Manhattan · Block 1319 · Lot 16 · 10017

235 East 45 Street

16 floors · 200,311 sq ft · built 1929 · class O3 · owner of record: Hearst Communications

18open violations
$10,000ECB/OATH penalties owed
0HPD class C (immediately hazardous)
43dto Gas piping inspection (2026 cycle)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Gas piping inspection (2026 cycle) Likely applies
Local Law 152 · During 2026
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 6 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2026
in 43 days
Due this year
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 43 days
Keep the report on file (not filed with DOB)
Facade inspection report (Cycle 10A) Applies
Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027
What this is

Buildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $900 in late-filing or failure-to-file penalties. Agency page

Feb 21, 2027
in 95 days
No Cycle 10 report on record yet
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 200,311 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 164 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 164 days
Annual filing
Energy audit and retro-commissioning (2029) Likely applies
Local Law 87 · Calendar year 2029
What this is

Buildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 1319). Agency page

Dec 31, 2029
in 1139 days
Next due 2029
Annual boiler inspection (2 boilers) Applies
Boiler inspection · By December 31 each year
What this is

Boilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-04-15 (Accepted). Agency page

On file2026 reports accepted

Open violations

ECB / OATH (4) · $10,000 owed
IssuedViolationHearingBalance
Nov 18, 2024Construction CLASS - 1
FAILURE TO MAINTAIN EXTERIOR BUILDING FACADE AND APPURTENANCES.NOTE:ATTIME OF INSPECTION OBSERVED AT EXPOSURE#1(SOUTH ELEVATION)LEANING STEEL FENCE.REM:MAINTAIN EXTERIOR BUILDING FACADE AND APPURTENANCES PROVID
#35686823H
Jan 23, 2025
IN VIOLATION
$2,500
Mar 14, 2024Construction CLASS - 1
UNLAWFUL ACTS.FAILURE TO COMPLY WITH COMMISSIONER'S ORDER.NOTE:AT THE TIME OF INSPECTION OBSERVED RESPONDENT FAILURE TO COMPLY WITH PREVIOUSVIOLATION#35675590M,35675591Y DATED 12/19/2023 AND DOB VIOLATION#12192
#35682246Z
Nov 14, 2024
IN VIOLATION
$2,500
Dec 19, 2023Construction CLASS - 1
28-323.8 AND RCVNY-103-13(5) FAILURE TO SECURE PUBLIC SAFTETY AND/OR MAKE THE BUILDINGS STRUCTURE AND APPURTENANCES CONFORM TO THE PREVIOUS OF THE ADMIN CODE AFTER UNSAFE NOTIFICATION FILLED-U.N.P.S.-M0002639 D
#35675591Y
Aug 1, 2024
IN VIOLATION
$2,500
Dec 19, 2023Construction CLASS - 1
28-323.1 FAILURE TO MAINTAIN PARKING STRUCTURE IN SAFE CONDITION: NOTE:-OBSERVED ON AN OCCUPIED PARKING STRUCTURE CONSISTING OF 3 LEVEL(CELLAR BELOW GL-L-1, AT GRADE L-2, AND ABOVE GL-3), SPALLING CONCRETE/EXPO
#35675590M
Aug 1, 2024
IN VIOLATION
$2,500
DOB (4)
IssuedViolationStatus
Nov 18, 2024CONSTRUCTION
EMERGENCY WORK ORDER DUE TO LEANING STEEL FENCY AT EXPOSURE #1 (SOUTH ELEV.) REMEDY: IMMEDIATELY TAKE & PROVIDE SAFETY MEASURES TO SECURE/ PROTECT THE PUBLIC & INSTALL PUBLIC PROTECTION AT EXP #1 (SOUTH ELEV.) MAKE IMMEDIATE REPAIRS UNDER SUPERVISION OF LICENSED PROFESSIONAL ALSO REMOVE/SECURE THE L
#FA0601AE
DOB VIOLATION - ACTIVE
Jul 10, 2024FAIL TO CERTIFY CLASS 1
FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
#00022
DOB VIOLATION - ACTIVE
Feb 21, 2024FAIL TO CERTIFY CLASS 1
FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION
#00015
DOB VIOLATION - ACTIVE
Dec 19, 2023CONSTRUCTION
EMERGENCY WORK ORDER(3 LEVELS(CELLAR L-1 @L-2 AND ABOVE GL L-3) SPALLING CONCRETE/EXPOSE REBAR, CRACK BEAM ANS SLAB @EVERY FLR@SEVERAL LOC.CAUSING IMMED HAZ TO VEHICULAR&PEDESTRIAN TRAFFIC,REQ.IMMED SAFETY MEASURES.REMEDY:RETAIN A NYS REG.DESIGN PROF.TO DIRECT&SUPERV.IMMED INSTALL SAFETY MEASURES RE
#LL10601MK
DOB VIOLATION - ACTIVE
DOB NOW Safety (11)
IssuedViolationStatus
Nov 6, 2026GHG Emissions - LL97 FTF-EN-LL97320
FAILURE TO FILE AN ANNUAL BUILDINGS EMISSIONS REPORT AS REQUIRED BY AD CODE SEC. 28-320.3.7 IN ACCORDANCE WITH 1 RCNY § 103-14.
Active
Apr 20, 2026GHG Emissions - LL97 FTF-EN-LL97320
Active
Aug 29, 2025Elevators FTF-VT-PER-CO
Violation Issued-Failure To File 2024 Periodic Inspection Report
Active
Dec 31, 2024Parking Structures FTC-PS-UNSAFE
Unsafe report of parking structures filed.
Active
Sep 11, 2024Elevators FTF-VT-PER-CO
Violation Issued-Failure To File 2023 Periodic Inspection Report
Active
Jul 10, 2024AEUHAZ FTC-AEU-HAZ
Active
Feb 21, 2024AEUHAZ FTC-AEU-HAZ
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction
Active
Aug 11, 2023Elevators FTF-VT-CAT1-CO
Violation Issued-Failure To File 2020 Cat1 Test Report
Active
Aug 11, 2023Elevators FTF-VT-CAT1-CO
Violation Issued-Failure To File 2020 Cat1 Test Report
Active
HPD (0)

None open.

Issued in the last 120 days

DateSourceWhatNow
Nov 6, 2026DOB SafetyGHG Emissions - LL97: FAILURE TO FILE AN ANNUAL BUILDINGS EMISSIONS REPORT AS REQUIRED BY AD CODE SEC. 28-320.3.7 IN ACCORDANCE WITH 1 RCNY § 103-14.Open

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Nov 18, 2026, 2:07 AM ET. BBL 1013190016.