5 floors · 80,564 sq ft · built 1921 · class W1 · owner of record: Nyc Department Of Education
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 43 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 80,564 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 164 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 164 days | Annual filing |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 3 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 774 days | Next cycle year 2028 |
| Energy audit and retro-commissioning (2029) Likely applies Local Law 87 · Calendar year 2029 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 2939). Agency page | Dec 31, 2029 in 1139 days | Next due 2029 |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-04-30 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 27, 2026 | Construction CLASS - 2 REISSUE: 35725128P-FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NO FIRESTOPPING @ ELECTRICAL ROOM. REMEDY: COMPLY WITH CODE. #35734963N | Aug 14, 2026 POP/IN-VIO | $0 |
| Jul 27, 2026 | Construction CLASS - 2 REISSUE: 35725127N-FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. ALL BULKHEADS HAVE SPALLING PLASTER. REMEDY: COMPLY WITH CODE. #35734964P | Aug 14, 2026 POP/IN-VIO | $0 |
| Aug 28, 2025 | Construction CLASS - 2 REISSUE#35688714H DATEO FO ISSUE:09.09.2024 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NO FIRESTOPPING PER BC 712.3;27-345.AT THETIME OF INSPECTION OBSERVED AND NOTED AT CELLAR ROOM ELECTRICAL ROOM N #35725128P | Sep 5, 2025 POP/IN-VIO | $0 |
| Aug 28, 2025 | Construction CLASS - 2 REISSUE:35688715J DATE OF ISSUE:09.09.2024 FAILIURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.AT THE TIME OF INSPECTION OBSERVED AND NOTED AT MISSING & SPALLING PLASTER AT STAIR 2 ROOF BULKHEAD FASMOTOR ROO #35725127N | Sep 5, 2025 POP/IN-VIO | $0 |
| Sep 9, 2024 | Construction CLASS - 2 REISSUE#35672196K DATE OF ISSUE:02.02.2023 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.AT THE TIME OF INSPECTION OBSERVED THAT AT STAIR A-B MISSING/BROKEN WIRE MESH GLASS PANELS AT DIFFERENT LEVEL,AT #35688713X | Nov 15, 2024 POP/IN-VIO | $0 |
| Sep 9, 2024 | Construction CLASS - 2 REISSUE#35672195Z DATE OF ISSUE:02.02.2023 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NO FIRESTOPPING PER BC 712.3;27-345 AT THE TIME OF INSPECTION AT CELLAR LEVEL OBSERVED AT ELECTRICAL ROOM PENETRA #35688714H | Nov 15, 2024 POP/IN-VIO | $0 |
| Sep 9, 2024 | Construction CLASS - 2 REISSUE#35672194R DATE OF ISSUE:02.02.2023 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED OBSERVED MISSING & SPALLING PLASTER AT STAIR 2 ROOF BULKHEAD FASMOTOR ROOM CLASSROOMS 503,505 INSIDE AUDITO #35688715J | Nov 15, 2024 POP/IN-VIO | $0 |
| Feb 2, 2023 | Construction CLASS - 2 REISSUE#35643175Z FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.AT TIME OF INSPECTION OBSERVED SPALLING AND MISSING PLASTER AT STAIRCASE A BULKHEAD,LANDING BETWEEN BULKHEAD & 5TH FLOOR.AT AUDITORIUM CEI #35672194R | May 5, 2023 POP/IN-VIO | $0 |
| Feb 2, 2023 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER:NO FIRESTOPPING PER BC 712.3;27-345.AT TIME OF INSPECTION AT CELLAR LEVEL OBSERVED PENETRATIONS IN WALLS ABOVE ELECTRICAL ROOM ENTRANCE DOOR AND OUTSIDE OF #35672195Z | May 5, 2023 POP/IN-VIO | $0 |
