| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 56 days | Keep the report on file (not filed with DOB) |
| Energy audit and retro-commissioning (2026) Likely applies Local Law 87 · Calendar year 2026 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 266). Agency page | Dec 31, 2026 in 56 days | Due this year |
| Annual boiler inspection (3 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2022-12-13 (Accepted). Agency page | Dec 31, 2026 in 56 days | 3 of 3 without an accepted 2026 report yet |
| Facade inspection report (Cycle 10A) Applies Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. Agency page | Feb 21, 2027 in 108 days | No Cycle 10 report on record yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 550,966 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 177 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 177 days | Annual filing |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 2 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1152 days | Next cycle year 2029 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Sep 27, 2026 | Unknown CLASS - 2 AT TIME OF INSPECTION OBSERVED: AT EXPO# 4 STAIR TOWER WITH INADEQUATE LOOSE NETTING DEBRIS AND TEAR APART NOT MAINTAINED CONTRARY TO BC 3314.8.2 CREATING UNSAFE CONDITIONS, DEBRIS OR OTHER ELEMENTS COULD FALL #39559848H | Dec 2, 2026 PENDING | $2,500 |
| Jul 24, 2026 | Construction CLASS - 1 UPON INSPECTION OF A FACADE/ROOF ALT I OBSERVED WORK CONTRARY TO THE APPROVED SITE SAFETY PLAN. NO 20FT SIDEWALK SHED EXTENSION PROVIDED AT EXPOS 1 AND 4. NO OVERHEAD PROTECTION PROVIDED FOR THE ADJOINING PROPE #39557029P | May 7, 2027 PENDING | $2,500 |
| Jul 24, 2026 | Construction CLASS - 2 UPON INSPECTION I OBSERVED A SIDEWALK SHED INSTALLED AT EXPOS 1&4 WITH AN INADEQUATE SIZE (NOT 3FTX6FT) SIDEWALK SHED PROJECT INFO PANEL INSTALLED AT EXPOS 1&4 CONTRARY TO CODE 3301.9.2.4 SIDEWALK SHED PARAPET #39557032X | May 7, 2027 | $1,250 |
| Jul 24, 2026 | Construction CLASS - 2 SIDEWALK SHED INSTALLED AT EXPOS 1 & 4 CONTRARY TO CODE. MULTIPLE BEAMS AT EXPOS 1 PLACED WITHIN 18IN FROM THE FACE OF THE CURB (3307.6.4.4. 8). 8FT MINIMUM HEIGHT NOT MAINTAINED IN PATHWAY AT MULTIPLE LOCATION #39557027L | Oct 7, 2026 DEFAULT | $2,430 |
| Jun 12, 2025 | Unknown CLASS - 1 AT THE TIME OF INSPECTION IT WAS OBSERVED, THAT THE CONTRACTOR FAILED TO SUBMIT REPORT WITHIN 3 BUSINESS DAYS OF REQUIRED 16 ITEMS TO CODE 28-103.21 PER-28-103.21.1 BY VIA WEB INCIDENTS, WHICH OCCURRED ON 05/2/ #39541339Y | Dec 18, 2026 | $10,030 |
| Aug 4, 2016 | Construction CLASS - 2 FAILURE TO MAINTAIN EXTERIOR BLDG FACADE.NORTH ELEVATION (NORTH/EAST CORNER) EXP#1, OBSERVE VERTICAL HAIR LINE CRACKS AT 4TH FLR AND UP ATMASONRY FACADE; (II)SOUTH ELEVATION,EXP#3 SPALLING/CRACKS/DAMAGE,STONE #35173640L | Sep 12, 2016 POP/IN-VIO | $0 |
| Mar 12, 2015 | Unknown CLASS - 2 UNAPPROVED UNSAFE UNSUITABLE ELECTRICAL EQUIPMENT DEVICES APPARTUS MATERIALS APPLIANCES OR WIRING IN USE. EXPOSE WIRING IN LOBBY NEXT TO SECURITY DESK WIRE MOLDING MISSING EL COVERS DUCTS TAPE USED AT 90 ELL. #35122868H | Jun 8, 2015 WRITTEN OFF | $0 |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION #00314 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01123 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01125 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION #00313 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01124 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #08244 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION #00315 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION #00327 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL LOW PRESSURE INSPECTION #07379 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION #01191 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION #01190 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION #00329 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION #01189 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION #00328 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #03429 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #03455 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #03305 | DOB VIOLATION - ACTIVE |
