8 floors · 14 apartments · 17,050 sq ft · built 2021 · class D6 · owner of record: The Hallet, Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | Registration expired 2018-09-01 |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 58 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 58 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 74 days | Annual |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 1 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 789 days | Next cycle year 2028 |
| Facade inspection report (Cycle 10C) Applies Local Law 11 / FISP · Feb 21, 2027 to Feb 21, 2029 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 1, 2 or 3 are in sub-cycle 10C. Agency page | Feb 21, 2029 in 841 days | Filing window not open yet |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Feb 6, 2024 | Construction CLASS - 1 FAILURE TO COMPLY WITH THE COMMISSIONERS ORDER CONTAINED IN SUMMONS/VIOLATION# 35576379N ISSUED ON 07/14/22 AND TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01. (FAILURE TO MAINTAIN BU #39105272H | Jun 5, 2026 IN VIOLATION | $2,500 |
| Oct 19, 2023 | Construction CLASS - 2 AT TIME OF INSPECTION NO UPDATED (PAA) COM-CHECK OR EN DRAWINGS ON SITE TO CONDUCT INSPECTION., PROVIDE APPROVED /ACCEPTED CONSTRUCTION DOCUMENTS #39097424K | Dec 4, 2026 DEFAULT | $1,562 |
| May 17, 2023 | Construction CLASS - 2 FAILURE TO COMPLY WITH DOT AND DOB REGULATIONS. ALSO FAILURE TO COMPLY WITH MFS. STORAGE ZONE AT EXPOS 1 WITH STORED MATERIALS AND EQUIPMENT WITH OUT DOT PERMIT AND PEDESTRIAN PROTECTION, ENCLOSED WITH PLASTICS #39516717H | Dec 11, 2026 DEFAULT | $3,125 |
| May 17, 2023 | Construction CLASS - 2 AT TIME OF INSPECTION OBSERVED AT EXP#1 ERECTED SIDEWALK SHED UNDER PERMIT#Q00514317-I1-SH EXPIRED AS OF 05-16-2023. #39516706M | Dec 11, 2026 DEFAULT | $3,125 |
| Mar 30, 2023 | Unknown CLASS - 2 AT TIME OF INSPECTION OF A 8 STORY BUILDING UNDER ACTIVE CONSTRUCTION OPERATIONS. COMPETENT PERSON WITH OLD SST TRAINING CARD. AS PER SST NOTICE ALL WORKERS MUST HAVE UPDATED SST TRAINING CARDS. #39514834H | Dec 11, 2026 DEFAULT | $5,000 |
| Mar 30, 2023 | Construction CLASS - 2 AT TIME OF INSPECTION OF A 8 STORY NEW BUILDING AT ROOF LEVEL WORK NOT CONFORMING TO APPROVED PLANS ON SITE. OBSERVED WORKERS ON IN THE PROCESS OF DOING WINDOW OPENING AT EXPOSURE #2 AND #4 NOT SHOWN ON APPROV #39514833X | Jan 9, 2024 IN VIOLATION | $1,250 |
| Mar 30, 2023 | Construction CLASS - 2 AT TIME OF INSPECTION OF A 8 STORY NEW BUILDING AT ROOF LEVEL. I OBSERVED STYROFOAM RESIDUE AND DEBRIS ON STREET SIDEWALK AND SITE. CREATING HAZARDOUS CONDITION FOR PEDESTRIANS ( EYES AND BREATHING ). STOP ALL #39514835J | Jan 9, 2024 IN VIOLATION | $1,250 |
