4 floors · 94,000 sq ft · built 1942 · class W1 · owner of record: Nyc Department Of Parks And Recreation
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 66 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 94,000 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 187 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 187 days | Annual filing |
| Gas piping inspection (2027 cycle) Likely applies Local Law 152 · During 2027 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 11 is on the 2027 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2027 in 431 days | Next cycle year 2027 |
| Energy audit and retro-commissioning (2028) Likely applies Local Law 87 · Calendar year 2028 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 1668). Agency page | Dec 31, 2028 in 797 days | Next due 2028 |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-05-13 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 22, 2026 | Construction CLASS - 2 REISSUE:35725157Y FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.GAS ROOM HAS STEP CRACKS.REM:COMPLY WITH CODE. #35734956P | Aug 20, 2026 POP/IN-VIO | $0 |
| Jul 22, 2026 | Construction CLASS - 2 REISSUE#35725162Z FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.FLASHING AT ROOF IN DISREPAIR.REM:COMPLY WITH CODE. #35734953J | Aug 20, 2026 POP/IN-VIO | $0 |
| Sep 12, 2025 | Construction CLASS - 2 RE-ISSUE #35674844Z. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. AT THE TIME OF INSPECTION, RUNNING STEP CRACKS WERE OBSERVED AT VARIOUS LOCATIONS IN VESTIBULE OF EXIT "8". GAS METER ROOM HAS STEP CR #35725157Y | Oct 22, 2025 POP/IN-VIO | $0 |
| Sep 12, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING WALL(S) OR APPURTENANCES. AT THE TIME OF INSPECTION, COUNTER FLASHING AROUND BULKHEAD IS IN DISREPAIR. REMEDY: REPAIR AND/OR REPLACE. #35725162Z | Oct 22, 2025 POP/IN-VIO | $0 |
| Aug 22, 2025 | Boilers CLASS - 2 FOUND FEDERAL FST-250 DUAL FUEL BOILER WITH EXPOSED WIRING, SIGHT GLASS MISSING ON BOTH BOILERS ON REAR CHAMBER DOOR, BOILER ROOM DOOR NOT SELF CLOSING, POOR LIGHTING IN BOILER ROOM SEVERAL LIGHT FIXTURES NO GO #39158104H | Aug 25, 2025 POP/IN-VIO | $0 |
| Jul 13, 2023 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: AT 1ST FLOOR BY EXIT 8 AND GAS METER ROOM, BOTH HAS RUNNING STEP CRACKS IN VAIROUS AREAS THROUGHOUT. ALSO, 2ND FLOOR STAIR F HAS CRACKS ON THE BEAMS #35674844Z | Sep 26, 2023 POP/IN-VIO | $0 |
| Aug 2, 2021 | Construction CLASS - 2 REISSUE #35490843K FAILURE TO MAINTAIN BUILDING IN CODEC OMPLIANT MANNER NOTED OBSERVED AT BOTH ROOF LEVEL SEVERAL LARGE BUBBLES AND DETEIORATING ROOF MEMBRANCE AND LOOSE FLASHING REPAIR AND OR REPLACE #35584436K | Nov 4, 2021 DEFAULT | $3,125 |
| Apr 22, 2021 | Elevators CLASS - 1 CLASS 1 NO DLM INSTALLED IN THIS CONTROLLER AS MANDATED BY 3.10.12 OF APPENDIX K3 OF THE 2014 NYCBC FILE APPLICATION AND INSTALL DLM #39039899Z | May 10, 2021 POP/IN-VIO | $0 |
| May 19, 2014 | Unknown CLASS - 2 WORK WITHOUT PERMIT. AT ROOM 431 "HOLDING ROOM", INSTALLED FULL HEIGHT PARTITION CREATING A STORAGE ROOM WITH CEILING LIGHT FIXTURES PASSING THROUGH. REMEDY: OBTAIN PERMIT IF FEASIBLE & COMPLY WITH BLDG CODE O #35094800X | Jul 31, 2014 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #23077 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #23078 | DOB VIOLATION - ACTIVE |
| Oct 4, 2010 | ELEVATOR #9027/357947 | DOB VIOLATION - ACTIVE |
| Nov 18, 2009 | ELEVATOR #9011/318508 | DOB VIOLATION - ACTIVE |
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #01462 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Jan 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle D (premises is in Community District 11) | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Affirmation of Correction | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Report | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Jul 22, 2026 | ECB | Construction: REISSUE:35725157Y FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.GAS ROOM HAS STEP CRACKS.REM:COMPLY WITH CODE. | Open |
| Jul 22, 2026 | ECB | Construction: REISSUE#35725162Z FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.FLASHING AT ROOF IN DISREPAIR.REM:COMPLY WITH CODE. | Open |