15 floors · 38,030 sq ft · built 1928 · class O6 · owner of record: Argus Realty 202 Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 48 days | Keep the report on file (not filed with DOB) |
| Facade inspection report (Cycle 10A) Applies Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $199,500 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2027 in 100 days | No Cycle 10 report on record yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 38,030 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 169 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 169 days | Annual filing |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 5 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1144 days | Next cycle year 2029 |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-06-30 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jun 17, 2024 | Construction CLASS - 2 A. C. 27-929.1, FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MOR #37028765R | Nov 7, 2024 IN VIOLATION | $6,250 |
| Feb 28, 2023 | Construction CLASS - 2 27-929.1 FAILURE TO COMPLETE INSTALLATION OF FULL SYSTEM OF AUTOMATIC SPRINKLERS & FILE FINAL SPRINKLER REPORT PREPARED BY REGISTERED DESIGNPROFESSIONAL IN OFFICE BLDG 100 FT OR MORE IN HEIGHT IN EXISTENCE ON #37025320K | Aug 10, 2023 IN VIOLATION | $0 |
| Nov 1, 2021 | Construction CLASS - 2 27-929.1 FAILURE TO COMPLETE INSTALLATION OF FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE FINAL SPRINKLER REPORT PREPARED BY REGISTERED DESIGN PROFESSIONAL IN OFFICE BUILDING 100 FEET OR MORE IN HEIGHT IN EXIST #37022702M | Jul 21, 2022 IN VIOLATION | $3,125 |
| Nov 15, 2019 | Construction CLASS - 2 A.C.27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL YSTSEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY REGISTRATION DESIGN PROFESSIONAL BY JULY 2019,IN AN OFFICE BUILDING 100 F #37016159Z | Jun 18, 2020 IN VIOLATION | $0 |
| Jun 7, 2018 | Construction CLASS - 2 FAILURE TO MAINTAIN EXTERIOR BLDG FACADE & APPURTENANCES, ROOF PARAPET MISSING RAILINGS(HEIGHT VERIES) FRONT PARAPET MISSING FLASHING EMR EXTERIOR OPENING NOT SECURE FIRE TOWER. OVERHEAD BEAM COVER CRACKED (TYP #35318942L | Jul 26, 2018 DEFAULT | $3,125 |
| May 18, 2018 | Local Law CLASS - 2 FAILURE TO SUBMIT ACCEPTABLE 8TH FOUND REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALLS AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL #801744. RMDY: SUBMIT REQUIRED TECHNICAL REPORT. #37010273P | Aug 30, 2018 DEFAULT | $3,125 |
| Issued | Violation | Status |
|---|---|---|
| Jul 15, 2021 | ELEVATOR #9027/703271 | DOB VIOLATION - ACTIVE |
| Feb 16, 2021 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) CYCLE 9A FAILURE TO CORRECT SWARMP CONDITIONS #00137 | DOB VIOLATION - ACTIVE |
| Jul 1, 2020 | ELEVATOR #9027/684822 | DOB VIOLATION - ACTIVE |
| Jul 1, 2020 | ELEVATOR #9027/684824 | DOB VIOLATION - ACTIVE |
| Jul 1, 2020 | ELEVATOR #9027/684823 | DOB VIOLATION - ACTIVE |
| Sep 6, 2019 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST #00905 | DOB VIOLATION - ACTIVE |
| Sep 6, 2019 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST #00907 | DOB VIOLATION - ACTIVE |
| Sep 6, 2019 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST #00906 | DOB VIOLATION - ACTIVE |
| Sep 3, 2019 | SPRINKLER FAILED TO FILE FINAL SPRINKLER REPORT BY JULY 1, 2019 #NRF00930 | DOB VIOLATION - ACTIVE |
