Manhattan · Block 864 · Lot 25 · 10016

185 Madison Avenue

16 floors · 79,961 sq ft · built 1911 · class O6 · owner of record: 185 Madison Avenue,

38open violations
$9,335ECB/OATH penalties owed
0HPD class C (immediately hazardous)
60dto Gas piping inspection (2026 cycle)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Gas piping inspection (2026 cycle) Likely applies
Local Law 152 · During 2026
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 6 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2026
in 60 days
Due this year
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 60 days
Keep the report on file (not filed with DOB)
Facade inspection report (Cycle 10A) Applies
Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027
What this is

Buildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $720,000 in late-filing or failure-to-file penalties. Agency page

Feb 21, 2027
in 112 days
No Cycle 10 report on record yet
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 79,961 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 181 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 181 days
Annual filing
Energy audit and retro-commissioning (2034) Likely applies
Local Law 87 · Calendar year 2034
What this is

Buildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 864). Agency page

Dec 31, 2034
in 2982 days
Next due 2034

Open violations

ECB / OATH (10) · $9,335 owed
IssuedViolationHearingBalance
Apr 29, 2026Construction CLASS - 2
UPON INSPECTION I OBSERVED A SIDEWALK SHED INSTALLED AT EXPOS 1&4 WITH NO SIDEWALK SHED PARAPET INFORMATION PANEL INSTALLED AT EXPOS 4 CONTRARY TO CODE 3301.9.2.2 POSTING OF SIDEWALK SHED PARAPET INFORMATION PA
#39553616L
May 24, 2027
DEFAULT
$1,280
Apr 29, 2026Construction CLASS - 2
UPON INSPECTION I OBSERVED A SIDEWALK SHED INSTALLED AT EXPOS 1 CONTRARY TO CODE. INADEQUATE COVERAGE OF CORRUGATED METAL UNDER THE WOOD DECK NEAR THE BUILDING AND ABOVE THE BUILDING ENTRIES. LARGE GAPS OF UNPR
#39553608L
Jun 8, 2027
DEFAULT
$5,000
Apr 29, 2026Construction CLASS - 2
I OBSERVED A SIDEWALK SHED INSTALLED AT EXPOS 1&4 CONTRARY TO CODE. MUDSILLS NOT SECURED TO VERTICAL MEMBERS AT EXPOS 4 CONTRARY TO 3307.6.4.10 . 8FT HEIGHT NOT MAINTAINED IN PATHWAY AT EXPOS 4 CONTRARY TO 3307
#39553614H
May 20, 2027
DEFAULT
$2,430
Apr 29, 2026Unknown CLASS - 2
UPON INSPECTION I OBSERVED A SIDEWALK SHED AT EXPOS 1&4 NOT MAINTAINED ACCORDING TO CODES 3307.6.5.1 & 3307.6.5.3 . I OBSERVED MULTIPLE UNPROTECTED BOLTS IN PATHWAY AT EXPOS 1&4. ADVERTISEMENTS HUNG BELOW THE D
#39553619R
Oct 1, 2026
IN VIOLATION
$625
Jun 17, 2024Construction CLASS - 2
AC27-929.1 FAILURE TO COMPLETE INSTALLATION OF FULL SYSTEM OF AUTOMATIC SPRINKLERS & FILE FINAL SPRINKLER REPORT PREPARED BY REGISTEREED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN HEIGHT IN E
#37028812K
Nov 7, 2024
IN VIOLATION
$0
Feb 28, 2023Construction CLASS - 2
27-929.1 FAILURE TO COMPLETE INSTALLATION OF FULL SYSTEM OF AUTOMATIC SPRINKLERS & FILE FINAL SPRINKLER REPORT PREPARED BY REGISTERED DESIGN PROFESSIONAL IN OFFICE BLDG 100 FT OR MORE IN HEIGHT IN EXISTENCE ON
#37025256P
Mar 21, 2024
IN VIOLATION
$0
Dec 9, 2022Local Law CLASS - 2
FAILURE TO SUBMIT ACCEPTABLE REQUIRED CYCLE 9A REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL & APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL #902483.REMEDY:SUBMIT ACCEPTABLE REQUIRED TE
#37024786H
Mar 2, 2023
IN VIOLATION
$0
Nov 1, 2021Construction CLASS - 2
SEC. AC 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEMOF AUTOMATIC SPRINKLERS & FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BLDG 100 FEET OR MORE IN
#37022594Y
Jul 21, 2022
IN VIOLATION
$0
Jul 13, 2020Construction CLASS - 2
