2 floors · 4 apartments · 3,844 sq ft · built 1930 · class C3 · owner of record: Atb Equity Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 58 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 58 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 74 days | Annual |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 302 days | Registered through 2027-09-01 |
| Gas piping inspection (2027 cycle) Likely applies Local Law 152 · During 2027 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 12 is on the 2027 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2027 in 423 days | Next cycle year 2027 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Sep 21, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH D.O.B FOR VIOLATION #39193897K WHICH WAS ISSUED ON 06/26/2026 AT TIME OF INSPECTION OBSERVED NO ACTION TAKING AS OF TODAY #39204966X | Dec 2, 2026 PENDING | $1,250 |
| Jun 26, 2026 | Unknown CLASS - 2 ELECTRICAL WORK WITHOUT PERMIT. AT A 2-STORY WALK UP OBSERVED INSTALLATION OF ELECTRICAL WIRING FOR 4 SINGLE AND 2 DOUBLE SPLIT SYSTEM AIR CONDITIONING UNITS, INCLUDING CONNECTIONS TO DEDICATED CIRCUITS AND INS #39193897K | Sep 2, 2026 IN VIOLATION | $1,250 |
| Jun 23, 2026 | Construction CLASS - 2 VIOLATION ISSUED FOR FAILURE TO FILE A CERTIFICATE OF CORRECTION WITH DEPT. OF BUILDINGS FOR SUMMONS #39182955X ISSUED 04/02/26, #39160453Z ISSUED 09/15/25, # 39160442N ISSUED 09/15/25, #39160441L ISSUED 09/15/ #39193402J | Sep 2, 2026 IN VIOLATION | $1,250 |
| Apr 2, 2026 | Construction CLASS - 1 TAMPERED WITH, REMOVED OR DEFACED A WRITTEN POSTED STOP WORK ORDER. NOTED: SWO STICKER ISSUED ON 09/15/2025 THAT WAS PLACED AT 1ST FLOOR WINDOW RIGHT SIDE HAS BEEN REMOVED., COMPLY WITH CODE #39182955X | Jun 3, 2027 DEFAULT | $25,000 |
| Sep 15, 2025 | Construction CLASS - 1 NO CERTIFICATE OF CORRECTION ON FILE AS PER REQUEST OF COMMISSIONER FOR CLASS 1 WORK WITHOUT A PERMIT VIOLATION 39098418Z ISSUED ON 10/31/23. NO PERMITS OBTAINED FOR THIS WORK AS OF 9/15/25., COMPLY WITH COMMIS #39160441L | Nov 19, 2025 IN VIOLATION | $2,500 |
| Sep 15, 2025 | Construction CLASS - 1 UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER; OBSERVED WORK ON THE INTERIOR AND EXTERIOR OF THE BUILDING APPEARS TO BE 100% COMPLETE. ON 3/20/24 EVIDENCE SHOWS WORK WAS APPROX 40% COMPLETE, WI #39160442N | Nov 19, 2025 IN VIOLATION | $10,000 |
| Sep 15, 2025 | Construction CLASS - 1 WORK WITHOUT A PERMIT; RAILING BEING INSTALLED ON ROOF WITH GLASS PANELING, ALSO FOUND NEW BALCONY INSTALLED AT EXP 3. AT EXP 2 AN APPROX 25' LONG AND 5' WIDE SECTION OF FACADE WAS REMOVED AND REPLACED WITH GLA #39160453Z | Nov 19, 2025 IN VIOLATION | $2,500 |
| Mar 20, 2024 | Construction CLASS - 1 UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER. NOTED : OBSERVED 4 WORKERS IN THE CELLAR, 2 ON THE FIRST FLOOR,AND 2 AT EXPOSURE 4 EXTERIOR DOING ELECTRICAL AND CONSTRUCTION WORK, WHICH IS AGAIN #39109397J | Nov 4, 2024 IN VIOLATION | $5,000 |
| Oct 31, 2023 | Construction CLASS - 1 WORK WITHOUT A PERMIT: 1ST FLOOR DEMOLITIONS, FRAMING WALLS AND JOISTS, BRICKWORKS ENCLOSED COMPROMISED WINDOWS ON EXP #2 AND #4. AT CELLAR HAS BEEN DEMO FOR POSSIBLE OCCUPANCY. AT REAR PLUS 2ND FLOORS SCAFFOLD #39098418Z | Jan 10, 2024 IN VIOLATION | $2,500 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Jan 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle D (premises is in Community District 12) | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Sep 21, 2026 | ECB | Construction: FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH D.O.B FOR VIOLATION #39193897K WHICH WAS ISSUED ON 06/26/2026 AT TIME OF INSPECTION OBSERVED NO ACTION TAKING AS OF TODAY | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)