13 floors · 101,283 sq ft · built 1927 · class O3 · owner of record: 175 Varick Street Llc,
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 6 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 43 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 43 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 101,283 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 164 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 164 days | Annual filing |
| Energy audit and retro-commissioning (2028) Likely applies Local Law 87 · Calendar year 2028 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 888). Agency page | Dec 31, 2028 in 774 days | Next due 2028 |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-04-08 (Accepted). Agency page | On file | 2026 reports accepted |
| Facade inspection report (Cycle 10B) Applies Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. DOB facade records for this building show $317,500 in late-filing or failure-to-file penalties. Agency page | On file | Cycle 10 filing on record: UNSAFE (2026-06-11) |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jun 17, 2024 | Construction CLASS - 2 A.C. 27-929 FAILURE TO COMPLETE INSTALLATION OF FULL SYSTEM OF AUTOMATIC SPRINKLERS & FILE FINAL SPRINKLER REPORT PREPARED BY REGISTERED DESIGN PROFESSIONAL IN OFFICE BUILDING 100 FEET OR MORE IN HEIGHT IN EXIS #37028824H | Sep 12, 2024 DEFAULT | $10,000 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL #902690. REMEDY: SUBMIT ACCEPTABLE REQU #37027672N | Jul 11, 2024 DEFAULT | $6,250 |
| Feb 28, 2023 | Construction CLASS - 2 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN HE #37025417R | Feb 8, 2024 IN VIOLATION | $0 |
| Nov 1, 2021 | Construction CLASS - 2 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULLY SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN H #37022642J | Jul 28, 2022 ADMIT/IN-VIO | $0 |
| Mar 30, 2021 | Construction CLASS - 2 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN HE #37020755R | Jul 1, 2021 DEFAULT | $9,310 |
| Sep 29, 2020 | Construction CLASS - 2 27-929.1,FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUT MATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGI TERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN #37020450X | Feb 11, 2021 DEFAULT | $0 |
| Issued | Violation | Status |
|---|---|---|
| Jun 23, 2024 | FAILURE TO SUBMIT EER FAILURE TO SUBMIT AN EER PER AD. CODE SEC. 28-308.4 - MULTIPLE YEARS (2023) #00672 | DOB VIOLATION - ACTIVE |
| Apr 22, 2023 | FAILURE TO SUBMIT EER FAILURE TO SUBMIT AN EER PER AD. CODE SEC. 28-308.4 - MULTIPLE YEARS (2022) #00468 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #02066 | DOB VIOLATION - ACTIVE |
| Aug 21, 2022 | FAILURE TO SUBMIT EER FAILURE TO SUBMIT AN EER PER AD. CODE SEC. 28-308.4 - MULTIPLE YEARS (2021) #00435 | DOB VIOLATION - ACTIVE |
| Jun 20, 2021 | FAILURE TO SUBMIT EER FAILURE TO SUBMIT AN EER PER AD. CODE SEC. 28-308.4 - MULTIPLE YEARS (2020) #00141 | DOB VIOLATION - ACTIVE |
| Jun 19, 2021 | FAILURE TO SUBMIT EER FAILURE TO SUBMIT AN EER PER AD. CODE SEC. 28-308.4 - MULTIPLE YEARS (2019) #00019 | DOB VIOLATION - ACTIVE |
| Apr 29, 2021 | FAILURE TO POST ENERGY GRADE/SCORE FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3 #2000599 | DOB VIOLATION - ACTIVE |
| Nov 12, 2019 | SPRINKLER FAILED TO FILE FINAL SPRINKLER REPORT BY JULY 1, 2019 #NRF00098 | DOB VIOLATION - ACTIVE |
| Sep 6, 2019 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST #01509 | DOB VIOLATION - ACTIVE |
| Sep 6, 2019 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST #01512 | DOB VIOLATION - ACTIVE |
