4 floors · 5 apartments · 8,750 sq ft · built 1920 · class S5 · owner of record: Nechal Nvei Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | Registration expired 2026-09-01 |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 70 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 70 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 86 days | Annual |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 1 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 801 days | Next cycle year 2028 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 13, 2026 | Construction CLASS - 1 ATOI OBSERVED UNAUTHORIZED NEWLY INSTALLED NON FIRE RATED PVC USED FOR HOT WATER HEATER VENT PIPING., REPAIR AND/REPLACE #39195860X | Nov 16, 2026 PENDING | $2,500 |
| Jul 13, 2026 | Unknown CLASS - 2 ATOI OBSERVED ACTIVE JOBSITE UNDER APPLICATION # B01162090-I1-GC WITH RESPONDENT FAILURE TO PROVIDE FIRE EXTINGUISHERS PER FIRE CODE THROUGH FLOORS., COMPLY WITH FIRE CODE #39195859Z | Nov 16, 2026 | $625 |
| Jul 13, 2026 | Construction CLASS - 2 ATOI OBSERVED APPROVED PLANS DOES NOT CONFORM TO JOB SITE CONDITION DUE TO GAS LINES NOT INDICATED ON DRAWING TO HOT WATER HEATERS AS PER APPROVED PLANS B01162090-I1-PL ALL WATER HEATERS ARE ELECTRIC THERE IS N #39195862J | Nov 16, 2026 | $2,500 |
| Sep 10, 2013 | Construction CLASS - 1 OCCUPANCY CONTRARY TO THAT ALLOWED BY THE C OF O #320430556 ILLEGAL OCCUPANCY NOTED: CELLAR OCCUPIED AT REAR AS THE OFFICE FOR "BERRY'S COOLING & HEATING". CONTRARY TO C OF O WHICH INDICATES ORDINARY HEAT AND #35033649N | Oct 28, 2013 ADMIT/IN-VIO | $0 |
| Dec 28, 2012 | Construction CLASS - 1 FAILURE TO MAINTAIN BLDG IN A CODE COMPLIANT MANNER.FAILURE TO PROVIDENUMBER OF REQUIRED MEANS OF EGRESS FOR EVERY FLOOR PER BC1018.1 & 27.366. NOTED: 4TH FLOOR APT OCCUPIED AS TRANSIENT USE W/O PROVIDING TWO #35006680H | Jul 26, 2013 WRITTEN OFF | $0 |
| Dec 28, 2012 | Unknown CLASS - 1 FAILURE TO PROVIDE AN AUTOMATIC FIRE ALARM SYSTEM.NOTED: BLDG OCCUPIEDAS TRANSIENT USE IN 4TH FLOOR APT WITHOUT PROVIDING FIRE ALARM SYSTEM.REMEDY: DISCONTINUE ILLEGAL OCCUPANCY. #35006681J | Jul 26, 2013 IN VIOLATION | $0 |
| Dec 28, 2012 | Unknown CLASS - 1 BC1008.1.2.2 FAILURE TO COMPLY WITH DIRECTION OF SWING.NOTED: FIRST FLOOR PRIMARY FIRE EXIT DOOR LEADING INTO THE STREET. SWINGS AGAINST THEDIRECTION OF EGRESS TRAVEL IN TRANSIENTLY OCCUPIED BLDG IN 4TH FLR APT #35006682L | Jul 26, 2013 IN VIOLATION | $0 |
| Dec 26, 2012 | Construction CLASS - 1 OCCUPANCY CONTRARY TO THAT ALLOWED BY C/O #301171826. ILLEGAL OCCUPANCY NOTED: (1) CREATE 6 BEDROOM AT 4 FLOOR (2) SUBDIVIDE 1 CLASS'A' APT INTO 2 CLASS'A' APT'S (3) CONVERT CLASS'A' APT INTO EXTENSION OF #35006704N | May 6, 2013 IN VIOLATION | $0 |
| Dec 26, 2012 | Construction CLASS - 1 WORK W/O PERMIT. WORK NOTED: (1) AT 4TH FL ERECT FULL HEIGHT PARTITIONS TO CREATE 6 BEDROOMS (2) AT 3 FLOOR ERECT FULL HEIGHT PARTITIONS & WATER & WASTE LINE TO CREATE CLASS'A' APT (3) AT 1 FLOOR ERECT 1 AWNING #35006702J | Jun 24, 2013 WRITTEN OFF | $0 |
| Aug 11, 2000 | Construction Hazardous OCCUPANCY CONTRARY TO THAT ALLOWED BY THE BLDG. DEPT. RECORDS NOTED:BN4110 INDICATE USE AS COMMERCIAL.OBSERVED 1 APT. AT 3RD STORY EAST WITH KITCHEN SPACE WITH GAS STOVE 3PCS BATHROOM OPEN SPACE AND SLEEPING #34262513R | Oct 2, 2000 DEFAULT | $2,500 |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01170 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION #00355 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION #01251 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION #00375 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #04566 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION #02230 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION #01034 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #03401 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION #04143 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION #01100 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION #02343 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION #03000 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION #01690 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00539 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION #00614 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION #00593 | DOB VIOLATION - ACTIVE |
