5 apartments · 5,533 sq ft · built 2025 · class C2 · owner of record: Roz Aig Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 66 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 66 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 82 days | Annual |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | No current registration found |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 3 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 797 days | Next cycle year 2028 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Sep 21, 2026 | Construction CLASS - 2 TEMPORARY CONSTRUCTION EQUIPMENT OR INSTALLATION ON SITE-EXPIRED PERMITRENEW PERMIT #39559398J | Nov 25, 2026 PENDING | $1,250 |
| Aug 28, 2026 | Construction CLASS - 2 AT THE TIME OF INSPECTION, NO ACCESS OBTAINED, CONTRACTOR FAILED TO COMPLY WITH COMMISSIONER'S ORDER. NO CORRECTIVE MEASURES ON RECORD FOR VIOLATION#039556033N ISSUED ON 7.01.2026... #39558497K | Nov 4, 2026 PENDING | $1,250 |
| Aug 28, 2026 | Construction CLASS - 2 AT THE TIME OF INSPECTION, NO ACCESS OBTAINED, CONTRACTOR FAILED TO COMPLY WITH COMMISSIONER'S ORDER. NO CORRECTIVE MEASURES ON RECORD FOR VIOLATION#039556034P ISSUED ON 7.01.2026 .. #39558499Y | Nov 4, 2026 PENDING | $1,250 |
| Aug 4, 2026 | Construction CLASS - 2 ATOI OBSERVED AT EXPOSURE 1 OF CONSTRUCTION SITE, FULLY ERECTED SIDEWALK SHED UNDER APPLICATION#B00981725 EXP DATE 07/02/2026. NOV ISSUED FOR EXPIRED TEMPORARY EQUIPMENT., RENEW PERMIT; RENEW PERMIT #39199107Y | Nov 25, 2026 PENDING | $1,250 |
| Jul 28, 2026 | Unknown CLASS - 2 UPON INSPECTION OF A NON-ACTIVE 4 STORY ALT CONSTRUCTION SITE I OBSERVED A FENCE INSTALLED AT EXPOSURE 1 THAT DID NOT FULLY ENCLOSE ON GOING CONSTRUCTION WORK AND POTENTIAL HAZARDS CONTRARY TO CODE 3307.7 FENCE #39557166L | Oct 7, 2026 IN VIOLATION | $2,500 |
| Jul 28, 2026 | Construction CLASS - 2 UPON INSPECTION I OBSERVED A SIDEWALK SHED INSTALLED AT EXPOS 1 INSTALLED CONTRARY TO CODE. 8FT MIN HEIGHT REQUIREMENT NOT MAINTAINED INFRONT OF ADJOINING PROPERTY AT EXPOS 2 CONTRARY TO CODE 3307.6.4.7. DRIVEW #39557168P | Oct 7, 2026 IN VIOLATION | $2,400 |
| Jul 28, 2026 | Unknown CLASS - 1 I OBSERVED A SIDEWALK SHED NOT MAINTAINED AND BEING USED IN SAFE CONDITION CONTRARY TO CODE 3307.6.5.1 SAFE CONDITION. MULTIPLE ROTTED MUDSILLS. LARGE ROLLING GATE UNSAFELY ATTACHED TO SHED CREATING A POTENTIAL #39557169R | Mar 5, 2027 PENDING | $5,000 |
| Jul 1, 2026 | Construction CLASS - 1 AT THE TIME OF INSPECTION OF THE ACTIVE 4-STORY JOB SITE, GUARDRAIL SYSTEMS WERE MISSING AT MULTIPLE LOCATIONS, INCLUDING ELEVATOR SHAFTS AND STAIRWAY OPENINGS, CREATING AN IMMEDIATE HAZARD TO WORKERS. STOP ALL #39556034P | Oct 21, 2026 | $5,000 |
| Jul 1, 2026 | Construction CLASS - 2 AT THE TIME OF INSPECTION OF THE ACTIVE 4-STORY JOB SITE, DEBRIS WAS OBSERVED THROUGHOUT THE SITE, CREATING TRIPPING, FIRE, AND SAFETY HAZARDS TO WORKERS, THE PUBLIC, AND PROPERTY. STOP ALL WORK, MAINTAIN PROPE #39556035R | Oct 21, 2026 PENDING | $1,250 |