| Sep 6, 2019 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST #01511 | DOB VIOLATION - ACTIVE |
| Sep 6, 2019 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST #01510 | DOB VIOLATION - ACTIVE |
| Mar 18, 2019 | FAILURE TO SUBMIT EER FAILURE TO SUBMIT AN EER PER AD. CODE SEC. 28-308.4 IN 2018 #10070 | DOB VIOLATION - ACTIVE |
| Jan 26, 2018 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST #01879 | DOB VIOLATION - ACTIVE |
| Jan 26, 2018 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST #01878 | DOB VIOLATION - ACTIVE |
| Jan 26, 2018 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST #01880 | DOB VIOLATION - ACTIVE |
| Sep 15, 2017 | ELEVATOR ANNUAL INSPECTION / TEST VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2016 INSPECTION/TEST #00860 | DOB VIOLATION - ACTIVE |
| Nov 14, 2016 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST #02048 | DOB VIOLATION - ACTIVE |
| Nov 14, 2016 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST #02047 | DOB VIOLATION - ACTIVE |
| Nov 14, 2016 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST #02046 | DOB VIOLATION - ACTIVE |
| Nov 14, 2016 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST #02045 | DOB VIOLATION - ACTIVE |
| Aug 15, 2012 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2010 CAT 1 INSP/TST #00186 | DOB VIOLATION - ACTIVE |
| Jan 15, 2007 | ELEVATOR #94444187576 | DOB VIOLATION - ACTIVE |
| Jan 15, 2007 | ELEVATOR #94444187580 | DOB VIOLATION - ACTIVE |
| Jan 15, 2007 | ELEVATOR #94444187579 | DOB VIOLATION - ACTIVE |
| Jan 15, 2007 | ELEVATOR #94444187578 | DOB VIOLATION - ACTIVE |
| Jan 15, 2007 | ELEVATOR #94444187577 | DOB VIOLATION - ACTIVE |
| Jan 5, 2000 | CONSTRUCTION #6JL01 | VIOLATION UNSERVED ECB-ACTIVE |
| Feb 26, 1992 | LL10/80-LOCAL LAW 10/80 - FACADE #0750HAZ | DOB VIOLATION - ACTIVE |
| Jan 24, 1992 | LL10/80-LOCAL LAW 10/80 - FACADE #0598HAZ | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Jul 16, 2026 | Facades FTC-FC-UNSAFE Unsafe 10B report filed | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 6) | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Jun 23, 2024 | Retro-Commissioning - LL87 FTF-EN-EARCX | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Aug 25, 2023 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Report | Active |
| Apr 22, 2023 | Retro-Commissioning - LL87 FTF-EN-EARCX | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Aug 21, 2022 | Retro-Commissioning - LL87 FTF-EN-EARCX | Active |
| Jun 20, 2021 | Retro-Commissioning - LL87 FTF-EN-EARCX | Active |
| Jun 19, 2021 | Retro-Commissioning - LL87 FTF-EN-EARCX | Active |
| Apr 29, 2021 | Energy Grade - LL33 FTP-EN-EGRDEA | Active |
| Nov 12, 2019 | Sprinklers FTF-SP-FINAL | Active |
| Sep 6, 2019 | Elevators ACC1 | Active |
| Sep 6, 2019 | Elevators ACC1 | Active |
| Sep 6, 2019 | Elevators ACC1 | Active |
| Sep 6, 2019 | Elevators ACC1 | Active |
| Mar 18, 2019 | Retro-Commissioning - LL87 FTF-EN-EARCX | Active |
| Jan 26, 2018 | Elevators ACC1 | Active |
| Jan 26, 2018 | Elevators ACC1 | Active |
| Jan 26, 2018 | Elevators ACC1 | Active |
| Sep 15, 2017 | Elevators EVCAT1 | Active |
| Nov 14, 2016 | Elevators ACC1 | Active |
| Nov 14, 2016 | Elevators ACC1 | Active |
| Nov 14, 2016 | Elevators ACC1 | Active |
| Nov 14, 2016 | Elevators ACC1 | Active |
| Aug 15, 2012 | Elevators ACC1 | Active |
| Aug 15, 2012 | Elevators ACC1 | Active |
| Aug 15, 2012 | Elevators ACC1 | Active |
| Aug 15, 2012 | Elevators ACC1 | Active |
| Aug 15, 2012 | Elevators ACC1 | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 18, 2026, 2:45 AM ET. BBL 1008880027.