| Mar 7, 2022 | Construction CLASS - 2 REISSUE#35540229N DATE OF ISSUE 01/28/2021 FAILURE TO MAINTAIN BLDG INCODE COMPLIANT MANNER AT THE TIME OF INSPECTION NOTED OBSERVED MISSING& SPALLING PLASTER AT STAIR 2 ROOF BULKHEAD,FASMOTOR ROOM,CLASSRMS#503 #35643175Z | Jun 17, 2022 POP/IN-VIO | $0 |
| Jan 28, 2021 | Construction CLASS - 2 REISSUE#35473188Z FAILURE TO MAINTAIN BLDG IN CODE COMPLIANT MANNER: NOTED: OBSERVED MISSING & SPALLING PLASTER AT STAIR 2 ROOF BULKHEAD,FASMOTOR ROOM,CLASSROOMS 503 & 505 INSIDE AUDITORIUM DUE TO WATER PENETRA #35540229N | May 7, 2021 POP/IN-VIO | $0 |
| Mar 17, 2020 | Construction CLASS - 2 REISSUE #35384094N FAILURE TO MAINAIN BUIDLINGIN CODE COMPLIANT MANNER NOTED OBSERVED THROUGHOUT THE FIFTH FLORO TEH WALL ARE SPALLING ALSO ON TEH THIRD FLOOR THE SAME CONDITIONS EXIST REPAIR/REPLACE #35473188Z | Aug 21, 2020 POP/IN-VIO | $0 |
| Feb 12, 2019 | Construction CLASS - 2 RE-ISSUE #35324708Y.FAILURE TO MAINTAIN BLD.IN CODE COMPLIANT MANNER.NOTED;AT THE FOLLOWING LOCATIONS THE PLASTER IS SPALLING ON THE 5TH FL.ROOM 505,ON THE 3RD FL.ABOVE THE AUDITORIUM,NEED TO MAKE REPAIRS.REM:C #35384094N | Aug 16, 2019 POP/IN-VIO | $0 |
| Mar 15, 2018 | Construction CLASS - 2 REISSUE #35235261M.FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED:@ THE FOLLOWING LOCATIONS THE PLASTER IS SPALLING ON THE 5TH FLOOR ROOM 505,ON THE 3RD FL ABOVE AUDITORIUM.REM:REPAIR &/REPLACE. #35324708Y | Jun 1, 2018 POP/IN-VIO | $0 |
| Mar 3, 2017 | Construction CLASS - 2 REISSUE VIO#35023357M. FOR: SPALLING AT VARIOUS LOCATIONS. 1-AUDITORIUM 2-BULKHEAD STAIRWAY E & B,3-2ND FL STAIRWAY H. 4-ROOM 302. REMEDY: REPAIR &/OR REPLACE. #35235261M | May 5, 2017 POP/IN-VIO | $0 |
| Feb 5, 2014 | Construction CLASS - 2 SPALLING AT VARIOUS LOCATIONS. 1- AUDITORIUM. 2- 3RD FLR MECHANICAL RMFOR BLOWERS. 3- 2ND FLR STAIRWELL D. REMEDY: MAINTAIN BLDG AS PER CODE. #35023357M | May 2, 2014 POP/IN-VIO | $0 |
| May 30, 2006 | Construction Hazardous BLOWERS NOT WORKING FOR EXHAUST NOT WORKING @ VARIOUS LOCATIONS. REMEDY: REPAIR BLOWERS. #34526755X | Aug 18, 2006 WRITTEN OFF | $0 |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #06279 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #06278 | DOB VIOLATION - ACTIVE |
| May 1, 2024 | RETAINING WALL FAILED TO FILE CYCLE 1 TECHNICAL REPORT BY 12/31/2018 PER RCNY 103-09 #00023 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION #41280 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION #43025 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Apr 23, 2025 | Retaining Walls | Active |
| May 1, 2024 | Retaining Walls FTF-RW-INITL | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Jul 27, 2026 | ECB | Construction: REISSUE: 35725128P-FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NO FIRESTOPPING @ ELECTRICAL ROOM. REMEDY: COMPLY WITH CODE. | Open |
| Jul 27, 2026 | ECB | Construction: REISSUE: 35725127N-FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. ALL BULKHEADS HAVE SPALLING PLASTER. REMEDY: COMPLY WITH CODE. | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 18, 2026, 10:40 AM ET. BBL 2029390045.