Queens · Block 10759 · Lot 102 · 11428

215-02 Jamaica Avenue

1 floors · 3,643 sq ft · built 1931 · class G2 · owner of record: 214 Jamaica Llc

26open violations
$81,530ECB/OATH penalties owed
0HPD class C (immediately hazardous)
1138dto Gas piping inspection (2029 cycle)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 42 days
Keep the report on file (not filed with DOB)
Gas piping inspection (2029 cycle) Likely applies
Local Law 152 · During 2029
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 13 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2029
in 1138 days
Next cycle year 2029

Open violations

ECB / OATH (22) · $81,530 owed
IssuedViolationHearingBalance
Oct 28, 2026Construction CLASS - 2
FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDERS TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPT. OF BUILDINGS FOR VIO# 39176171R, FILE A CERTIFICATE OF CORRECTION
#39209708X
Jan 5, 2027
PENDING
$1,250
Oct 28, 2026Construction CLASS - 2
FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDERS TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPT. OF BUILDINGS FOR VIO# 39176184X, FILE A CERTIFICATE OF CORRECTION
#39209709H
Jan 5, 2027
PENDING
$1,250
Aug 7, 2026Construction CLASS - 1
RESPONDENT HAS FAILED TO PROVIDE A PE REPORT AS REQUESTED BY THE DEPARTMENT IN DOBVIO24-02208 FOR THE STRUCTURAL STABILITY OF THE BUILDING., COMPLY WITH COMMISSIONER'S ORDER; PROVIDE PE REPORT TO EXECUTIVE INSP
#39199704M
Oct 13, 2026
DEFAULT
$2,530
Feb 5, 2026Construction CLASS - 1
FAILURE TO OBEY A VACATE ORDER FROM THE COMMISSIONER. OBSERVED PREMISES IS ILLEGALLY OCCUPIED WITH THREE (3) MALE OCCUPANTS AND VEHICLES WHILE ON AN ACTIVE FULL VACATE ORDER VAC Q297/2024, WHICH WAS ISSUED ON 0
#39176184X
Nov 13, 2026
PENDING
$10,000
Feb 5, 2026Construction CLASS - 1
UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER. PREMISES WERE ISSUED WITH A FULL STOP WORK ORDER ON 06/16/2022. OBSERVED 100% COMPLETED BUILDING WITH NEW FACADE, WINDOWS, PLUMBING WORKS, AND INT
#39176171R
Nov 13, 2026
PENDING
$10,000
Feb 3, 2026Construction CLASS - 2
FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 39106886R., FILE A CERTIFICATE OF CORRECTION
#39175857R
Apr 14, 2026
IN VIOLATION
$1,250
Feb 3, 2026Construction CLASS - 1
UNLAWFUL ACTS. FAILURE TO COMPLY WITH COMMISSIONER'S ORDER FOR SUMMONS 39120853L. OBSERVED 100% COMPLETED OCCUPIED BUILDING WITH NO ENGINEERS REPORT NOR ALL NECESSARY PERMITS ON FILE. NON-COMPLIANT WITH FULL ST
#39175855N
Nov 13, 2026
PENDING
$6,250
Feb 3, 2026Construction CLASS - 2
FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 39104547N., FILE A CERTIFICATE OF CORRECTION
#39175854L
Apr 14, 2026
IN VIOLATION
$1,250
Feb 3, 2026Construction CLASS - 2
FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 39106627M., FILE A CERTIFICATE OF CORRECTION
#39175856P
Apr 14, 2026
IN VIOLATION
$1,250
Feb 3, 2026Construction CLASS - 2
FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 39084132X., FILE A CERTIFICATE OF CORRECTION
#39175852H
Apr 14, 2026
IN VIOLATION
$1,250
Feb 3, 2026Construction CLASS - 2
FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 39107656X., FILE A CERTIFICATE OF CORRECTION
#39175858Z
Apr 14, 2026
IN VIOLATION
$1,250
Feb 3, 2026Construction CLASS - 2
FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 39106604J., FILE A CERTIFICATE OF CORRECTION
#39175851X
Apr 14, 2026
IN VIOLATION
$1,250
Feb 3, 2026Construction CLASS - 1
UNLAWFUL ACTS. FAILURE TO COMPLY WITH COMMISSIONER'S ORDER FOR SUMMONS 39095431J., COMPLY WITH COMMISSIONER'S ORDER
#39175853J
Apr 14, 2026
IN VIOLATION
$2,500
Jan 22, 2025Construction CLASS - 3
WORK WITHOUT A PERMIT, ILLEGAL CURB CUT CREATED. NOTED AT FRONT LEFT SIDE OF PREMISES. CREATED CURB CUT MEASURING APPROXIMATELY 9FT WIDE. NO PERMITS ON FILE OR IN DOB RECORDS FOR WORK COMPLETED., OBTAIN PERMIT
