2020Construction CLASS - 2
SEC. 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OFAUTOMATIC SPRINKLERS & FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BLDG 100 FEET OR MORE IN HEIG
#37020580Y
Jun 9, 2022
ADMIT/IN-VIO
$0
DOB (13)
IssuedViolationStatus
Sep 17, 2021ELEVATOR

#9027/707898
DOB VIOLATION - ACTIVE
Sep 9, 2020ELEVATOR

#9027/688208
DOB VIOLATION - ACTIVE
Sep 9, 2020ELEVATOR

#9027/688212
DOB VIOLATION - ACTIVE
Sep 9, 2020ELEVATOR

#9027/688210
DOB VIOLATION - ACTIVE
Sep 9, 2020ELEVATOR

#9027/688209
DOB VIOLATION - ACTIVE
Nov 12, 2019SPRINKLER
FAILED TO FILE FINAL SPRINKLER REPORT BY JULY 1, 2019
#NRF00095
DOB VIOLATION - ACTIVE
Sep 6, 2019(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
#01454
DOB VIOLATION - ACTIVE
Sep 6, 2019(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST
#01455
DOB VIOLATION - ACTIVE
Aug 13, 2019ELEVATOR

#9027/660357
DOB VIOLATION - ACTIVE
Apr 6, 2018LOW PRESSURE BOILER
VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT
#02813
DOB VIOLATION - ACTIVE
Aug 15, 2012ELEVATOR

#ACC101137
DOB VIOLATION - ACTIVE
Jan 13, 1997LOCAL LAW 10/81 - ELEVATOR

#00716
DOB VIOLATION - ACTIVE
May 7, 1992CONSTRUCTION

#C14SS05
DOB VIOLATION - ACTIVE
DOB NOW Safety (26)
IssuedViolationStatus
Oct 29, 2026Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2025 Cat1 Test Affirmation of Correction
Active
Oct 2, 2026Elevators FTF-VT-CAT1-CO
Violation Issued-Failure To File 2025 Cat1 Test Report
Active
Aug 24, 2026GHG Emissions - LL97 FTX-EN-LL97320
Active
Oct 10, 2025Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction
Active
Oct 10, 2025Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction
Active
Oct 11, 2024Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction
Active
Oct 11, 2024Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction
Active
Oct 11, 2024Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction
Active
Oct 11, 2024Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2019 Cat1 Test Affirmation of Correction
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2021 Cat1 Test Affirmation of Correction
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2019 Cat1 Test Affirmation of Correction
Active
Oct 2, 2023Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction
Active
Oct 2, 2023Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction
Active
Nov 12, 2019Sprinklers FTF-SP-FINAL
Active
Sep 6, 2019Elevators ACC1
Active
Sep 6, 2019Elevators ACC1
Active
Apr 6, 2018Boiler LBLVIO
VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT
Active
Aug 15, 2012Elevators E
Active
Aug 15, 2012Elevators E
Active
Aug 15, 2012Elevators E
Active
Aug 15, 2012Elevators E
Active
Aug 15, 2012Elevators E
Active
Aug 15, 2012Elevators E
Active
HPD (0)

None open.

Issued in the last 120 days

DateSourceWhatNow
Oct 29, 2026DOB SafetyElevators: Violation Issued-Failure To File 2025 Cat1 Test Affirmation of CorrectionOpen
Oct 2, 2026DOB SafetyElevators: Violation Issued-Failure To File 2025 Cat1 Test ReportOpen
Aug 24, 2026DOB SafetyGHG Emissions - LL97: Open

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Nov 19, 2026, 2:17 AM ET. BBL 1008750001.

Look up another building