| Aug 4, 2021 | ELEVATOR #9027/705616 | DOB VIOLATION - ACTIVE |
| Aug 4, 2021 | ELEVATOR #9027/705610 | DOB VIOLATION - ACTIVE |
| Aug 4, 2021 | ELEVATOR #9027/705611 | DOB VIOLATION - ACTIVE |
| Aug 4, 2021 | ELEVATOR #9027/705612 | DOB VIOLATION - ACTIVE |
| Aug 4, 2021 | ELEVATOR #9027/705613 | DOB VIOLATION - ACTIVE |
| Aug 4, 2021 | ELEVATOR #9027/705614 | DOB VIOLATION - ACTIVE |
| Aug 4, 2021 | ELEVATOR #9027/705615 | DOB VIOLATION - ACTIVE |
| Aug 4, 2021 | ELEVATOR #9027/705618 | DOB VIOLATION - ACTIVE |
| Aug 3, 2021 | ELEVATOR #9027/705607 | DOB VIOLATION - ACTIVE |
| Aug 3, 2021 | ELEVATOR #9027/705609 | DOB VIOLATION - ACTIVE |
| Aug 3, 2021 | ELEVATOR #9027/705608 | DOB VIOLATION - ACTIVE |
| Aug 3, 2021 | ELEVATOR #9027/705606 | DOB VIOLATION - ACTIVE |
| Aug 3, 2021 | ELEVATOR #9027/705605 | DOB VIOLATION - ACTIVE |
| Jun 19, 2020 | ELEVATOR #9027/683693 | DOB VIOLATION - ACTIVE |
| Jun 19, 2020 | ELEVATOR #9027/683695 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION #00490 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION #00489 | DOB VIOLATION - ACTIVE |
| Sep 3, 2019 | SPRINKLER FAILED TO FILE FINAL SPRINKLER REPORT BY JULY 1, 2019 #NRF01034 | DOB VIOLATION - ACTIVE |
| Jun 24, 2019 | ELEVATOR #9027/654347 | DOB VIOLATION - ACTIVE |
| May 25, 2017 | ELEVATOR #9027/604814 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 29, 2026 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Active |
| Oct 29, 2026 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Active |
| Oct 29, 2026 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Active |
| Oct 29, 2026 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2026 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Report | Active |
| Aug 31, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Aug 29, 2025 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Report | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Sep 23, 2024 | Boiler LBLVIO Violation Issued-Failure To File 2023 External Low Pressure Inspection Report | Active |
| Sep 23, 2024 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION | Active |
| Sep 23, 2024 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Sep 23, 2024 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Sep 23, 2024 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Sep 23, 2024 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION | Active |
| Sep 23, 2024 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION | Active |
| Sep 11, 2024 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Report | Active |
Showing 60 of 121. Full list on the agency site.
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Open |
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Open |
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Open |
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Report | Open |
| Sep 27, 2026 | ECB | Unknown: AT TIME OF INSPECTION OBSERVED: AT EXPO# 4 STAIR TOWER WITH INADEQUATE LOOSE NETTING DEBRIS AND TEAR APART NOT MAINTAINED CONTRARY TO BC 3314.8.2 CREATING UNSAFE CONDITIONS, DEBRIS OR OTHER ELEMENTS COULD FALL | Open |
| Aug 31, 2026 | DOB Safety | AEUHAZ: | Open |
| Jul 24, 2026 | ECB | Construction: UPON INSPECTION OF A FACADE/ROOF ALT I OBSERVED WORK CONTRARY TO THE APPROVED SITE SAFETY PLAN. NO 20FT SIDEWALK SHED EXTENSION PROVIDED AT EXPOS 1 AND 4. NO OVERHEAD PROTECTION PROVIDED FOR THE ADJOINING PROPE | Open |
| Jul 24, 2026 | ECB | Construction: UPON INSPECTION I OBSERVED A SIDEWALK SHED INSTALLED AT EXPOS 1&4 WITH AN INADEQUATE SIZE (NOT 3FTX6FT) SIDEWALK SHED PROJECT INFO PANEL INSTALLED AT EXPOS 1&4 CONTRARY TO CODE 3301.9.2.4 SIDEWALK SHED PARAPET | Closed |
| Jul 24, 2026 | ECB | Construction: SIDEWALK SHED INSTALLED AT EXPOS 1 & 4 CONTRARY TO CODE. MULTIPLE BEAMS AT EXPOS 1 PLACED WITHIN 18IN FROM THE FACE OF THE CURB (3307.6.4.4. 8). 8FT MINIMUM HEIGHT NOT MAINTAINED IN PATHWAY AT MULTIPLE LOCATION | Open |