Brooklyn · Block 8281 · Lot 24 · 11236

1871 Rockaway Parkway

1 floors · 44,936 sq ft · built 1961 · class K6 · owner of record: Seaview Comp

50open violations
$0ECB/OATH penalties owed
0HPD class C (immediately hazardous)
47dto Annual boiler inspection (1 boiler)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 47 days
Keep the report on file (not filed with DOB)
Annual boiler inspection (1 boiler) Applies
Boiler inspection · By December 31 each year
What this is

Boilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2024-02-09 (Accepted). Agency page

Dec 31, 2026
in 47 days
1 of 1 without an accepted 2026 report yet
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 44,936 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 168 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 168 days
Annual filing
Gas piping inspection (2029 cycle) Likely applies
Local Law 152 · During 2029
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 18 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2029
in 1143 days
Next cycle year 2029

Open violations

ECB / OATH (0)

None open.

DOB (20)
IssuedViolationStatus
Nov 14, 2025HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
#01331
DOB VIOLATION - ACTIVE
Nov 14, 2025HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
#00507
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION
#00941
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
#04461
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
#03318
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION
#02105
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION
#00990
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION
#02205
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION
#03387
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION
#04538
DOB VIOLATION - ACTIVE
Apr 25, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION
#01864
DOB VIOLATION - ACTIVE
Apr 25, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION
#00733
DOB VIOLATION - ACTIVE
Dec 1, 2021FAILURE TO POST ENERGY GRADE/SCORE
FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
#2102907
DOB VIOLATION - ACTIVE
Apr 29, 2021FAILURE TO POST ENERGY GRADE/SCORE
FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
#2004048
DOB VIOLATION - ACTIVE
Mar 16, 2020HIGH PRESSURE BOILER
VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION
#00840
DOB VIOLATION - ACTIVE
Mar 16, 2020HIGH PRESSURE BOILER
VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION
#00802
DOB VIOLATION - ACTIVE
Dec 29, 2018ELEVATOR

#9028/643559
DOB VIOLATION - ACTIVE
Jun 22, 2018HIGH PRESSURE BOILER
VIOLATION ISSUED FOR FAILURE TO FILE 2016 ANNUAL HIGH PRESSURE BOILER INSPECTION
#00268
DOB VIOLATION - ACTIVE
Dec 27, 2017ELEVATOR

#9028/618818
DOB VIOLATION - ACTIVE
Jun 23, 2017HIGH PRESSURE BOILER
VIOLATION ISSUED FOR FAILURE TO FILE 2015 ANNUAL HIGH PRESSURE BOILER INSPECTION
#00281
DOB VIOLATION - ACTIVE
DOB NOW Safety (30)
IssuedViolationStatus
Oct 2, 2026Elevators FTF-VT-PER-CO
Violation Issued-Failure To File 2025 Periodic Inspection Report
Active
Oct 2, 2026Elevators FTF-VT-CAT1-CO
Violation Issued-Failure To File 2025 Cat1 Test Report
Active
Nov 14, 2025Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
Active
Nov 14, 2025Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
Active
Aug 29, 2025Elevators FTF-VT-PER-CO
Violation Issued-Failure To File 2024 Periodic Inspection Report
Active
Aug 29, 2025Elevators FTF-VT-CAT1-CO
Violation Issued-Failure To File 2024 Cat1 Test Report
Active
Sep 11, 2024Elevators FTF-VT-CAT1-CO
Violation Issued-Failure To File 2023 Cat1 Test Report
Active
Sep 11, 2024Elevators FTF-VT-PER-CO
Violation Issued-Failure To File 2023 Periodic Inspection Report
Active
Aug 25, 2023Elevators FTF-VT-PER-CO
Violation Issued-Failure To File 2022 Periodic Inspection Report
Active
Aug 11, 2023Elevators FTF-VT-CAT1-CO
Violation Issued-Failure To File 2022 Cat1 Test Report
Active
Aug 11, 2023Elevators FTF-VT-CAT1-CO
Violation Issued-Failure To File 2021 Cat1 Test Report
Active
Aug 11, 2023Elevators FTF-VT-CAT1-CO
Violation Issued-Failure To File 2019 Cat1 Test Report
Active
Aug 11, 2023Elevators FTF-VT-CAT1-CO
Violation Issued-Failure To File 2020 Cat1 Test Report
Active
Aug 11, 2023Elevators FTF-VT-CAT1-CO
Violation Issued-Failure To File 2018 Cat1 Test Report
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION
Active
Apr 25, 2023Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Apr 25, 2023Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Dec 1, 2021Energy Grade - LL33 FTP-EN-EGRDEA
Active
Apr 29, 2021Energy Grade - LL33 FTP-EN-EGRDEA
Active
Mar 16, 2020Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Mar 16, 2020Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Jun 22, 2018Boiler HBLVIO
VIOLATION ISSUED FOR FAILURE TO FILE 2016 ANNUAL HIGH PRESSURE BOILER INSPECTION
Active
Jun 23, 2017Boiler HBLVIO
VIOLATION ISSUED FOR FAILURE TO FILE 2015 ANNUAL HIGH PRESSURE BOILER INSPECTION
Active
HPD (0)

None open.

Issued in the last 120 days

DateSourceWhatNow
Oct 2, 2026DOB SafetyElevators: Violation Issued-Failure To File 2025 Periodic Inspection ReportOpen
Oct 2, 2026DOB SafetyElevators: Violation Issued-Failure To File 2025 Cat1 Test ReportOpen

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Nov 14, 2026, 3:56 AM ET. BBL 3082810024.