3 floors · 53,000 sq ft · built 1936 · class W1 · owner of record: Nyc Department Of Education
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 60 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-12-15 (Accepted). Agency page | Dec 31, 2026 in 60 days | 2 of 2 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 53,000 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 181 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 181 days | Annual filing |
| Gas piping inspection (2027 cycle) Likely applies Local Law 152 · During 2027 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 11 is on the 2027 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2027 in 425 days | Next cycle year 2027 |
| Energy audit and retro-commissioning (2030) Likely applies Local Law 87 · Calendar year 2030 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 7410). Agency page | Dec 31, 2030 in 1521 days | Next due 2030 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| May 5, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED SMOKE DOORS NOT CLOSING PROPERLY AT: 3RD FLOOR STAIR G; GYM STAIRCASE; CLASSROOMS #209, #232. REMEDY: REPAIR AND/OR REPLACE. #35732827J | Jun 1, 2026 POP/IN-VIO | $0 |
| May 5, 2026 | Construction CLASS - 2 REISSUED ECB #35721003N. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: WATER PENETRATIONS AT BOILER ROOM-SEVERAL AREAS THROUGH FOUNDATION WALLS, FLOORS AND THROUGH OLD COAL CHUTE; AT BULKHEADSTA #35732826H | Jun 1, 2026 POP/IN-VIO | $0 |
| Jul 23, 2025 | Construction CLASS - 2 REISSUE#35684714J FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:AT BOILER ROOM WATER PENETRATION AT SEVERAL AREAS THROUGH FOUNDATION WALLS,FLOOR,SLAB AND THROUGH OLD COAL CHUTE APPROX.1 OF WATER.R #35721003N | Sep 9, 2025 POP/IN-VIO | $0 |
| Jul 18, 2024 | Construction CLASS - 2 REISSUE#35676250K FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED AT BOILER ROOM WATER PENETRATION AT SEVERAL AREAS THROUGH FOUNDATION WALLS,FLOOR SLAB AND THROUGH OLD COAL CHUTE.APPROX.1"OF WATER A #35684714J | Sep 24, 2024 POP/IN-VIO | $0 |
| Jul 25, 2023 | Construction CLASS - 2 REISSUED #35643596R: FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: AT BOILER ROOM, WATER INFILTRATED THROUGHOUT BUILDING ONTO AREA. REMEDY: REPAIR AND/OR REPLACE #35676250K | Oct 31, 2023 POP/IN-VIO | $0 |
| Jun 16, 2022 | Construction CLASS - 2 REISSUE#35577566N.FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.AT TIME OF INSPECTION OBSERVED BASEMENT LEVEL BOILER ROOM WALLS HAVEBECOME POROUS.REMEDY:REPAIR AND/OR REPLACE. #35643596R | Sep 13, 2022 POP/IN-VIO | $0 |
| Aug 5, 2021 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:OBSERVED DURING INSPECTION OF BASEMENT BOILER ROOM,WALLS HAVE BECOME POUROUS ALLOWING WATER INTO THE BASEMENT. #35577566N | Dec 7, 2021 POP/IN-VIO | $0 |
| Jul 13, 2020 | Construction CLASS - 2 FAILURE TO MAINTAIN BLDG IN CODE COMPLIANT MANNER. NOTED: AT CELLAR BOILER ROOM,FOUNDATION WALL HAS BECOME FORMS ALLOWING THE WATER INTO THECELLAR. REMEDY: MAKE NECESSARY REPAIRS. #35500845K | Oct 27, 2020 POP/IN-VIO | $0 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Jan 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle D (premises is in Community District 11) | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 1, 2026, 8:02 AM ET. BBL 4074100001.