14open violations
$3,750ECB/OATH penalties owed
0HPD class C (immediately hazardous)
188dto Energy and water benchmarking

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 67 days
Keep the report on file (not filed with DOB)
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 53,883 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 188 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 188 days
Annual filing
Facade inspection report (Cycle 10B) Applies
Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028
What this is

Buildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. DOB facade records for this building show $382,100 in late-filing or failure-to-file penalties. Agency page

Feb 21, 2028
in 484 days
No Cycle 10 report on record yet
Energy audit and retro-commissioning (2028) Likely applies
Local Law 87 · Calendar year 2028
What this is

Buildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 2808). Agency page

Dec 31, 2028
in 798 days
Next due 2028
Gas piping inspection (2029 cycle) Likely applies
Local Law 152 · During 2029
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 5 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2029
in 1163 days
Next cycle year 2029
Annual boiler inspection (1 boiler) Applies
Boiler inspection · By December 31 each year
What this is

Boilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-01-25 (Accepted). Agency page

On file2026 reports accepted

Open violations

ECB / OATH (3) · $3,750 owed
IssuedViolationHearingBalance
Jan 29, 2025Construction CLASS - 2
FAILURE TO COMPLY WITH COMMISSIONER'S ORDER CONTAINED IN SUMMONS #35664185P ISSUED ON 10/27/2022, AND FAILURE TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28.201.1 AND 1 RCNY 102-01(D)(2). AN ACCEPTABLE CERT
#37032709Y
May 30, 2025
IN VIOLATION
$0
Oct 27, 2022Construction CLASS - 2
FAILURE TO MAINTAIN EXTERIOR BLDG FACADE/WALLS&APPURTENANCE.NOTE:ATOI OBSERVED@EXP2S ELEVATION:SPALLED COPING STONE/DAMAGED MASONRY@8FL SECORNER FACING ROOF LEVEL:CRACKED STUCCO@PARAPET WALLS@MULTIPLE LOCATIONS
#35664185P
Jan 20, 2023
STIPULATION/IN-VIO
$1,250
Aug 29, 2022Construction CLASS - 1
FAILURE TO MAINTAIN BLDG EXTERIOR WALLS OR APPURTENANCES.NOTE:ATOI,OBSERVED CRACKED WINDOWPANE GLASSES ON EXP2S ELEVATION@5FL 1ST WINDOWLINE,7FL 2ND WINDOWLINE,9FL 2ND WINDOWLINE,&11FL 7TH WINDOWLINE BY E ELEVA
#35664278Y
Dec 16, 2022
IN VIOLATION
$2,500
DOB (0)

None open.

DOB NOW Safety (12)
IssuedViolationStatus
Sep 11, 2024Elevators FTF-VT-PER-CO
Violation Issued-Failure To File 2023 Periodic Inspection Report
Active
Sep 11, 2024Elevators FTF-VT-PER-CO
Violation Issued-Failure To File 2023 Periodic Inspection Report
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction
Active
Aug 25, 2023Elevators FTF-VT-PER-CO
Violation Issued-Failure To File 2022 Periodic Inspection Report
Active
Aug 25, 2023Elevators FTF-VT-PER-CO
Violation Issued-Failure To File 2022 Periodic Inspection Report
Active
Apr 25, 2023Boiler LBLVIO
VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT
Active
Jul 14, 2022Facades FISPHAZ
CYCLE 9B UNSAFE REPORT FILED
Active
Sep 5, 2019Facades FISP
CYCLE 8B UNSAFE REPORT FILED
Active
Sep 5, 2019Facades FISP
CYCLE 7B UNSAFE REPORT FILED
Active
Aug 30, 2013Facades FISPNRF
FAILED TO FILE FISP CYCLE 7B TECHNICAL REPORT BY 08/21/2012
Active
Mar 31, 2008Emergency Power FTF-EL-ENRF
Active
HPD (0)

None open.

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Oct 25, 2026, 6:40 PM ET. BBL 2028087502.

Look up another building