| Feb 10, 2023 | Construction CLASS - 1 FAILURE TO INSTITUTE/MAINTAIN SAFETY MEASURES: UNSAFE EQUIPMENT. AT TIME OF INSPECTION OBSERVED MASONRY/METAL CUTTING GRINDER WITH PROTECTIVE GUARD REMOVED WHERE BLADE POTENTIAL BREAK BECOMING A PROJECTILE HAZA #39079497M | Sep 26, 2023 IN VIOLATION | $1,250 |
| Feb 10, 2023 | Construction CLASS - 2 FAILURE TO SAFE GUARD ALL PERSONS & PROPERTY AFFECTED BY CONSTRUCTION OPERATIONS. AT TIME OF INSPECTION OBSERVED NO OVERHEAD PROTECTION FOR 31-05 21 ST REAR YARD OF 1A/1B WHERE MASONRY AND FOOD GARBAGE HAS FALL #39079498Y | Sep 26, 2023 IN VIOLATION | $5,000 |
| Jan 17, 2023 | Construction CLASS - 2 AT TIME OF INSPECTION OF ONGOING NEW BUILDING CONSTRUCTION I OBSERVED NO COMPLIANCE FROM RESPONDENT FOR PREVIOUSLY ISSUED VIOLATION 39508631R ISSUED ON 11/2/22 FOR SUPPORTED SCAFFOLDING AND SIDEWALK SHED NON CO #39511754Y | Dec 11, 2026 DEFAULT | $3,125 |
| Jan 17, 2023 | Construction CLASS - 2 AT TIME OF INSPECTION OF ONGOING NEW BUILDING CONSTRUCTION I OBSERVED NO COMPLIANCE FOR PREVIOUSLY ISSUED VIOLATION 39508640Z ISSUED ON 11/2/22 FOR FAILURE TO DRAIN SITE OF PONDING WATER. SINCE ORIGINAL VIOLATI #39511759N | Dec 11, 2026 DEFAULT | $3,125 |
| Jan 17, 2023 | Construction CLASS - 2 AT TIME OF INSPECTION OF ONGOING NEW BUILDING CONSTRUCTION I OBSERVED NO COMPLIANCE FROM RESPONDENT FOR PREVIOUSLY ISSUED VIOLATION 39508639L ISSUED ON 11/2/22 FOR FAILURE TO PROVIDE LOADS IMPOSED LETTER FOR SI #39511758L | Dec 11, 2026 DEFAULT | $3,125 |
| Oct 12, 2022 | Construction CLASS - 2 ATOI FOR CLASS 1 VIOLATION#35641588H, JOB SITE WAS CLOSED AND ACCESS WAS NOT GAINED. UPON BIS RESEARCH, NO CERTIFICATE OF CORRECTION WAS FILED FOR FORESAID VIOLATION. G.C FAILED TO COMPLY WITH THE COMMISSIONER' #39507456Y | Mar 28, 2023 IN VIOLATION | $1,250 |
| Oct 7, 2022 | Construction CLASS - 2 SIDEWALK SHED/OVERHEAD PROTECTION BC3307.2/6.@8STORY NB SITE I OBSERVE SIDEWALK SHED DECK NOT TIGHT TO FACE OF BUILDING AND GAPS NOT ENCLOSED, EXPOSURE#2 PROPERTY WALKWAY ADJACENT TO SITE OVERHEAD PROTECTION SH #39507315K | Mar 27, 2023 IN VIOLATION | $2,400 |
| Aug 18, 2022 | Construction CLASS - 2 AT THE TIME OF INSPECTION I OBSERVED, UNSAFE SUPPORTED SCAFFOLD ON SWS. LOOSEN WOOD PLANKS ON SCAFFOLD FRAME. INADEQUATE GUARDRAILS SYSTEM MISSING MID-RAILS AND END-RAILS. WHICH WAS CREATING FALL HAZARD ON WOR #39505315L | Mar 10, 2023 IN VIOLATION | $1,250 |
| Aug 18, 2022 | Construction CLASS - 2 AT THE TIME OF INSPECTION I OBSERVED. TEMPORARY PLATFORM ON SITE FROM 1ST FLOOR UP TO 6TH FLOOR, WITHOUT CAZ. UPON REQUEST UNABLE TO PROVIDE DD.PERMIT HOLDER FAILURE TO PROVIDE DD FOR TEMPORARY ELEVATOR PLATFOR #39505317P | Mar 10, 2023 IN VIOLATION | $1,250 |
| Aug 2, 2022 | Construction CLASS - 2 FAILURE TO PROVIDE AN ADEQUATE INSPECTION PROGRAM TR-3 TECHNICAL REPORT CONCRETE DESIGN MIX 4000 PSI(LIGHT WEIGHT CONCRETE).AS NOTED:AT TIMEOF INSPECTION ON AN ACTIVE CONSTRUCTION SITE 8 STORY NEW BUILDING,OBSE #35647240Y | Mar 17, 2023 IN VIOLATION | $625 |
