4 floors · 69,000 sq ft · built 1926 · class W1 · owner of record: Nyc Department Of Education
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 60 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (3 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-12-15 (Accepted). Agency page | Dec 31, 2026 in 60 days | 3 of 3 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 69,000 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 181 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 181 days | Annual filing |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 13 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1156 days | Next cycle year 2029 |
| Energy audit and retro-commissioning (2033) Likely applies Local Law 87 · Calendar year 2033 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 13353). Agency page | Dec 31, 2033 in 2617 days | Next due 2033 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Feb 19, 2026 | Construction CLASS - 2 RE-ISSUE #35692439H. EXIT DOOR NOT SELF-CLOSING. NOTED: AT "EXIT 3" EXTERIOR DOOR NOT SELF-CLOSING PROPERLY. REMEDY: REPAIR/REPLACE DOOR. #35728863P | Mar 12, 2026 POP/IN-VIO | $0 |
| Feb 19, 2026 | Construction CLASS - 2 RE-ISSUE #35692433N. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: AT EXIT FLOOR AT "EXIT 3/4: SADDLE ELEVATED AND IN DISREPAIR, TRIPPING HAZARD. REMEDY: REPAIR AND/OR REPLACE. #35728860J | Mar 12, 2026 POP/IN-VIO | $0 |
| Feb 19, 2026 | Construction CLASS - 2 RE-ISSUE #35692431J. FAILURE TO MAINTAIN IN CODE-COMPLIANT MANNER. NOTED: AT EXPOSURE 3 PARAPET ABOVE WINDOWS MORTAR MISSING AND 2ND LEVEL ROOF. WATER AT LADDER HORIZOTANL CRACK IN WALL APPROX: 20FT LONG. REMED #35728862N | Mar 12, 2026 POP/IN-VIO | $0 |
| Feb 19, 2026 | Construction CLASS - 2 RE-ISSUE #35692429K. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: MISSING DOOR CLOSERS THROUGHOUT BUILDING. INTERIOR DOORS AT 1ST FLR-"EXIT 3" DO NOT SELF-CLOSE PROPERLY. CLASSROOM DOORS AT 4TH #35728864R | Mar 12, 2026 POP/IN-VIO | $0 |
| Feb 19, 2026 | Construction CLASS - 2 REISSUE #35692432L. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: AT 4 FLOOR CLASSROOMS 401B AND 409 WATER PENETRATION FROM ROOF. REMEDY: REPAIR AND/OR REPLACE. #35728861L | Mar 12, 2026 POP/IN-VIO | $0 |
| Feb 21, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED AT EXPOSURE 3 PARAPET ABOVE WINDOWS MORTAR MISSING AND 2ND LEVEL ROOF WATER AT LADDER HORIZONTAL CRACK IN WALL APPROX 20 FEET LONG.REM:REPAIR AND/OR R #35692431J | Apr 29, 2025 POP/IN-VIO | $0 |
| Feb 21, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED AT 4 FLOORCLASSROOMS 401B & 409 WATER PENETRATION FROM ROOF.REM:REPAIR AND/OR REPLACE. #35692432L | Apr 29, 2025 POP/IN-VIO | $0 |
| Feb 21, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED AT EXIT FLOOR AT SADDLE ELEVATED AND INDISREPAIR,TRIPPING HAZARD.REM:REPAIR AND/OR REPLACE. #35692433N | Apr 29, 2025 POP/IN-VIO | $0 |
| Feb 21, 2025 | Construction CLASS - 2 REISSUE#35678887R FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED AT MISSING DOOR CLOSERS THROUGHOUT BUILDING,ROOM 207,208 DOORSARE NOT CLOSING CORRECTLY AND STAGE LEFT.REM:REPAIR AND/OR REPLACE. #35692429K | Apr 29, 2025 POP/IN-VIO | $0 |
| Feb 21, 2025 | Construction CLASS - 2 EXIT DOOR NOT SELF-CLOSING.NOTED AT 4 FL SMOKE DOOR STAIR B 3 FL(S) STAIR A,2 FL(S)STAIR B,C,1 FL(S)BY ROOM 112,STAIR B,EXITS AND EXITS 3 & 4 DOORS ARE NOT CLOSING PROPERLY.REM:REPAIR AND/OR REPLACE DOOR. #35692430H | Apr 29, 2025 POP/IN-VIO | $0 |
| Mar 4, 2024 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER-NOTED: CLASS ROOM DOORS ARE MISSING DOOR CLOSERS THROUGHOUT THE BUILDING. REMEDY: PROVIDE DOOR CLOSERS. #35678887R | May 13, 2024 POP/IN-VIO | $0 |
| Jun 8, 2021 | Boilers CLASS - 2 HAND VALVE MISSING ON OIL TANK BETWEEN THE TANK AND ANTI-SYPHON VALVE, SWITCH JUMPED OUT FOR LOUVER ON COMBUSTION AIR, CONDENSATION TANK LEAKING CORRECT ALL VIOLATING CONDITIONS AND SUBMIT A CERTIFICATE OF CORR #39042395M | Jun 17, 2021 POP/IN-VIO | $0 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
None open.