| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 9 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 65 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 65 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 65 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 81 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 68,287 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 186 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 186 days | Annual filing |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | No current registration found |
| Facade inspection report (Cycle 10C) Applies Local Law 11 / FISP · Feb 21, 2027 to Feb 21, 2029 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 1, 2 or 3 are in sub-cycle 10C. Agency page | Feb 21, 2029 in 848 days | Filing window not open yet |
| Energy audit and retro-commissioning (2032) Likely applies Local Law 87 · Calendar year 2032 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 3712). Agency page | Dec 31, 2032 in 2257 days | Next due 2032 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 6, 2026 | Construction CLASS - 2 OBSERVED JERSEY BARRIERS INSTALLED ON THE ROADWAY NOT IN ACCORDANCE WITH MANUFACTURER SPECIFICATIONS. THE BARRIERS WERE NOT INTERLOCKING AND NOT ALL FILLED WITH WATER OR SAND, AND COULD BE EASILY DISPLACED DURI #39556275X | Nov 17, 2026 PENDING | $1,250 |
| Jul 6, 2026 | Unknown CLASS - 2 ATOI OF A PROPOSED 7-STORY NB, THE JOB SITE WAS NON-ACTIVE WITH NO PERSONNEL PRESENT. THE SITE EXCEEDED 9,000 SQ FT AND REQUIRED A DESIGNATED WATCH PERSON. I OBSERVED THAT NO WATCH PERSON WAS PROVIDED MAINTAINE #39556276H | Nov 17, 2026 PENDING | $2,500 |
| Jun 14, 2026 | Construction CLASS - 1 AT THE TIME OF INSPECTION, AT AN 7-STORY NB. PLASTIC JERSEY BARRIERS PLACED IN THE ROADWAY WERE NOT IN ACCORDANCE WITH BC 3301.1.3 BARRIERS WERE NOT PROPERLY INTERLOCK OR FILLED WITH WATER OR SAND, CREATING AN #39555446R | Aug 21, 2026 IN VIOLATION | $1,250 |
| Jun 14, 2026 | Construction CLASS - 1 AT THE TIME OF INSPECTION OF A 7-STORY NEW BUILDING, ACTIVE SITE WITH INTERIOR WORK UPON REQUESTING WORKERS ONSITE FOR PRE SHIFT MEETING, APPROVED DOB PLAN, ORIENTATION FOR WORKERS NON WAS PRESENT OR PROVIDE, C #39555444N | Aug 21, 2026 IN VIOLATION | $1,250 |
| Jun 14, 2026 | Unknown CLASS - 1 AT THE TIME OF INSPECTION OF INSPECTION, I OBSERVED WORKERS PREFORMING INTERIOR WORK SHEET ROCK, ELECTRICAL WIRING AND PAINTING OPERATION. UPON REQUESTING A DESIGNATED COMPETENT PERSON ONSITE OR CONSTRUCTION SU #39555447Z | Mar 12, 2027 | $5,000 |
| Jun 14, 2026 | Construction CLASS - 2 AT TIME OF INSPECTION OF 7-STORY NB, I OBSERVED AT EXP#1 DEBRIS CONTAINER OVERFILLED WITH CONSTRUCTION DEBRIS AND BUILDING MATERIALS ABOVE THE ALLOWABLE LIMIT. NO COVER WAS PROVIDED. FAILURE TO COVER AND SECURE #39555445P | Aug 21, 2026 IN VIOLATION | $1,250 |
| Feb 22, 2026 | Unknown CLASS - 2 AT THE TIME OF INSPECTION, I OBSERVED UNSAFE SUPPORTED SCAFFOLDING WITH INADEQUATE AND MISSING ENCLOSED NETTING. THIS CONDITION CREATES AN IMMEDIATE HAZARD OF FLYING DEBRIS STRIKING THE PUBLIC. MAINTAIN IN COMP #39550759P | Nov 20, 2026 | $2,500 |