#39136888H
Apr 8, 2025
IN VIOLATION
$250
Aug 5, 2024Construction CLASS - 1
UNLAWFUL ACTS. FAILURE TO COMPLY WITH COMMISSIONER'S ORDER. NOTED; AN ILLEGAL STEEL FRAME STRUCTURE CREATING 2ND STORY VERTICAL AND HORIZONTAL ENLARGEMENT WITH NO PERMITS ON TOP OF AN EXISTING 1-STORY COMMERCIA
#39120853L
Oct 15, 2024
IN VIOLATION
$2,500
Mar 4, 2024Construction CLASS - 1
UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER,NOTED: ON 03/04/2024 I OBSERVED 3 WORKERS INSTALLING PIPE FOR AN AIR COOLING SYSTEM, 1ST STORY., COMPLY WITH STOP WORK ORDER
#39107656X
Feb 18, 2025
IN VIOLATION
$5,000
Feb 26, 2024Construction CLASS - 1
TAMPERED WITH, REMOVED OR DEFACED A WRITTEN POSTED STOP WORK ORDER. NOTED; STOP WORK ORDER THAT WAS POSTED ON 2/22/2024 HAS BEEN REMOVED FROM FRONT., COMPLY WITH CODE
#39106886R
Feb 18, 2025
IN VIOLATION
$12,500
Feb 22, 2024Construction CLASS - 1
TAMPERED WITH, REMOVED OR DEFACED A WRITTEN POSTED STOP WORK ORDER. NOTED; STOP WORK ORDER THAT WAS POSTED HAS BEEN REMOVED FROM FRONT., COMPLY WITH CODE
#39106604J
Feb 18, 2025
IN VIOLATION
$2,500
Feb 22, 2024Construction CLASS - 1
UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF STOP WORK ORDER. NOTED; FULL STOP WORK ORDER WAS ISSUED ON 6/16/2022 FOR NEW STEEL FRAME VERTICAL EXTENSION CREATING 2ND STORY, ON 2/22/2024 OBSERVED 4 WORKERS ON SI
#39106627M
Feb 18, 2025
IN VIOLATION
$5,000
Jan 29, 2024Construction CLASS - 1
UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF STOP WORK ORDER. NOTED; FULL STOP WORK ORDER WAS ISSUED ON 6/16/2022 FOR NEW STEEL FRAME VERTICAL EXTENSION CREATING 2ND STORY, ON 1/29/2024 OBSERVED 4 WORKERS ON SI
#39104547N
Feb 18, 2025
IN VIOLATION
$5,000
Sep 20, 2023Construction CLASS - 1
WORK WITHOUT A PERMIT, OBSERVED AT REAR OF PREMISES. ERECTED HORIZONTAL EXTENSION MEASURING APPROXIMATELY 13'X15.' EXTENSION SPANS ENTIRE WIDTH OF BUILDING. WORK IS 100% DONE WITH CINDERBLOCK EXTERIOR, FLASHING
#39095431J
Feb 18, 2025
IN VIOLATION
$2,500
Apr 19, 2023Construction CLASS - 1
UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER. PREMISES WAS ISSUED A FULL SWO ON 6/16/2022, AT TIME OF INSPECTION BUILDING NOW FULLY ENCLOSED WITH NEW FACADE AND COMMERCIAL WINDOWS. MORE THAN 5
#39084132X
Jun 27, 2023
IN VIOLATION
$5,000
DOB (1)
IssuedViolationStatus
Aug 6, 2024CONSTRUCTION
STRUCTURE STABILITY REPORT. ILLEGAL STEEL FRAME STRUCTURE CREATING 2ND STORY VERTICAL AND HORIZONTAL ENLARGEMENT WITH NO PERMITS ON TOP OF AN EXISTING 1-STORY COMMERCIAL BUILDING WITHOUT AN ENGINEER'S REPORT FOR STRUCTURAL STABILITY. PROPERTY HAS ACTIVE SWO AND HAS UNLAWFULLY CONTINUED WORK AND IS O
#24-02208
DOB VIOLATION - ACTIVE
DOB NOW Safety (3)
IssuedViolationStatus
Oct 14, 2026AEUHAZ FTC-AEU-HAZ
Active
Oct 14, 2026AEUHAZ FTC-AEU-HAZ
Active
Sep 18, 2025Gas Piping - LL152 FTF-PL-PER
Cycle 1, Sub-cycle B (premises is in Community District 13)
Active
HPD (0)

None open.

Issued in the last 120 days

DateSourceWhatNow
Oct 28, 2026ECBConstruction: FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDERS TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPT. OF BUILDINGS FOR VIO# 39176171R, FILE A CERTIFICATE OF CORRECTIONOpen
Oct 28, 2026ECBConstruction: FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDERS TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPT. OF BUILDINGS FOR VIO# 39176184X, FILE A CERTIFICATE OF CORRECTIONOpen
Oct 14, 2026DOB SafetyAEUHAZ: Open
Oct 14, 2026DOB SafetyAEUHAZ: Open
Aug 7, 2026ECBConstruction: RESPONDENT HAS FAILED TO PROVIDE A PE REPORT AS REQUESTED BY THE DEPARTMENT IN DOBVIO24-02208 FOR THE STRUCTURAL STABILITY OF THE BUILDING., COMPLY WITH COMMISSIONER'S ORDER; PROVIDE PE REPORT TO EXECUTIVE INSPOpen

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Nov 19, 2026, 2:40 AM ET. BBL 4107590102.