2 floors · 2 apartments · 2,680 sq ft · built 1910 · class B1 · owner of record: 1854 47 Street Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual property registration Check HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 309 days | Required only if the owner doesn't live there |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Oct 21, 2026 | Construction CLASS - 2 OBSERVED AFTER HOUR WORK IN PROGRESS AT 6:25PM ON 10/21/2026 WITH NO AFTER HOUR HOUR VARIANCE., OBTAIN AFTER HOURS VARIANCE; OBTAIN AHV PERMIT. #39208839L | Jan 6, 2027 PENDING | $1,250 |
| Oct 20, 2026 | Unknown CLASS - 1 ON SECOND FLOOR AT LAUNDRY ROOM OBSERVED AN OPEN ELECTRICAL PANEL. PANEL MISSING COVER. EXPOSED WIRES, BREAKERS CONNECTIONS. POTENTIAL FOR SHOCK OR ELECTRICUTION. NO ELECTRICIAN OBSERVED ON SITE., COMPLY WITH E #39208549N | Jan 6, 2027 PENDING | $1,600 |
| Oct 20, 2026 | Construction CLASS - 1 LARGE STEEL DECK AT EXP 3 (REAR) APPROX 15' ABOVE GRADE WITH NO GAURD RAILS. POTENTIAL FOR FALL SERIOUS I NJURY OR DEATH TO PUBLIC, FIRST RESPONDERS ETC. DECK IS ACCESSABLE FROM UNLOCKED DOOR AT SECOND FLOOR., #39208556L | Jan 6, 2027 PENDING | $5,000 |
| Oct 20, 2026 | Construction CLASS - 1 OBSERVED ADDITIONAL PLUMBING WORK IN VIOLATION OF PSWO ISSUED ON 09/18/2026 UNDER COMPLAINT #3A81092. OBSERVED GAS ON DEMAND WATER HEATER (HEATER HAS DATE 10/14/2026) WRITTEN ON IT AS INSTALL DATE), GAS DRYER A #39208550K | Jan 6, 2027 PENDING | $10,000 |
| Sep 29, 2026 | Construction CLASS - 2 ATOI OBSERVED A WORK WITHOUT A PERMIT AT REAR YARD , THE CAR GARAGE BEEN MODIFIED NEW FRAMING AND 2 SWING DOORS INSTALLED, NO PERMIT FOUND ON FILE FOR THE WORK, THIS ELIMENATE THE USE OF THE CAR GARAGE SINCE EN #39206047Y | Dec 9, 2026 PENDING | $1,250 |
| Sep 18, 2026 | Construction CLASS - 1 WORK WITHOUT PERMIT. PSWO ISSUED FOR ALL PLUMBING WORK BEING DONE .ATOI OBSERVED IN THE INTERIOR OF THE RESIDENT ON THE 2ND FLOOR NEWLY INSTALLED PLUMBING WORK IN THE KITCHEN AND BATHROOMS CONSISTING OF COOPER #39204652N | Nov 25, 2026 PENDING | $2,500 |
| Sep 18, 2026 | Unknown CLASS - 1 WORK WITHOUT PERMIT. PSWO ISSUED FOR ALL ELECTRICAL WORK BEING DONE . ATOI AT 9 AM OBSERVED IN THE INTERIOR OF THE RESIDENT ON THE SECOND FLOOR NEWLY INSTALLED ELECTRICAL WORK CONSISTING OF BW WIRING, CEILING L #39204651L | Nov 25, 2026 PENDING | $2,500 |
| Aug 2, 2026 | Construction CLASS - 1 WORK WITHOUT PERMIT. AT TIME OF INSPECTION AT EXPOSURE #4 I OBSERVED A WORKER ON A M,AN LIFT PERFORMING MASONRY WORK AND AT EXPOSURE #3 THERE IS STEEL WORK BEING PERFORMED BY INSTALLING METAL BEAMS BEAMS. WHILE #39198749L | May 11, 2027 | $6,250 |
| Aug 2, 2026 | Construction CLASS - 1 UNLAWFUL ACTS. CONTINUING TO WORK WHILE UNDER A STOP WORK ORDER. AT EXPOSURE 4(RIGHT) ILLEGAL WORK CONTINUED AFTER PSWO ON 06/26/2026, OBSERVED 2 WORKERS AT EXTERIOR FACADE MASONRY WORK IN PROGRESS, INTERIOR AC #39198750Z | May 11, 2027 PENDING | $25,000 |
| Jun 26, 2026 | Construction CLASS - 1 OBSERVED @ EXPO 4 TWO WINDOWS HAVE BEEN SEALED WITH CMU BLOCKS. BLOCKING WIDOWS AND POTENTIALLY CHANGE OF INTERIOR CONFIGURATION LAYOUT OF INTERIOR IS UNKNOWN. NO PERMITS ON FILE FOR SCOPE OF WORK., OBTAIN PERM #39194010P | Sep 2, 2026 IN VIOLATION | $2,500 |
None open.
