Bronx · Block 2939 · Lot 93 · 10460

1619 Crotona Park East

5 floors · 142,500 sq ft · built 1931 · class W1 · owner of record: Nyc Department Of Education

20open violations
$0ECB/OATH penalties owed
0HPD class C (immediately hazardous)
165dto Energy and water benchmarking

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 44 days
Keep the report on file (not filed with DOB)
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 142,500 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 165 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 165 days
Annual filing
Gas piping inspection (2028 cycle) Likely applies
Local Law 152 · During 2028
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 3 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2028
in 775 days
Next cycle year 2028
Energy audit and retro-commissioning (2029) Likely applies
Local Law 87 · Calendar year 2029
What this is

Buildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 2939). Agency page

Dec 31, 2029
in 1140 days
Next due 2029
Annual boiler inspection (2 boilers) Applies
Boiler inspection · By December 31 each year
What this is

Boilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-04-30 (Accepted). Agency page

On file2026 reports accepted

Open violations

ECB / OATH (11)
IssuedViolationHearingBalance
Jul 16, 2026Construction CLASS - 2
OCCUPANCY CONTRARY TO THAT ALLOWED BY THE COFO OR DEPT OF BUILDINGS RECORDS NOTED:AT ROOF 5TH FL/BULKHEAD STORAGE RM OCCUPIED/USED AS MS.BRYANT DANCE STUDIO/DANCE RM.REM:DISCONTINUE ILLEGAL OCCUPANCY OR AMEND C
#35734793J
Aug 7, 2026
POP/IN-VIO
$0
Jul 16, 2026Construction CLASS - 2
FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.LACK OF EMERGENCY LIGHTING FOR EXITS,EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1;27-542.NOTED:AT 2ND FL DANCE RM 219 3RD FL LIBRARY RM 319 NOT INSTAL
#35734792H
Aug 7, 2026
POP/IN-VIO
$0
Jul 16, 2026Construction CLASS - 2
FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:AT 1ST FL AUDITORIUM EXIT 9 HALLWAY SMOKE DOOR NEAR RM 108,131,EXIT 10,11 2ND FLSTAIR C,G,F 3RD FL STAIR F,J,B 4TH FL HALLWAY SMOKE DOOR NEAR RM 411,S
#35734789R
Aug 7, 2026
POP/IN-VIO
$0
Jul 16, 2026Construction CLASS - 2
FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.ILLUMINATION FOREXITS,EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1;27-381.NOTED:AT 3RD FL GYM 4TH FL GYM BASEMENT CAFETERIA EMERGENCY LIGHTS NOT WORKI
#35734791X
Aug 7, 2026
POP/IN-VIO
$0
Jul 16, 2026Construction CLASS - 2
REISSUE ECB#35693399N EXIT DOOR NOT SELF CLOSING.NOTED:AT 1ST FL EXIT 4 DOOR IN DISREPAIR/NOT CLOSING WHEN TESTED.REM:REPAIR/REPLACE DOOR.
#35734788P
Aug 7, 2026
POP/IN-VIO
$0
Jul 16, 2026Construction CLASS - 2
FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED:AT 1ST FL HALLWAY AND 2ND FL HALLWAY INSTALLED/HONG CEILINGS WITH NON FIRE RETACTED DECORATIONS.REM:COMPLY WITH CODE.
#35734790Y
Aug 7, 2026
POP/IN-VIO
$0
Aug 26, 2025Construction CLASS - 2
REISSUE: 35688710K-EXIT DOOR NOT SELF-CLOSING: EXIT #9, #5, SE #C, EXIT 10. #11, #1 AND BOILER ROOM DOOR; DOORS NOT SELF-CLOSING OR GETTING STUCK. REMEDY: COMPLY WITH CODE.
#35693399N
Sep 12, 2025
POP/IN-VIO
$0
Sep 9, 2024Construction CLASS - 2
REISSUE#3567200Y DATE OF ISSUE:02.02.2023 EXIT DOOR NOT SELF-CLOSING PROPERLY,AT EXIT 9,LEFT DOES NOT CLOSING EXIT 5,STAIRCASE C EXIT DOOR 10 POSH BAR IS STUCKY EXIT-11 AND EXIT-1 AND BASEMENTS BOILER ROOM EXIT
#35688710K
Nov 15, 2024
POP/IN-VIO
$0
Feb 2, 2023Construction CLASS - 2
REISSUE#35643177M EXIT DOOR NOT SELF-CLOSING PROPERLY.AT EXIT 9 LEFT DOES NOT CLOSING ALL THE WAY EXIT 5,STAIRCASE C EXIT DOOR 10 POSH BAR IS STUCK/WENT OPEN,EXIT 11 AND EXIT 1 DOORS NOT CLOSING PROPERLY.AT CEL
#35672200Y
May 5, 2023
POP/IN-VIO
$0
Mar 7, 2022Construction CLASS - 2
REISSUE#35540233X DATE ISSUE:01.28.2021 EXIT DOOR NO SELF CLOSING PROPERLY.AT BASEMENT LEVEL EXIT DOOR NO PUSH BAR THAT DOOR JAMMED SHUT WITH HENGE REPAIR REPLACE DOOR.REM:REPAIR AND OR REPLACE EXIT DOOR.
#35643177M
Jun 17, 2022
POP/IN-VIO
$0
Jan 28, 2021Construction CLASS - 2
EXIT DOOR NOT SELF CLOSING. NOTED: OBSERVED AT BASEMENT'S BOILER ROOM,EXIT DOOR DOES NOT OPEN AT ALL,DOOR IS JAMMEED SHUT. REMEDY: REPAIR/REPLACE DOOR.
#35540233X
May 7, 2021
POP/IN-VIO
$0
DOB (2)
IssuedViolationStatus
Nov 14, 2025LOW PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION
#06281
DOB VIOLATION - ACTIVE
Nov 14, 2025LOW PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION
#06282
DOB VIOLATION - ACTIVE
DOB NOW Safety (7)
IssuedViolationStatus
Nov 14, 2025Boiler LBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION
Active
Nov 14, 2025Boiler LBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION
Active
Oct 25, 2024Boiler FTC-BE-EXT-LP
Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device
Active
Oct 25, 2024Boiler FTC-BE-EXT-LP
Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device
Active
Nov 14, 2023Boiler FTC-BE-EXT-LP
Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device
Active
Nov 14, 2023Boiler FTC-BE-EXT-LP
Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device
Active
Nov 14, 2023Boiler FTC-BE-EXT-LP
Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device
Active
HPD (0)

None open.

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Nov 17, 2026, 8:02 PM ET. BBL 2029390093.

Look up another building