1 floors · 3,643 sq ft · built 1931 · class G2 · owner of record: 214 Jamaica Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 42 days | Keep the report on file (not filed with DOB) |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 13 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1138 days | Next cycle year 2029 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Oct 28, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDERS TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPT. OF BUILDINGS FOR VIO# 39176171R, FILE A CERTIFICATE OF CORRECTION #39209708X | Jan 5, 2027 PENDING | $1,250 |
| Oct 28, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDERS TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPT. OF BUILDINGS FOR VIO# 39176184X, FILE A CERTIFICATE OF CORRECTION #39209709H | Jan 5, 2027 PENDING | $1,250 |
| Aug 7, 2026 | Construction CLASS - 1 RESPONDENT HAS FAILED TO PROVIDE A PE REPORT AS REQUESTED BY THE DEPARTMENT IN DOBVIO24-02208 FOR THE STRUCTURAL STABILITY OF THE BUILDING., COMPLY WITH COMMISSIONER'S ORDER; PROVIDE PE REPORT TO EXECUTIVE INSP #39199704M | Oct 13, 2026 DEFAULT | $2,530 |
| Feb 5, 2026 | Construction CLASS - 1 FAILURE TO OBEY A VACATE ORDER FROM THE COMMISSIONER. OBSERVED PREMISES IS ILLEGALLY OCCUPIED WITH THREE (3) MALE OCCUPANTS AND VEHICLES WHILE ON AN ACTIVE FULL VACATE ORDER VAC Q297/2024, WHICH WAS ISSUED ON 0 #39176184X | Nov 13, 2026 PENDING | $10,000 |
| Feb 5, 2026 | Construction CLASS - 1 UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER. PREMISES WERE ISSUED WITH A FULL STOP WORK ORDER ON 06/16/2022. OBSERVED 100% COMPLETED BUILDING WITH NEW FACADE, WINDOWS, PLUMBING WORKS, AND INT #39176171R | Nov 13, 2026 PENDING | $10,000 |
| Feb 3, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 39106886R., FILE A CERTIFICATE OF CORRECTION #39175857R | Apr 14, 2026 IN VIOLATION | $1,250 |
| Feb 3, 2026 | Construction CLASS - 1 UNLAWFUL ACTS. FAILURE TO COMPLY WITH COMMISSIONER'S ORDER FOR SUMMONS 39120853L. OBSERVED 100% COMPLETED OCCUPIED BUILDING WITH NO ENGINEERS REPORT NOR ALL NECESSARY PERMITS ON FILE. NON-COMPLIANT WITH FULL ST #39175855N | Nov 13, 2026 PENDING | $6,250 |
| Feb 3, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 39104547N., FILE A CERTIFICATE OF CORRECTION #39175854L | Apr 14, 2026 IN VIOLATION | $1,250 |
| Feb 3, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 39106627M., FILE A CERTIFICATE OF CORRECTION #39175856P | Apr 14, 2026 IN VIOLATION | $1,250 |
| Feb 3, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 39084132X., FILE A CERTIFICATE OF CORRECTION #39175852H | Apr 14, 2026 IN VIOLATION | $1,250 |
| Feb 3, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 39107656X., FILE A CERTIFICATE OF CORRECTION #39175858Z | Apr 14, 2026 IN VIOLATION | $1,250 |
| Feb 3, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 39106604J., FILE A CERTIFICATE OF CORRECTION #39175851X | Apr 14, 2026 IN VIOLATION | $1,250 |
| Feb 3, 2026 | Construction CLASS - 1 UNLAWFUL ACTS. FAILURE TO COMPLY WITH COMMISSIONER'S ORDER FOR SUMMONS 39095431J., COMPLY WITH COMMISSIONER'S ORDER #39175853J | Apr 14, 2026 IN VIOLATION | $2,500 |
| Jan 22, 2025 | Construction CLASS - 3 WORK WITHOUT A PERMIT, ILLEGAL CURB CUT CREATED. NOTED AT FRONT LEFT SIDE OF PREMISES. CREATED CURB CUT MEASURING APPROXIMATELY 9FT WIDE. NO PERMITS ON FILE OR IN DOB RECORDS FOR WORK COMPLETED., OBTAIN PERMIT #39136888H | Apr 8, 2025 IN VIOLATION | $250 |
| Aug 5, 2024 | Construction CLASS - 1 UNLAWFUL ACTS. FAILURE TO COMPLY WITH COMMISSIONER'S ORDER. NOTED; AN ILLEGAL STEEL FRAME STRUCTURE CREATING 2ND STORY VERTICAL AND HORIZONTAL ENLARGEMENT WITH NO PERMITS ON TOP OF AN EXISTING 1-STORY COMMERCIA #39120853L | Oct 15, 2024 IN VIOLATION | $2,500 |