None open.
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 21, 2026 | ECB | Construction: OBSERVED AFTER HOUR WORK IN PROGRESS AT 6:25PM ON 10/21/2026 WITH NO AFTER HOUR HOUR VARIANCE., OBTAIN AFTER HOURS VARIANCE; OBTAIN AHV PERMIT. | Open |
| Oct 20, 2026 | ECB | Unknown: ON SECOND FLOOR AT LAUNDRY ROOM OBSERVED AN OPEN ELECTRICAL PANEL. PANEL MISSING COVER. EXPOSED WIRES, BREAKERS CONNECTIONS. POTENTIAL FOR SHOCK OR ELECTRICUTION. NO ELECTRICIAN OBSERVED ON SITE., COMPLY WITH E | Open |
| Oct 20, 2026 | ECB | Construction: LARGE STEEL DECK AT EXP 3 (REAR) APPROX 15' ABOVE GRADE WITH NO GAURD RAILS. POTENTIAL FOR FALL SERIOUS I NJURY OR DEATH TO PUBLIC, FIRST RESPONDERS ETC. DECK IS ACCESSABLE FROM UNLOCKED DOOR AT SECOND FLOOR., | Open |
| Oct 20, 2026 | ECB | Construction: OBSERVED ADDITIONAL PLUMBING WORK IN VIOLATION OF PSWO ISSUED ON 09/18/2026 UNDER COMPLAINT #3A81092. OBSERVED GAS ON DEMAND WATER HEATER (HEATER HAS DATE 10/14/2026) WRITTEN ON IT AS INSTALL DATE), GAS DRYER A | Open |
| Sep 29, 2026 | ECB | Construction: ATOI OBSERVED A WORK WITHOUT A PERMIT AT REAR YARD , THE CAR GARAGE BEEN MODIFIED NEW FRAMING AND 2 SWING DOORS INSTALLED, NO PERMIT FOUND ON FILE FOR THE WORK, THIS ELIMENATE THE USE OF THE CAR GARAGE SINCE EN | Open |
| Sep 18, 2026 | ECB | Construction: WORK WITHOUT PERMIT. PSWO ISSUED FOR ALL PLUMBING WORK BEING DONE .ATOI OBSERVED IN THE INTERIOR OF THE RESIDENT ON THE 2ND FLOOR NEWLY INSTALLED PLUMBING WORK IN THE KITCHEN AND BATHROOMS CONSISTING OF COOPER | Open |
| Sep 18, 2026 | ECB | Unknown: WORK WITHOUT PERMIT. PSWO ISSUED FOR ALL ELECTRICAL WORK BEING DONE . ATOI AT 9 AM OBSERVED IN THE INTERIOR OF THE RESIDENT ON THE SECOND FLOOR NEWLY INSTALLED ELECTRICAL WORK CONSISTING OF BW WIRING, CEILING L | Open |
| Aug 2, 2026 | ECB | Construction: WORK WITHOUT PERMIT. AT TIME OF INSPECTION AT EXPOSURE #4 I OBSERVED A WORKER ON A M,AN LIFT PERFORMING MASONRY WORK AND AT EXPOSURE #3 THERE IS STEEL WORK BEING PERFORMED BY INSTALLING METAL BEAMS BEAMS. WHILE | Closed |
| Aug 2, 2026 | ECB | Construction: UNLAWFUL ACTS. CONTINUING TO WORK WHILE UNDER A STOP WORK ORDER. AT EXPOSURE 4(RIGHT) ILLEGAL WORK CONTINUED AFTER PSWO ON 06/26/2026, OBSERVED 2 WORKERS AT EXTERIOR FACADE MASONRY WORK IN PROGRESS, INTERIOR AC | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)