| Mar 3, 2015 | HIGH PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE 2013 ANNUAL HIGH PRESSURE BOILER INSPECTION #00593 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Aug 19, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Sep 23, 2024 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Sep 23, 2024 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 3, 2015 | Boiler HBLVIO VIOLATION ISSUED FOR FAILURE TO FILE 2013 ANNUAL HIGH PRESSURE BOILER INSPECTION | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Feb 8, 2019 | A | § 27-2005 ADM CODE PROPERLY REPAIR THE BROKEN OR DEFECTIVE LOCKS AT MAILBOX AT WEST WALL AT PUBLIC HALL, 1st STORY | May 14, 2019 |
| Feb 8, 2019 | A | § 27-2005 HMC: POST, IN A FORM APPROVED BY THE COMMISSIONER, AND MAINTAIN A NOTICE IN A COMMON AREA OF THE BUILDING REGARDING THE PROCEDURES THAT SHOULD BE FOLLOWED WHEN A GAS LEAK IS SUSPECTED | May 14, 2019 |
| Feb 8, 2019 | A | § 26-1103 ADMIN. CODE: POST AND MAINTAIN A PROPER NOTICE ON WALL OF THE ENTRANCE STORY IN ENGLISH AND SPANISH ON THE AVAILABILITY OF THE AGENCYS HOUSING INFORMATION GUIDE. A SAMPLE NOTICE CAN BE FOUND AT WWW.NYC.GOV/HPD. AT PUBLIC HALL, 1st STORY | May 14, 2019 |
| Jun 26, 2017 | B | Apt 3 · § 27-2046.1, 2046.2 HMC: PROVIDE AN APPROVED AND OPERATIONAL CARBON MONOXIDE DETECTING DEVICE, INSTALLED IN ACCORDANCE WITH APPLICABLE LAW AND RULES. IN THE ENTIRE APARTMENT LOCATED AT APT 3, 3rd STORY, APARTMENT AT EAST | Jul 31, 2017 |
| Jun 26, 2017 | B | § 27-2021 ADM CODE PROVIDE SUFFICIENT, PROPER AND SEPARATE METAL RECEPTACLES FOR THE DEPOSIT OF GARBAGE, RUBBISH AND OTHER WASTE MATERIAL AND ARRANGE FOR COLLECTION AND DISPOSAL OF SUCH MATERIAL. AT PUBLIC HALL, 1st STORY | Jul 31, 2017 |
| Jun 26, 2017 | B | Apt 3 · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR THE CEILING IN THE 1st ROOM FROM EAST AT SOUTH LOCATED AT APT 3, 3rd STORY, APARTMENT AT EAST | Jul 31, 2017 |
| Jun 26, 2017 | B | Apt 3 · § 27-2045 ADM CODE REPAIR OR REPLACE THE SMOKE DETECTOR THAT IS DEFECTIVE IN THE ENTIRE APARTMENT LOCATED AT APT 3, 3rd STORY, APARTMENT AT EAST | Jul 31, 2017 |
| Mar 1, 2010 | B | SECTION 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE WOOD SCUTTLE HATCH AT PUBLIC HALL, 4th STORY | Apr 5, 2010 |
| Feb 22, 2010 | B | SECTION 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE 7TH AND 8TH METAL STAIR TREADS, BOTTOM UP FROM 2ND TO 3RD STORY AT PUBLIC HALL STAIRS | Mar 29, 2010 |
| Date | Source | What | Now |
|---|---|---|---|
| Aug 19, 2026 | DOB Safety | AEUHAZ: | Open |
| Jul 13, 2026 | ECB | Construction: ATOI OBSERVED FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SECTION REQUIREMENTS. DUE TO DEBRIS SCATTERED ALL OVER FLOOR AND NOT ORGANIZED MATERIALS CREATING TRIPPING HAZARDS., MAINTAIN ADEQUATE CONSTRUCTION HO | Closed |
| Jul 13, 2026 | ECB | Construction: ATOI OBSERVED UNAUTHORIZED NEWLY INSTALLED NON FIRE RATED PVC USED FOR HOT WATER HEATER VENT PIPING., REPAIR AND/REPLACE | Open |
| Jul 13, 2026 | ECB | Unknown: ATOI OBSERVED ACTIVE JOBSITE UNDER APPLICATION # B01162090-I1-GC WITH RESPONDENT FAILURE TO PROVIDE FIRE EXTINGUISHERS PER FIRE CODE THROUGH FLOORS., COMPLY WITH FIRE CODE | Closed |
| Jul 13, 2026 | ECB | Construction: ATOI OBSERVED APPROVED PLANS DOES NOT CONFORM TO JOB SITE CONDITION DUE TO GAS LINES NOT INDICATED ON DRAWING TO HOT WATER HEATERS AS PER APPROVED PLANS B01162090-I1-PL ALL WATER HEATERS ARE ELECTRIC THERE IS N | Closed |