4 floors · 22,483 sq ft · built 1926 · class O5 · owner of record: Zdravos Realty Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 50 days | Keep the report on file (not filed with DOB) |
| Gas piping inspection (2027 cycle) Likely applies Local Law 152 · During 2027 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 11 is on the 2027 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2027 in 415 days | Next cycle year 2027 |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-10-09 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 23, 2025 | Construction CLASS - 2 OBSERVED ON THE GROUND FLOOR AT LIMON PIZZERIA HALAL STORE. NEW WASTE LINES WERE INSTALLED FOR A HAND SINK AND A THREE COMPARTMENT SINK. ALL WORK COMPLETED 100 PERCENT NO PLUMBING PERMIT ON FILE, OBTAIN ALL PER #39154717M | Oct 2, 2025 STIPULATION/IN-VIO | $0 |
| Jul 23, 2025 | Construction CLASS - 2 OBSERVED ON THE GROUND FLOOR AT LIMON PIZZERIA HALAL STORE. INSTALLED PVC WASTE LINES IN BATHROOM WHICH CONTRARY TO CODE SECTION PC 1101.10, REPAIR AND/OR REPLACE #39154716K | Oct 2, 2025 STIPULATION/IN-VIO | $0 |
| Jul 27, 2023 | Construction CLASS - 2 OBSERVED IN BASEMENT HAVE CORROSION ON GAS PIPE WHICH CONTRARY TO FGC 404.11.1, REPAIR AND/OR REPLACE #39091192N | Oct 5, 2023 ADMIT/IN-VIO | $0 |
| Jul 27, 2023 | Construction CLASS - 2 OBSERVED IN BASEMENT REMOVAL OF GAS PIPING NO PERMITS, OBTAIN ALL PERMITS #39091193P | Oct 5, 2023 ADMIT/IN-VIO | $0 |
| Jan 12, 2005 | Construction Non-Hazardous WORK DOES NOT CONFORM TO APPROVED PLANS NOTED:APPROVED PLANS UNDER APPL#103789848, DIRECTIVE 14 INDICATE THAT PIPE ESCAPES AT EAST SIDE OF BLDG IS EXISTING TO REMAIN NOTE THAT THERE ARE NO PIPE ESCAPES ON EAST #34455788R | Apr 21, 2005 IN VIOLATION | $0 |
None open.
None open.
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 11, 2026, 7:40 AM ET. BBL 1017490050.