| Mar 4, 2024 | Construction CLASS - 1 UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER,NOTED: ON 03/04/2024 I OBSERVED 3 WORKERS INSTALLING PIPE FOR AN AIR COOLING SYSTEM, 1ST STORY., COMPLY WITH STOP WORK ORDER #39107656X | Feb 18, 2025 IN VIOLATION | $5,000 |
| Feb 26, 2024 | Construction CLASS - 1 TAMPERED WITH, REMOVED OR DEFACED A WRITTEN POSTED STOP WORK ORDER. NOTED; STOP WORK ORDER THAT WAS POSTED ON 2/22/2024 HAS BEEN REMOVED FROM FRONT., COMPLY WITH CODE #39106886R | Feb 18, 2025 IN VIOLATION | $12,500 |
| Feb 22, 2024 | Construction CLASS - 1 TAMPERED WITH, REMOVED OR DEFACED A WRITTEN POSTED STOP WORK ORDER. NOTED; STOP WORK ORDER THAT WAS POSTED HAS BEEN REMOVED FROM FRONT., COMPLY WITH CODE #39106604J | Feb 18, 2025 IN VIOLATION | $2,500 |
| Feb 22, 2024 | Construction CLASS - 1 UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF STOP WORK ORDER. NOTED; FULL STOP WORK ORDER WAS ISSUED ON 6/16/2022 FOR NEW STEEL FRAME VERTICAL EXTENSION CREATING 2ND STORY, ON 2/22/2024 OBSERVED 4 WORKERS ON SI #39106627M | Feb 18, 2025 IN VIOLATION | $5,000 |
| Jan 29, 2024 | Construction CLASS - 1 UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF STOP WORK ORDER. NOTED; FULL STOP WORK ORDER WAS ISSUED ON 6/16/2022 FOR NEW STEEL FRAME VERTICAL EXTENSION CREATING 2ND STORY, ON 1/29/2024 OBSERVED 4 WORKERS ON SI #39104547N | Feb 18, 2025 IN VIOLATION | $5,000 |
| Sep 20, 2023 | Construction CLASS - 1 WORK WITHOUT A PERMIT, OBSERVED AT REAR OF PREMISES. ERECTED HORIZONTAL EXTENSION MEASURING APPROXIMATELY 13'X15.' EXTENSION SPANS ENTIRE WIDTH OF BUILDING. WORK IS 100% DONE WITH CINDERBLOCK EXTERIOR, FLASHING #39095431J | Feb 18, 2025 IN VIOLATION | $2,500 |
| Apr 19, 2023 | Construction CLASS - 1 UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER. PREMISES WAS ISSUED A FULL SWO ON 6/16/2022, AT TIME OF INSPECTION BUILDING NOW FULLY ENCLOSED WITH NEW FACADE AND COMMERCIAL WINDOWS. MORE THAN 5 #39084132X | Jun 27, 2023 IN VIOLATION | $5,000 |
| Issued | Violation | Status |
|---|---|---|
| Aug 6, 2024 | CONSTRUCTION STRUCTURE STABILITY REPORT. ILLEGAL STEEL FRAME STRUCTURE CREATING 2ND STORY VERTICAL AND HORIZONTAL ENLARGEMENT WITH NO PERMITS ON TOP OF AN EXISTING 1-STORY COMMERCIAL BUILDING WITHOUT AN ENGINEER'S REPORT FOR STRUCTURAL STABILITY. PROPERTY HAS ACTIVE SWO AND HAS UNLAWFULLY CONTINUED WORK AND IS O #24-02208 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 14, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Oct 14, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Sep 18, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle B (premises is in Community District 13) | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 28, 2026 | ECB | Construction: FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDERS TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPT. OF BUILDINGS FOR VIO# 39176171R, FILE A CERTIFICATE OF CORRECTION | Open |
| Oct 28, 2026 | ECB | Construction: FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDERS TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPT. OF BUILDINGS FOR VIO# 39176184X, FILE A CERTIFICATE OF CORRECTION | Open |
| Oct 14, 2026 | DOB Safety | AEUHAZ: | Open |
| Oct 14, 2026 | DOB Safety | AEUHAZ: | Open |
| Aug 7, 2026 | ECB | Construction: RESPONDENT HAS FAILED TO PROVIDE A PE REPORT AS REQUESTED BY THE DEPARTMENT IN DOBVIO24-02208 FOR THE STRUCTURAL STABILITY OF THE BUILDING., COMPLY WITH COMMISSIONER'S ORDER; PROVIDE PE REPORT TO EXECUTIVE INSP | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 19, 2026, 2:40 AM ET. BBL 4107590102.