8 floors · 40 apartments · 26,684 sq ft · built 1974 · class R4 · owner of record: The 215 East 81st Street Condominium
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 8 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 43 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 43 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 43 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 59 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 26,684 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 164 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 164 days | Annual filing |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 287 days | Registered through 2027-09-01 |
| Facade inspection report (Cycle 10B) Applies Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. Agency page | Feb 21, 2028 in 460 days | No Cycle 10 report on record yet |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-06-12 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Aug 24, 2011 | Unknown CLASS - 2 FAILURE TO COMPLY W/COMMISSIONER'S ORDER TO FILE A C/C W/THE DOB RESPONDENT FAILED TO COMPLY W/THE COMMISSIONER'S ORDER TO CORRECT THE VIOLATION CONDITIONS AND FILE A C/C PURSUANT TO SECTION 28-204.2 FOR NOV #34923847M | Feb 9, 2012 IN VIOLATION | $0 |
| May 26, 2011 | Unknown CLASS - 1 (MISC)BC1003.2THE MEANS OF EGRESS SMALL HAVE A CEILING HEIGHT OF NOT LESS THAN '-6"NOTED:BLDG HAVING @ PENTHOUSE TOP FLR STAIRCASE LANDING/CORRIDOR CEILING HEIGHT 80INCHES & CORRIDOR ON GROUND/LOBBY LEVEL78 1/2 #34907390L | Jul 14, 2011 DEFAULT | $0 |
| Apr 26, 2011 | Construction CLASS - 1 C/O #74637 DATED 6/05/74 ILLEGAL OCCUPANCY NOTED LOBBY NOT INDICATED ON C/O NEW LAUNDRY ROOM IN CELLAR LVL BOILER ROOM METER ROOM PUMP ROOM REFUSE COLLECTION ROOM LOCATED IN SUBCELLAR EXTENSION VERTICAL OVER PE #34907219L | Aug 4, 2011 IN VIOLATION | $0 |
| Jan 5, 2010 | Construction CLASS - 1 OCCUPANCY CONTRARY TO THAT ALLOWED BY COFO#74637 1-SUBCELLAR NOT SHOWING OR C/O OCCUPIED AS A BOILER,REFUSE & COMPACTOR ROOMS.2-NEW LAUNDRY ROOM IN CELLAR 3-EXTENSION OF PENHOUSE ABOVE & MECHANICAL ROOM ABOVE I #34754471Z | Aug 26, 2010 IN VIOLATION | $0 |
| Jan 5, 2010 | Construction CLASS - 1 OCCUPANCY CONTRARY TO THAT ALLOWED BY C/O #74637. 1) SUB CELLAR NOT SHOWING OR C/O OCCUPIED AS A BOILER, REFUSE AND COMPACTOR ROOMS. 2) NEW LAUNDRY ROOM IN CELLAR. 3) EXTENSION OF PENTHOUSE ABOVE AND MECHANICAL #34838103N | May 12, 2011 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Oct 26, 2020 | CONSTRUCTION BOROUGH COMMISSIONER HAS ORDERED A SWO FOR APPLICATION# 106640408 DUE TO APPLICANT WITHDRAWAL. STOP ALL WORK AND MAKE SITE SAFE. #20-01464 | DOB VIOLATION - ACTIVE |
| Jan 6, 2010 | IMMEDIATE EMERGENCY #1389 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Nov 23, 2009 | C | Apt 4C · SECTION 27-2005 ADM CODE & 309 M/D LAW ABATE THE NUISANCE CONSISTING OF NO ELECTRICITY SUPPLY TO FIXTURE IN THE ENTIRE APARTMENT LOCATED AT APT 4C, 4th STORY, 1st APARTMENT FROM SOUTH AT WEST | Nov 29, 2009 |
| May 11, 2006 | A | Apt 7B · SECTION 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR EAST AND SOUTH WALLS IN THE 1st ROOM FROM NORTH LOCATED AT APT 7B UPPER LEVEL, 7th STORY, 4th APARTMENT FROM EAST AT SOUTH | Aug 19, 2006 |
| May 11, 2006 | A | Apt 7B · SECTION 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR NORTH WALL IN THE 2nd ROOM FROM NORTH LOCATED AT APT 7B LOWER LEVEL, 7th STORY, 4th APARTMENT FROM EAST AT SOUTH | Aug 19, 2006 |
| May 11, 2006 | B | Apt 7B · SECTION 27-2005, 2007 ADM CODE ARRANGE AND MAKE SELF-CLOSING THE DOORS , IN THE ENTRANCE LOCATED AT APT 7B, 7th STORY, 4th APARTMENT FROM EAST AT SOUTH | Jun 20, 2006 |
| May 11, 2006 | A | SECTION 27-2027 ADM CODE REPAIR THE BROKEN OR DEFECTIVE RAIN LEADER FRONT OF BUILDING. | Aug 19, 2006 |
| May 22, 2001 | B | Apt 7D · SECTION 27-2005 ADM CODE PROPERLY REPAIR THE BROKEN OR DEFECTIVE ELECTRICAL WALL SWITCH 7 STY NORTH APT 7D NROTH ROOM. , SECTION '' '' | Jul 1, 2001 |
| May 22, 2001 | C | SECTION 27-2033 ADM CODE POST NOTICE, IN FORM APPROVED BY THE DEPARTMENT, STATING THE NAME AND LOCATION OF THE PERSON DESIGNATED BY THE OWNER TO HAVE KEY TO BUILDINGS HEATING SYSTEM AT OR NEAR MAILBOXES 1 STY PUBLIC HALL | Jun 2, 2001 |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)