| Jul 1, 2026 | Unknown CLASS - 1 AT THE TIME OF INSPECTION OF THE ACTIVE 4-STORY JOB SITE, OVERHEAD PROTECTION WAS MISSING AT EXPOSURE 1, THE CORNERS OF EXPOSURES 1/2 AND 1/4, AND THE REAR OF EXPOSURES 2 AND 4, CREATING AN IMMEDIATE HAZARD TO #39556033N | Oct 21, 2026 PENDING | $10,000 |
| Apr 24, 2026 | Unknown CLASS - 2 OBSERVED EXP #1 OFFICE TRAILER ON THE STREET, BUT NO DEPT OF TRANSPORTATION PERMITS ON SITE (BC 3307.1), NO JERSEY BARRIERS ENCLOSURE, CONTRARY TO SSP PLAN. STOP ALL STREET OPERATION ON EXP #1. OBTAIN DOT PERMI #39553453X | Jul 1, 2026 IN VIOLATION | $625 |
| Apr 24, 2026 | Construction CLASS - 1 OBSERVED EXP #3 FOUNDATION WALL IN PLACE BUT NO GUARDRAIL ON GRADE. FALLING OVER 6FT WAS A SURE HAZARD FOR WORKERS. STOP WORK ON EXP#3 AND STAY 10 FT FROM THE LEADING EDGE. #39553452Y | Jul 1, 2026 IN VIOLATION | $5,000 |
| Aug 21, 2025 | Construction CLASS - 1 OBSERVED SOE AT EXP#2 CONTRARY TO APPROVE DOCUMENTS. INDICATE 5 SOLDIER PILES. SITE ADD H PILE GO TO DETAIL 1A SOE-200., CONFORM WORK TO APPROVED CONSTRUCTION DOCUMENTS/AMENDMENTS; STOP ALL WORK UNDER PERMIT B0 #39157984K | Nov 6, 2026 | $2,500 |
| Jul 22, 2025 | Construction CLASS - 1 AT TIME OF INSPECTION OBSERVED: EXCAVATION WORK IN PROGRESS UNDER PERMIT# B00797380-S4-FO-EA UPON REVIEWED DEPARTMENT RECORD NOT EARTHWORK NOTIFICATION CREATING UNSAFE CONDITION FOR SAFETY MONITORING AND COMPLI #39542687P | Oct 1, 2025 IN VIOLATION | $2,500 |
| Mar 3, 2025 | Construction CLASS - 2 UPON ARRIVAL OF DEMO SAFETY MONITORING INSPECTION #B00896730 I OBSERVED A CLOSED JOB SITE. NO WORK BEING PERFORMED. UPON FURTHER RESEARCH I SAW THAT SIDEWALK SHED PERMIT IN PLACE WITH AN EXPIRED PERMIT. COMPLY #39537512R | Oct 6, 2025 IN VIOLATION | $1,250 |
| Mar 3, 2025 | Unknown CLASS - 2 REVIEWED DOBNOW SWS PERMIT B00981725 ,REVEALED SWS PERMIT EXPIRED 01/11/2025 AND WAS NOT RENEWED. RENEWED SWS PERMIT #39537532Y | Jun 18, 2026 IN VIOLATION | $1,250 |
| Mar 4, 2022 | Construction CLASS - 2 FAILURE TO COMPLY WITH COMMISSIONER'S ORDER CONTAINED IN SUMMONS/VIOL TION #35560905H ISSUED 05/18/21 AND FILE CERTIFICATE OF CORRECTION PU SUANT TO 28-201.1 AND 1RCNY 102-01.FOR WORK W/O A PERMIT.NOTE:JOB #B0 #35569467H | Oct 21, 2022 DEFAULT | $3,125 |
| Oct 2, 2020 | Zoning CLASS - 3 PLANTING REQUIREMENTS.PLANTING AREA AT FRONT YARD HAS BEEN REMOVED ANDFILLED IN WITH MASONRY TILES.THE ENTIRE FRONT YARD WAS OBSERVED COVERED.REM:COMPLY WITH PLANTING REQUIREMENTS AS PER ZONING. #35501372Y | Feb 10, 2021 DEFAULT | $0 |
| Issued | Violation | Status |
|---|---|---|
| Jan 19, 2021 | CONSTRUCTION AT TIME OF INSPECTION OBSERVED DAMAGE TO THE BACK EXTERIOR WALL DUE TO CONSTRUCTION CAUSED THE WALL TO SEPARATE AND SHIFT APPROXIMATELY 12 INCHES . AS A RESULT THE FIRE WALL BETWEEN THE PROPERTIES IS COMPROMIS EDAND UINSAFE TO RESIDE IN. THE RESULT OF DAMAGE DUE TO CONSTRUCTION HAS RENDERED THIS STR #CER02ND | DOB VIOLATION - ACTIVE |
None open.