SEC. AC 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEMOF AUTOMATIC SPRIKLERS & FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL BY 7/1/19,IN AN OFFICE BLDG 100 FEET OR
#37019802M
Apr 29, 2021
ADMIT/IN-VIO
$0
Nov 15, 2019Construction CLASS - 2
SEC. A.C.27-929.1,FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS & FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL BY 7/1/19,IN AN OFFICE BLDG 100 FEET
#37016369R
Jun 18, 2020
IN VIOLATION
$0
DOB (19)
IssuedViolationStatus
Sep 18, 2024CONSTRUCTION
FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER. AT EXPOSURE (NORTH ELEVATION) IT WAS BULGING PARAPET, CRACK ON BRICK FACADE REMEDY REPAIR AND/OR REPLACE
#SR10601
DOB VIOLATION - ACTIVE
Sep 18, 2024CONSTRUCTION
FTM BLDG IN A CODE COMPLIANT MANNER. AT EXPOSURE 2 (NORTH ELEVATION) IT WAS OBSERVED BULDGING PARAPET, CRACK ON BRICK FACADE. REMEDY: REPAIR AND OR REPLACE
#SR10601MA
DOB VIOLATION - ACTIVE
Apr 24, 2024CONSTRUCTION
FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER: OBSERVED AT EXP 1 CRACK BRICK AT 6TH FLOOR & SPALLING AT PARAPET NORTH WEST. EXPOSURE 4 DAMAGED JOINT AND SPALLING AT LOWER FLOORS. ROOF AREA OPENING AT MAIN ROOF PARAPET EXPOSURE 2. REMEDY: REPAID AND/OR REPLACE
#SR0601NS
DOB VIOLATION - ACTIVE
Dec 29, 2023CONSTRUCTION
FAILURE TO MAINTAIN BUILDING IN A CODE COMPLIANT MANNER INADEQUATE RAILING AT ROOF LEVEL NOT SECURE AT EXPOSURE#1 OBSERVED A VERTICAL CRA CRACK ABOUT 6 STORY UP REMEDY:REPAIR AND OR REPLACE
#SR10601DO
DOB VIOLATION - ACTIVE
Dec 19, 2023CONSTRUCTION
FAILURE TO MAINTAIN BUILDING IN A CODE COMPLIANT MANNER INADEQUATE RAILING AT ROOF LEVEL REMEDY:REPAIR AND OR REPLACE
#SR10601DO
DOB VIOLATION - ACTIVE
Jul 20, 2023CONSTRUCTION
FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.OBSERVEDSPALLING AND ERODED JOINTS AT EXPOSURE#3 WALL OPENING AT HIGH PARAPET,SPALLING AND ERODED JOINTS AT EXPOSURE #2 REMEDY:MAINTAIN BUILDING REPAIR AND OR REPLACE
#SR0603NS
DOB VIOLATION - ACTIVE
May 2, 2023CONSTRUCTION
FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER:OBSERVED SPALLING AN ERODED JOINTS AT EXPOSURE #3AND AT HIGH AND LOW PARAPET WALLS SOUTH WEST WALL DAMAGED. REMEDY:MAINTAIN BUILDING REPAIR AND OR REPLACE
#SR0601NS
DOB VIOLATION - ACTIVE
Nov 22, 2022CONSTRUCTION
FTM BLDG IN CODE COMPLIANT MANNER. OBSERVED RUST HOLES IN CORNICE AT EXPOSURES 1 AND 4(ELEVATIONS WEST AND SOUTH)ALSO CRACKED TERRA COTTA ON EXPOSURES 4 SOUTH ELEVATIONS. REMEDY: MAINTAIN BLDG AND REPAIR DEFECTS ON ALL EXPOSURES
#SR10602XN
DOB VIOLATION - ACTIVE
Jun 1, 2022CONSTRUCTION
FTM EXTERIOR BLDG WALLS AND APPURTENANCES. OBSERVED ON EXP1 AND 4 CORRODED METAL CORNICE WITH RUSTED OPEN HOLES AT SEVERAL LOCATIONS EXP4 SOUTH ELEVATION-CRACKED TILE ON 10FL. REMEDY: MAINTAIN EXTERIOR BLDG WALLSM PROVIDE ADEQUATE SAFETY MEASURES, REPAIR DAMAGE FACADE AND APPURTENANCES
#LL0603RF
DOB VIOLATION - ACTIVE
Feb 22, 2022NO REPORT AND / OR LATE FILING (FACADE)
FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022
#00243
DOB VIOLATION - ACTIVE
Jul 2, 2021CONSTRUCTION
FTM BUILDING EXTERIOR WALLS/FACADE AND APPURTENANCES. EXP 2 NORTH ELEVATION OBSERVED DETERIORATING MORTAR JOINTS, OPEN JOINTS, SPALLED MASONRY FROM 13TH THROUGHT 16 FLOORS DIRECTLY ABOVE ADJACENT PROPERTY. REMEDY: MAINTAIN EXTERIOR BUILDING WALLS/FACADE AND APPURTENANCES
#LLFA02KA
DOB VIOLATION - ACTIVE
Apr 29, 2021FAILURE TO POST ENERGY GRADE/SCORE
FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3
#2000565
DOB VIOLATION - ACTIVE
Sep 3, 2019SPRINKLER
FAILED TO FILE FINAL SPRINKLER REPORT BY JULY 1, 2019
#NRF00231
DOB VIOLATION - ACTIVE
May 31, 2018NO REPORT AND / OR LATE FILING (FACADE)
FAILED TO FILE FISP CYCLE 8A TECHNICAL REPORT BY 02/21/2017
#01558
DOB VIOLATION - ACTIVE
Jan 5, 2015ELEVATOR