| Mar 4, 2022 | Construction CLASS - 2 FAILURE TO PROVIDE APPROVED CONSTRUCTION DOCUMENTS AT JOBSITE FOR MAKESHIFT HOIST AND STEEL ASSEMBLY.AT TIME OF INSPECTION OBSERVED A MAKESHIFT HOIST IN PLACE FABRICATED WITH METAL,STEEL COMPONENTS AND BOLTED A #35642677Y | Nov 3, 2022 IN VIOLATION | $625 |
| Mar 4, 2022 | Construction CLASS - 2 FAILURE TO MAINTAIN/DISPLAY ONSITE DOCUMENTS REQUIRED BY BC CHAPTER 33AT TIME OF INSPECTION OBSERVED OVERHEAD PROTECTION AT REAR EXP3.UPON REQUEST OF APPROVED DESIGN DRAWINGS IN ACCORDANCE WITH THE REQUIREMENTS #35642676M | Nov 3, 2022 IN VIOLATION | $1,250 |
| Mar 4, 2022 | Construction CLASS - 2 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROVED AMENDMENTS.AT TIME OF INSPECTION OBSERVED A SIDEWALK SHED IN PLACE AT EXP1.UPON REVIEW OF THE SIDEWALK SHED DRAWINGS PROVIDED,THE SITE OB #35642678X | Nov 3, 2022 IN VIOLATION | $1,250 |
| Mar 4, 2022 | Construction CLASS - 2 PROJECT INFORMATION PANEL/SIDEWALK SHED PARAPET PANEL/CONSTRUCTION SIGN NOT PROVIDED OR NOT IN COMPLIANCE WITH SECTION.AT TIME OF INSPECTIONOBSERVED A SIDEWALK SHED IN PLACE AT EXP1 IN CONJUCTION WITH CONSTRUCT #35642679H | Nov 3, 2022 IN VIOLATION | $1,250 |
| Oct 8, 2021 | Construction CLASS - 2 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROVED AMENDMENTS.NOTE OBSERVED COLD FORM STEEL JOIST FRAMING FOR 2ND FLOOR AT STAIRWAY LANDING CFS JOIST INSTALLED BETWEEN CFS BOX BEAM CONTRAR #35582743L | May 31, 2022 IN VIOLATION | $625 |
| Jun 10, 2021 | Construction CLASS - 1 FAILURE TO SAFEGUARD ALL PERSONS AND PROPERTY AFFECTED BY CONSTRUCTIONOPERATIONS PLUS INSTITUTE SAFETY MEASURES NOT MAINTAINED.AT TIME OF INSPECTION OF ACTIVE PERMIT SITE OF 8 STORY NEW BUILDING SUPER STRUCTURE #35547422R | Feb 22, 2022 IN VIOLATION | $10,000 |
| Jun 10, 2021 | Site Safety CLASS - 1 CONSTRUCTION SUPERINTENDENT FAILED TO PERFORM DUTIES PER CODE.AT TIME OF INSPECTION OF ACTIVE PERMIT 8 STORY NEW BUILDING UP TO 2ND FLOOR OBSERVED MULTIPLE HAZARDOUS CONDITIONS AT SITE TO THE ADJOINING PROPERTI #35547424K | Feb 22, 2022 IN VIOLATION | $2,500 |
| Jun 10, 2021 | Unknown CLASS - 1 FAILURE TO ENSURE EACH WORKER HAS SUCCESSFULLY COMPLETED THE REQUIRED TRAINING.CONSTRUCTION SUPERINTENDENT#024908 NO 62 HOUR SITE SAFETY TRAINING SUPERVISOR SST CARD.AT TIME OF INSPECTION OF ACTIVE PERMIT 8 STO #35574425X | Feb 22, 2022 IN VIOLATION | $1,250 |
| Jun 10, 2021 | Construction CLASS - 1 3301.7,3301.1.3 FAILURE TO MAINTAIN ONSITE DOCUMENTS REQUIRED BY BC CHAPTER 33 AND FAILURE TO COMPLY WITH MANUFACTURER SPECIFICATION FOR COLD FORM STEEL.AT TIME OF INSPECTION OF ACTIVE PERMIT 8 STORY NEW BUILDI #35547423Z | Feb 22, 2022 IN VIOLATION | $0 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 1) | Active |
None open.