| Jul 12, 2018 | ELEVATOR #9027/628404 | DOB VIOLATION - ACTIVE |
| May 31, 2018 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 8A TECHNICAL REPORT BY 02/21/2017 #01501 | DOB VIOLATION - ACTIVE |
| Sep 15, 2017 | ELEVATOR ANNUAL INSPECTION / TEST VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2016 INSPECTION/TEST #00579 | DOB VIOLATION - ACTIVE |
| Dec 1, 2016 | ELEVATOR ANNUAL INSPECTION / TEST VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2015 INSPECTION/TEST #00385 | DOB VIOLATION - ACTIVE |
| Jun 10, 2015 | ELEVATOR ANNUAL INSPECTION / TEST VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2014 INSPECTION/TEST #00502 | DOB VIOLATION - ACTIVE |
| Oct 31, 2014 | ELEVATOR ANNUAL INSPECTION / TEST VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2013 INSPECTION/TEST #00479 | DOB VIOLATION - ACTIVE |
| Jun 24, 2014 | ELEVATOR #9028/514355 | DOB VIOLATION - ACTIVE |
| Jun 24, 2014 | ELEVATOR #9028/514354 | DOB VIOLATION - ACTIVE |
| Jun 24, 2014 | ELEVATOR #9028/514353 | DOB VIOLATION - ACTIVE |
| May 30, 2014 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST #01214 | DOB VIOLATION - ACTIVE |
| Jan 31, 2013 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 7A TECHNICAL REPORT BY 02/21/2012 #00523 | DOB VIOLATION - ACTIVE |
| Oct 1, 2012 | ELEVATOR ANNUAL INSPECTION / TEST VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2011 INSPECTION/TEST #00593 | DOB VIOLATION - ACTIVE |
| Aug 15, 2012 | ELEVATOR #ACC101278 | DOB VIOLATION - ACTIVE |
| Apr 21, 2004 | LOCAL LAW 10/81 - ELEVATOR #00525 | DOB VIOLATION - ACTIVE |
| Mar 26, 2002 | LOCAL LAW 62/91 - BOILERS #02197 | DOB VIOLATION - ACTIVE |
| Aug 19, 1992 | CONSTRUCTION #MTF13RI | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 2, 2026 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2025 Cat1 Test Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Report | Active |
| Aug 25, 2023 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Report | Active |
| Feb 16, 2021 | Facades FISPFCS CYCLE 9A FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| Sep 6, 2019 | Elevators ACC1 | Active |
| Sep 6, 2019 | Elevators ACC1 | Active |
| Sep 6, 2019 | Elevators ACC1 | Active |
| Sep 3, 2019 | Sprinklers FTF-SP-FINAL | Active |
| May 20, 2019 | Elevators EVCAT5 | Active |
| May 31, 2018 | Facades FISPNRF FAILED TO FILE FISP CYCLE 8A TECHNICAL REPORT BY 02/21/2017 | Active |
| Sep 15, 2017 | Elevators EVCAT1 | Active |
| Dec 1, 2016 | Elevators EVCAT1 | Active |
| Jun 10, 2015 | Elevators EVCAT1 | Active |
| Oct 31, 2014 | Elevators EVCAT1 | Active |
| May 30, 2014 | Elevators ACC1 | Active |
| Jan 31, 2013 | Facades FISPNRF FAILED TO FILE FISP CYCLE 7A TECHNICAL REPORT BY 02/21/2012 | Active |
| Oct 1, 2012 | Elevators EVCAT1 | Active |
| Oct 1, 2012 | Elevators EVCAT1 | Active |
| Aug 15, 2012 | Elevators E | Active |
| Aug 15, 2012 | Elevators E | Active |
| Aug 15, 2012 | Elevators E | Active |
| Aug 15, 2012 | Elevators E | Active |
| Apr 21, 2004 | Elevators LL1081 | Active |
| Apr 21, 2004 | Elevators LL1081 | Active |
| Apr 21, 2004 | Elevators LL1081 | Active |
| Apr 21, 2004 | Elevators LL1081 | Active |
| Mar 26, 2002 | Boiler LL6291 | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Report | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 13, 2026, 9:53 PM ET. BBL 1007890044.