Brooklyn · Block 55 · Lot 7502 · 11201

206 Front Street

7 floors · 31 apartments · 37,725 sq ft · built 2006 · class R4 · owner of record: Unavailable Owner

9open violations
$2,530ECB/OATH penalties owed
0HPD class C (immediately hazardous)
Overdueto Annual property registration

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual property registration Applies
HPD registration · September 1 each year
What this is

Residential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page

OverdueRegistration expired 2026-09-01
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 70 days
Keep the report on file (not filed with DOB)
Bedbug annual filing Applies
Local Law 69 · December 1 to 31 each year
What this is

Owners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page

Dec 31, 2026
in 70 days
Annual
Annual notice: window guards and lead paint Applies
HPD / Health Code · January 1 to 16 each year
What this is

Deliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page

Jan 16, 2027
in 86 days
Annual
Facade inspection report (Cycle 10A) Applies
Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027
What this is

Buildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $132,000 in late-filing or failure-to-file penalties. Agency page

Feb 21, 2027
in 122 days
No Cycle 10 report on record yet
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 37,725 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 191 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 191 days
Annual filing
Gas piping inspection (2029 cycle) Likely applies
Local Law 152 · During 2029
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 2 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2029
in 1166 days
Next cycle year 2029

Open violations

ECB / OATH (1) · $2,530 owed
IssuedViolationHearingBalance
Aug 15, 2024Construction CLASS - 1
WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROVED AMENDMENTS. AT TIME OF INSPECTION, I OBSERVED A 7 STORY AND BASEMENT; CONDOMINIUM WITH STEEL FRAMING AS PRIMARY STRUCTURAL SYSTEM. HOWEVE
#35684044J
Feb 26, 2027
$2,530
DOB (5)
IssuedViolationStatus
Jan 13, 2025CONSTRUCTION
FAILURE TO MAINTAIN BLDG IN A SAFE CONDITIONS.CELLAR PARKING GARAGE PIERS D-1 AT EXP 2/3 CRNR&D-1@EXP4 #3/4 CRNR WERE PREVIOUSLY CUT & INADEQUATELY SUPPORTD.D-1 PIER WAS CUT APPRX3FT TALL 14"X24".IMMED COMPLY W/COMMISSIONER'S ORDER #341660 (081524FEU30302PN)DATED 8/15/24
#FEU30201PN
DOB VIOLATION - ACTIVE
Aug 15, 2024CONSTRUCTION
EMERGENCY WORK ORDER.REBAR WAS CUT&EXPOSED @TOP OF CELLAR SLAB& UNDERSIDE OF PIER.PIER 0-1 STRUCTURALLY COMPROMISED.OWNR TO IMMED RTAIN NYSPE TO SHORE/TEMP STBLIZE CELLAR CONC PIER D-1 @EXP2/3 CRNR SBMT MEANS&METHDS TO FEU FOR APPRVL
#FEU30201PN
DOB VIOLATION - ACTIVE
Aug 15, 2024CONSTRUCTION
FAILURE TO MAINTAIN BLDG IN A SAFE CONDITION.CELLAR PARKING GARAGE PIERS D-1 AT EXP 2/3CRNR&D-1 @EXP4 @3/4 CRNR WERE PREVIOUSLY CUT& INADEQUATELU SUPPORTD.D-1 PIER WAS CUT APPRX 3FT TALL 14'X24".OWNR TO RTAIN PE TO EVAL ENT BLDG&FILE RPAIR DWGS W/DOB TO RPAIR &/OR LEGALIZE WRK@CELLAR PIERS D-1,D-10,
#FEU30202PN
DOB VIOLATION - ACTIVE
Apr 18, 2019ELEVATOR

#9027/651002
DOB VIOLATION - ACTIVE
Jan 3, 2017(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST
#09204
DOB VIOLATION - ACTIVE
DOB NOW Safety (2)
IssuedViolationStatus
Apr 30, 2025Parking Structures FTC-PS-UNSAFE
Unsafe PIPS compliance report filed
Active
Jan 3, 2017Elevators ACC1
Active
HPD (2) · C 0 · B 1 · A 1
IssuedClassViolationCorrect by
Sep 27, 2021BApt 6D · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF BEDBUGS IN THE ENTIRE APARTMENT LOCATED AT APT 6D, 6th STORY, 1st APARTMENT FROM WEST AT NORTHNov 1, 2021
Sep 27, 2021A§ 329, M/D LAW AND DEPT. RULES AND REGS. PROVIDE A COMPLETED CERTIFICATE OF INSPECTION VISITS IN A PROPER FRAME AT OR NEAR MAILBOXES, BOTTOM EDGE OF FRAME BETWEEN 48-62 INCHES ABOVE FLOOR AT PUBLIC HALL, 1st STORYDec 31, 2021

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Oct 22, 2026, 8:25 PM ET. BBL 3000557502.

Look up another building