7 floors · 24,960 sq ft · built 1923 · class O6 · owner of record: 155 W 72 St Realty Corp
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 48 days | Keep the report on file (not filed with DOB) |
| Facade inspection report (Cycle 10A) Applies Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $76,000 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2027 in 100 days | No Cycle 10 report on record yet |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 7 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1144 days | Next cycle year 2029 |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-01-29 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Mar 19, 2021 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING EXTERIOR WALLS /FACADE AND APPURTENANCES NOTE AT TH ETIME OF MY INSPECTION OBSERVED AT EXPOSURE 1 SOUTH ELEVATIONS CRACK DETERIORATING AT PARAPET WALL EAST EXPOSURE 2 WEST ELEVATION #35548999X | Aug 19, 2021 IN VIOLATION | $0 |
| Jan 21, 2021 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING FACADE/WALLS AND APPURTENANCES NOTE AT THE TIME OF MY INSPECTION OBSERVED EPXOSURE 1 ELEVATION DEFECTIVE CORNICE TERRA COTTA AT MULTIPLE LOCATIOSN EXPOSURE 2 WEST ELEVATION DEFECTIV #35542420K | Jul 15, 2021 IN VIOLATION | $0 |
| Dec 8, 2020 | Construction CLASS - 3 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT. NOTED AS:AT THE TIME OF MY INSPECTION "THE EXTERIOR WALL CONDITION CERTIFICATE" WAS NOT POSTED IN THE INTERIOR OF THE BLDG(LOBBY OR VESTIBLE ROOM). REMEDY:COMPLY #35542139Z | Aug 26, 2021 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Feb 24, 2021 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) CYCLE 9A FAILURE TO CORRECT SWARMP CONDITIONS #00140 | DOB VIOLATION - ACTIVE |
| Feb 23, 2021 | HAZARDOUS CONDITION (FACADE) CYCLE 9A UNSAFE REPORT FILED #909272 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Feb 24, 2021 | Facades FISPFCS CYCLE 9A FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| Feb 23, 2021 | Facades FISPHAZ CYCLE 9A UNSAFE REPORT FILED | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 13, 2026, 9:11 PM ET. BBL 1011440011.