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Sep 21, 2026 | ECB | Construction: TEMPORARY CONSTRUCTION EQUIPMENT OR INSTALLATION ON SITE-EXPIRED PERMITRENEW PERMIT | Open |
| Aug 28, 2026 | ECB | Construction: AT THE TIME OF INSPECTION, NO ACCESS OBTAINED, CONTRACTOR FAILED TO COMPLY WITH COMMISSIONER'S ORDER. NO CORRECTIVE MEASURES ON RECORD FOR VIOLATION#039556033N ISSUED ON 7.01.2026... | Open |
| Aug 28, 2026 | ECB | Construction: AT THE TIME OF INSPECTION, NO ACCESS OBTAINED, CONTRACTOR FAILED TO COMPLY WITH COMMISSIONER'S ORDER. NO CORRECTIVE MEASURES ON RECORD FOR VIOLATION#039556034P ISSUED ON 7.01.2026 .. | Open |
| Aug 4, 2026 | ECB | Construction: ATOI OBSERVED AT EXPOSURE 1 OF CONSTRUCTION SITE, FULLY ERECTED SIDEWALK SHED UNDER APPLICATION#B00981725 EXP DATE 07/02/2026. NOV ISSUED FOR EXPIRED TEMPORARY EQUIPMENT., RENEW PERMIT; RENEW PERMIT | Open |
| Jul 28, 2026 | ECB | Unknown: UPON INSPECTION OF A NON-ACTIVE 4 STORY ALT CONSTRUCTION SITE I OBSERVED A FENCE INSTALLED AT EXPOSURE 1 THAT DID NOT FULLY ENCLOSE ON GOING CONSTRUCTION WORK AND POTENTIAL HAZARDS CONTRARY TO CODE 3307.7 FENCE | Open |
| Jul 28, 2026 | ECB | Construction: UPON INSPECTION I OBSERVED A SIDEWALK SHED INSTALLED AT EXPOS 1 INSTALLED CONTRARY TO CODE. 8FT MIN HEIGHT REQUIREMENT NOT MAINTAINED INFRONT OF ADJOINING PROPERTY AT EXPOS 2 CONTRARY TO CODE 3307.6.4.7. DRIVEW | Open |
| Jul 28, 2026 | ECB | Unknown: I OBSERVED A SIDEWALK SHED NOT MAINTAINED AND BEING USED IN SAFE CONDITION CONTRARY TO CODE 3307.6.5.1 SAFE CONDITION. MULTIPLE ROTTED MUDSILLS. LARGE ROLLING GATE UNSAFELY ATTACHED TO SHED CREATING A POTENTIAL | Open |
| Jul 1, 2026 | ECB | Construction: AT THE TIME OF INSPECTION OF THE ACTIVE 4-STORY JOB SITE, GUARDRAIL SYSTEMS WERE MISSING AT MULTIPLE LOCATIONS, INCLUDING ELEVATOR SHAFTS AND STAIRWAY OPENINGS, CREATING AN IMMEDIATE HAZARD TO WORKERS. STOP ALL | Closed |
| Jul 1, 2026 | ECB | Construction: AT THE TIME OF INSPECTION OF THE ACTIVE 4-STORY JOB SITE, DEBRIS WAS OBSERVED THROUGHOUT THE SITE, CREATING TRIPPING, FIRE, AND SAFETY HAZARDS TO WORKERS, THE PUBLIC, AND PROPERTY. STOP ALL WORK, MAINTAIN PROPE | Open |
| Jul 1, 2026 | ECB | Unknown: AT THE TIME OF INSPECTION OF THE ACTIVE 4-STORY JOB SITE, OVERHEAD PROTECTION WAS MISSING AT EXPOSURE 1, THE CORNERS OF EXPOSURES 1/2 AND 1/4, AND THE REAR OF EXPOSURES 2 AND 4, CREATING AN IMMEDIATE HAZARD TO | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 26, 2026, 1:33 PM ET. BBL 3018220049.