#9027/526744
DOB VIOLATION - ACTIVE
May 30, 2014(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST
#01811
DOB VIOLATION - ACTIVE
May 30, 2014(OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION
VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST
#01813
DOB VIOLATION - ACTIVE
Jan 31, 2013NO REPORT AND / OR LATE FILING (FACADE)
FAILED TO FILE FISP CYCLE 7A TECHNICAL REPORT BY 02/21/2012
#00076
DOB VIOLATION - ACTIVE
Dec 26, 2008ELEVATOR

#9011/289650
DOB VIOLATION - ACTIVE
DOB NOW Safety (10)
IssuedViolationStatus
Oct 11, 2024Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction
Active
Oct 11, 2024Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2019 Cat1 Test Affirmation of Correction
Active
Oct 2, 2023Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction
Active
Oct 2, 2023Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction
Active
Feb 22, 2022Facades FISPNRF
FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022
Active
Apr 29, 2021Energy Grade - LL33 FTP-EN-EGRDEA
Active
Sep 3, 2019Sprinklers FTF-SP-FINAL
Active
May 31, 2018Facades FISPNRF
FAILED TO FILE FISP CYCLE 8A TECHNICAL REPORT BY 02/21/2017
Active
Jan 31, 2013Facades FISPNRF
FAILED TO FILE FISP CYCLE 7A TECHNICAL REPORT BY 02/21/2012
Active
HPD (0)

None open.

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Nov 1, 2026, 9:54 AM ET. BBL 1008640025.