15 floors · 198 apartments · 211,910 sq ft · built 1941 · class D4 · owner of record: Murray House Owners Corp
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 60 days | Keep the report on file (not filed with DOB) |
| Energy audit and retro-commissioning (2026) Likely applies Local Law 87 · Calendar year 2026 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 866). Agency page | Dec 31, 2026 in 60 days | Due this year |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 60 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 76 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 211,910 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 181 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 181 days | Annual filing |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 304 days | Registered through 2027-09-01 |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 5 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1156 days | Next cycle year 2029 |
| Annual boiler inspection (4 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-08-21 (Accepted). Agency page | On file | 2026 reports accepted |
| Facade inspection report (Cycle 10A) Applies Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $207,000 in late-filing or failure-to-file penalties. Agency page | On file | Cycle 10 filing on record: SAFE (2026-01-28) |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Apr 21, 2026 | Unknown CLASS - 1 ATOI OBSERVED COMMERCIAL SPACE, WITH NEWLY INSTALLED ELECTRICAL DEVICES WITHOUT ELECTRICAL PERMIT. PSWO FOR ELECTRICAL #OP-71-25-06371, OBTAIN PERMIT #39185514Y | Jun 25, 2026 DEFAULT | $6,250 |
| Jan 16, 2024 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 9A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL #902505. REMEDY: FILE ACCEPTABLE REPORT. #37026696N | Jun 6, 2024 IN VIOLATION | $1,250 |
| Jan 13, 2019 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.AT VARIOUS LOCATIONS WINDOW AIR CONDITIONS INSTALLED WITHOUT ADEQUATE SUPPORT BRACKETS AS REQUIRED.REPAIR/AND OR/REPLACE. #35375576L | May 9, 2019 STIPULATION/IN-VIO | $625 |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #02753 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #02754 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL LOW PRESSURE INSPECTION #02755 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL LOW PRESSURE INSPECTION #02756 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #04920 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #04921 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #24608 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #24609 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION #26467 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #04952 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #04953 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION #26466 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION #05974 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION #05973 | DOB VIOLATION - ACTIVE |
| Nov 8, 2019 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2017 INSPECTION REPORT #02786 | DOB VIOLATION - ACTIVE |
| Nov 8, 2019 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2017 INSPECTION REPORT #02787 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 2, 2026 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2025 Cat1 Test Report | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Aug 29, 2025 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2024 Cat1 Test Report | Active |
| Sep 23, 2024 | Boiler LBLVIO Violation Issued-Failure To File 2023 External Low Pressure Inspection Report | Active |
| Sep 23, 2024 | Boiler LBLVIO Violation Issued-Failure To File 2023 External Low Pressure Inspection Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2023 Cat1 Test Report | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2021 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2018 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2022 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-NJ Violation Issued-Failure To File 2020 Cat1 Test Report | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT | Active |