| Feb 22, 2026 | Construction CLASS - 2 AT THE TIME OF INSPECTION, I OBSERVED PLASTIC BARRIERS INSTALLED ON THE ROADWAY NOT IN ACCORDANCE WITH MANUFACTURER SPECIFICATIONS. THE BARRIERS WERE NOT INTERLOCKING AND NOT FILLED WITH WATER OR SAND, AND COUL #39550758N | Nov 20, 2026 | $1,250 |
| Feb 1, 2026 | Unknown CLASS - 2 AT THE TIME OF INSPECTION OF A PROPOSED 7-STORY NEW BUILDING, I OBSERVED NO WATCH PERSON ON SITE OR IN THE AREA OF THE PREMISES. THE JOB SITE EXCEEDED A 9,000 SQ. FT. FOOTPRINT AND REQUIRED A DESIGNATED WATCH P #39549773N | Nov 24, 2026 | $2,500 |
| Feb 1, 2026 | Unknown CLASS - 2 AT THE TIME OF INSPECTION OF A PROPOSED NEW BUILDING, I OBSERVED AN ADVERTISEMENT ON VERTICAL NETTING AT EXPOSURE 1. DISPLAY OF ADVERTISING ON TEMPORARY CONSTRUCTION PROTECTIVE STRUCTURES IS PROHIBITED AND NOT #39549774P | Nov 24, 2026 | $2,500 |
| Jan 4, 2026 | Unknown CLASS - 2 AT THE TIME OF MY INSPECTION I OBSERVED A 30 YARD DEBRIS CONTAINER FULL TO THE RIM BEING STORE ON ROADWAY ADJACENT TO SIDEWALK SHED. I ALSO OBSERVED THAT THERE WERE NO BARRIERS (4 FT AND WIRE MESH) PROVIDED OR #39548708M | Oct 5, 2026 IN VIOLATION | $2,500 |
| Jan 4, 2026 | Construction CLASS - 1 AT TIME OF INSPECTION, OBSERVED ACCUMULATION OF ICE BENEATH SIDEWALK SHED CREATING UNSAFE WALKING CONDITION FOR PEDESTRIANS. CONTRARY TO BC 3303.4, FAILURE TO MAINTAIN SAFE MEANS OF PEDESTRIAN PASSAGE CREATES A #39548707K | Oct 5, 2026 IN VIOLATION | $2,500 |
| Jan 4, 2026 | Unknown CLASS - 1 AT THE TIME OF MY INSPECTION OF A 7 STORY NEW BUILDING APPROXIMATELY 9,710 SQUARE FEET, SITE WAS CLOSED AND THERE WAS NO CONSTRUCTION ACTIVITY. UPON SHOUTING AT PERIMETER AND BANGING ON FENCE TO ALERT WATCHPERS #39548709Y | Apr 9, 2027 | $5,000 |
| Sep 29, 2025 | Unknown CLASS - 2 DURING MY INSPECTION OF AN ACTIVE 7-STORY NB. I OBSERVED A CONCRETE POUR AND SIDEWALK SHED INSTALLATION OPERATION ON THE 2ND FLOOR WITHIN 10' OF EXPOSURE 2 ADJACENT PROPERTY WINDOWS. NO WINDOW COVERAGE OR PROTE #39545520R | Jul 7, 2026 IN VIOLATION | $2,500 |
| Sep 29, 2025 | Construction CLASS - 2 DURING MY INSPECTION OF AN ACTIVE 7-STORY NB WITH AN ONGOING CONCRETE POUR, EXPOSURE 1. I OBSERVED THAT PERMIT HOLDERS HAVE FAILED TO COMPLETE THE INSTALLATION OF THE OVERHEAD PROTECTION, SIDEWALK SHED, BEFORE #39545521Z | Jul 7, 2026 IN VIOLATION | $2,400 |
None open.
None open.
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Jul 6, 2026 | ECB | Construction: OBSERVED JERSEY BARRIERS INSTALLED ON THE ROADWAY NOT IN ACCORDANCE WITH MANUFACTURER SPECIFICATIONS. THE BARRIERS WERE NOT INTERLOCKING AND NOT ALL FILLED WITH WATER OR SAND, AND COULD BE EASILY DISPLACED DURI | Open |
| Jul 6, 2026 | ECB | Unknown: ATOI OF A PROPOSED 7-STORY NB, THE JOB SITE WAS NON-ACTIVE WITH NO PERSONNEL PRESENT. THE SITE EXCEEDED 9,000 SQ FT AND REQUIRED A DESIGNATED WATCH PERSON. I OBSERVED THAT NO WATCH PERSON WAS PROVIDED MAINTAINE | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)