4 floors · 9 apartments · 7,482 sq ft · built 1920 · class C4 · owner of record: 2 Berkley Realty Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | Registration expired 2026-09-01 |
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 6 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 65 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 65 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 65 days | Annual |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-12-15 (Accepted). Agency page | Dec 31, 2026 in 65 days | 1 of 1 without an accepted 2026 report yet |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 81 days | Annual |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Mar 17, 2022 | Construction CLASS - 1 FAILURE TO PROVIDE SIDEWAK SHED WHERE REQUIRED TO PROTECT PUBLIC.NOTED:AT TIME OF INSPECTION OBSERVED AT EXP #1 NORTH ELEVATION SWS DOES NOT EXTEND FULL LENGTH OF EXP #1 AS WAS CITED IN SUMMONS #35640204P TO TH #35647399X | May 22, 2023 IN VIOLATION | $25,000 |
| Mar 17, 2022 | Construction CLASS - 1 FAILURE TO MAINTAIN EXTERIOR BUILDING IN CODE COMPLIANT MANNER.NOTED:AT TIME OF INSPECTION OBSERVED HAZARDOUS CONDITION STILL EXISTS FROM PREVIOUS INSPECTION CITED IN PREVIOUS SUMMONS #3564591X DETERIORATING MA #35647398Y | Sep 7, 2022 IN VIOLATION | $4,373 |
| Feb 8, 2022 | Construction CLASS - 1 FAILURE TO MAINTAIN EXTERIOR BLDG FACADE & APPURTENANCES IN A CODE COMPLIANT MANNER.AS NOTED CONDITIONS FROM SUMMONS #35640591Y STILL EXIST WHILE INCLUDE DEFECTIVE STORE SILLS,CRACKS ON STAGE INADEQUATE REPAIRS #35640203N | Jul 27, 2022 IN VIOLATION | $1,012 |
| Feb 8, 2022 | Construction CLASS - 1 FAILURE TO PROVIDE SIDEWALK SHED WHERE REQUIRED.AT TIME OF INSPECTION SIDEWALK SHED DOES NOT EXTEND THE ENTIRE FACADE ON EXP.#1 BERKLEY PLACE CONDITION EXIST FROM SUMMONS #35640592X ISSUED ON 12/21/21.REMEDY:PR #35640204P | May 1, 2023 IN VIOLATION | $1,189 |
| Dec 21, 2021 | Construction CLASS - 1 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.AT NORTH ELEVATION EXP #1 OBSERVED DEFECTIVE STONE AND INADEQUATE REPAIR ABOVE WINDOW AT 3RD FLOOR.REMEDY:REPAIR AND/OR REPLACE. #35640591Y | Jun 1, 2022 IN VIOLATION | $157 |
| Dec 21, 2021 | Construction CLASS - 1 FAILURE TO PROVIDE UNOBSTRUCTED EXIT PASSAGEWAY AT NORTH ELEVATION EXP #1 OBSERVED PLANTS POTS OBSTRUCTING EXIT PASSAGEWAY AND 2ND FLOOR.REMEDY:REMOVE EGRESS OBSTRUCTION. #35640593H | Jun 1, 2022 IN VIOLATION | $10 |
| Sep 29, 2020 | Construction CLASS - 1 WORK W/O PERMIT. RENOVATION OF COMMERCIAL SPACE EXCEEDING WORK FILED FOR,INCLUDING BUT NOT LIMITED TO THE REMOVAL OF FIRE STOPPING. REMEDY:OBTAIN PERMIT. STOP ALL WORK EXCEPT TO MAKE SITE SAFE CONTACT DOB AT (7 #35537439Y | Aug 25, 2022 IN VIOLATION | $2,500 |
| Sep 29, 2020 | Construction CLASS - 1 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. RENOVATION OF COMMERCIAL SPACE EXCEEDING SAFETY CONDITIONS. BC 712, A.C. 27-345. REMEDY: MAINTAIN FIRE STOPPING #35537440L | Aug 25, 2022 IN VIOLATION | $2,500 |
| Issued | Violation | Status |
|---|---|---|
| May 11, 2022 | FAIL TO CERTIFY CLASS 1 FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION #00324 | DOB VIOLATION - ACTIVE |
| Jun 1, 1994 | LOCAL LAW 62/91 - BOILERS #18195 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #31468 | DOB VIOLATION - ACTIVE |
| Jun 1, 1993 | LOCAL LAW 62/91 - BOILERS #18194 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| May 11, 2022 | AEUHAZ FTC-AEU-HAZ | Active |
| Jun 1, 1994 | Boiler LL6291 | Active |
| Jun 1, 1993 | Boiler LL6291 | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)