| Apr 25, 2023 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT | Active |
| Nov 8, 2019 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2017 INSPECTION REPORT | Active |
| Nov 8, 2019 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2017 INSPECTION REPORT | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Apr 2, 2025 | C | Apt 11F · § 27-2005, 2007 ADM CODE REMOVE THE ILLEGAL FASTENING HASP AND EYE LOCK READYTO PADLOCK AT DOOR (INTERIOR) IN THE ENTRANCE LOCATED AT APT 11F LOWER LEVEL, 11th STORY, 2nd APARTMENT FROM NORTH AT EAST | Apr 8, 2025 |
| Apr 2, 2025 | B | § 300, 301, 302, M/D LAW FILE PLANS AND OBTAIN A CERTIFICATE OF OCCUPANCY TO LEGALIZE THE FOLLOWING ALTERATION OR RESTORE PREMISES TO PRIOR LEGAL CONDITION PARTITIONS REMOVED WALL NORTHEAST MAKING PENTHOUSE E & PENTHOUSE D AS ONE APT CONTRARY TO C OF O. | May 7, 2025 |
| Apr 2, 2025 | B | Apt 3-0 · § 27-2026 ADM CODE REPAIR THE LEAKY AND/OR DEFECTIVE FAUCETS KITCHEN SINK 3 STY NORTHWEST APT 3-0. LOCATED AT APT 3-0 | May 7, 2025 |
| Apr 2, 2025 | B | § 27-2005 ADM CODE & 309 M/D LAW ABATE THE NUISANCE CONSISTING OF WATER PENETRATING NORTH WALL NORTH ROOM 15 STY NORTH APT PHE. | May 7, 2025 |
| Apr 2, 2025 | B | § 27-2005 ADM CODE & 309 M/D LAW ABATE THE NUISANCE CONSISTING OF WATER PENETRATING EAST WALL SOUTHEAST ROOM 15 STY NORTH APT PHE. | May 7, 2025 |
| Apr 2, 2025 | B | § 27-2005 ADM CODE & 309 M/D LAW ABATE THE NUISANCE CONSISTING OF TERRACE FLOOR PITCHING IN WARD CAUSING WATER TO PENETRATING NORTH ROOM 15 STY NORTH APT PHE. | May 7, 2025 |
| Apr 2, 2025 | B | Apt 11K · § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE CEMENT PLASTER CEILIGN NORTHWEST ROOM 11 STY NORTHEAST APT 11K , SECTION '' '' | May 7, 2025 |
| Apr 2, 2025 | B | Apt 11K · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR WALLS & CEILING NORTHWEST ROOM UPPER FLOOR 11 STY DUPLEX APT 11K. , SECTION '' '' | May 7, 2025 |
| Apr 2, 2025 | A | § 27-2046.1 HMC: POST A PROPER NOTICE OF CARBON MONOXIDE DETECTING DEVICE REQUIREMENTS, IN A FORM APPROVED BY THE COMMISSIONER, IN A COMMON AREA OF A CLASS A MULTIPLE DWELLING NEAR INSPECTION CERTIFICATE OR PROVIDE NOTICE TO TENANTS IN A PRIVATE DWELLING. AT PUBLIC HALL, 1st STORY | Jul 6, 2025 |
| Apr 2, 2025 | A | § 27-2005 HMC: POST, IN A FORM APPROVED BY THE COMMISSIONER, AND MAINTAIN A NOTICE IN A COMMON AREA OF THE BUILDING REGARDING THE PROCEDURES THAT SHOULD BE FOLLOWED WHEN A GAS LEAK IS SUSPECTED AT PUBLIC HALL, 1st STORY | Jul 6, 2025 |
| Apr 2, 2025 | A | § 27-2053 ADM CODE POST SIGN ON WALL OF ENTRANCE STORY BEARING NAME, ADDRESS INCLUDING APARTMENT NUMBER IF ANY, AND TELEPHONE NUMBER OF SUPERINTENDENT, JANITOR OR HOUSEKEEPER. AT PUBLIC HALL, 1st STORY | Jul 6, 2025 |
| Apr 2, 2025 | A | Apt 2E · § 300 M/D LAW FILE PLANS AND APPLICATION AND LEGALIZE THE FOLLOWING ALTERATION OR RESTORE TO THE LEGAL CONDITION EXISTING PRIOR TO THE MAKING OF SAID ALTERATION PARTITION SHEETROCK WALL FROM FLOOR TO CEILING IN THE 2nd ROOM FROM EAST AT NORTH LOCATED AT APT 2E, 2nd STORY, 3rd APARTMENT FROM NORTH AT | Jul 6, 2025 |
| Apr 2, 2025 | C | Apt 11K · § 27-2005 ADM CODE REPAIR THE ROOF SO THAT IT WILL NOT LEAK TERRACE OVER NORTHWEST ROOM 11 STY NORTHEAST APT 11K ER1 , SECTION '' '' | Apr 8, 2025 |
| Apr 2, 2025 | C | Apt 30 · § 27-2005 ADM CODE & 309 M/D LAW ABATE THE NUISANCE CONSISTING OF CASCADING LEAK AT BATHTUB FAUCET 3 STY NORTHWEST APT 30. , SECTION '' '' | Apr 8, 2025 |
| Apr 2, 2025 | C | Apt 11K · § 27-2005 ADM CODE & 309 M/D LAW ABATE THE NUISANCE CONSISTING OF CONCEALED WATER LEAK AT CEILING NORTHWEST ROOM UPPER FLOOR 11 STY DUPLEX APT 11K. , SECTION '' '' | Apr 8, 2025 |
| Apr 10, 2019 | C | Apt 3L · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF MICE IN THE ENTIRE APARTMENT LOCATED AT APT 3L, 3rd STORY, 1st APARTMENT FROM EAST AT SOUTH , SECTION AT NORTH | May 1, 2019 |
| Date | Source | What | Now |
|---|---|---|---|
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Report | Open |