6 floors · 63 apartments · 53,620 sq ft · built 1958 · class D1 · owner of record: Bk Property Two, Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 58 days | Keep the report on file (not filed with DOB) |
| Energy audit and retro-commissioning (2026) Likely applies Local Law 87 · Calendar year 2026 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 5046). Agency page | Dec 31, 2026 in 58 days | Due this year |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 58 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 74 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 53,620 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 179 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 179 days | Annual filing |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 302 days | Registered through 2027-09-01 |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 7 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1154 days | Next cycle year 2029 |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-09-23 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Dec 9, 2022 | Local Law CLASS - 2 FAILURE TO SUBMIT ACCEPTABLE REQUIRED CYCLE 9A REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL & APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL #911370.REMEDY:SUBMIT ACCEPTABLE REQUIRED TE #37024504K | Feb 28, 2023 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Feb 22, 2022 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022 #01356 | DOB VIOLATION - ACTIVE |
| Apr 6, 2018 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT #15074 | DOB VIOLATION - ACTIVE |
| Nov 14, 2016 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2014 CAT 1 INSP/TST #07471 | DOB VIOLATION - ACTIVE |
| May 15, 2014 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT #17200 | DOB VIOLATION - ACTIVE |
| Dec 13, 2011 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2010 INSPECTION REPORT #19645 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Aug 29, 2025 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Report | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Affirmation of Correction | Active |
| Aug 25, 2023 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Report | Active |
| Feb 22, 2022 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022 | Active |
| Apr 6, 2018 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT | Active |
| Nov 14, 2016 | Elevators ACC1 | Active |
| May 15, 2014 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT | Active |
| Dec 13, 2011 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2010 INSPECTION REPORT | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Aug 13, 2008 | B | D26-10.01 ADM CODE PROPERLY REPAIR THE BROKEN OR DEFECTIVE EXHAUST VENTS ROOF THROUGHOUT R115. | Sep 17, 2008 |
| Aug 13, 2008 | B | D26-10.01 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE MASONARY CLG & WALLS BOILER ROOM CELLAR. | Sep 17, 2008 |
| Jan 8, 2008 | B | Apt 5D · SECTION 27-2018 ADM CODE ABATE THE NUISANCE CONSISTING OF VERMIN BED-BUGS IN THE ENTIRE APARTMENT LOCATED AT APT 5D, 5th STORY, 1st APARTMENT FROM SOUTH AT WEST | Feb 12, 2008 |
| Jun 12, 2006 | B | Apt 7D · SECTION 27-2018 ADM CODE ABATE THE NUISANCE CONSISTING OF VERMIN BEDBUGS IN THE ENTIRE APARTMENT LOCATED AT APT 7D, 7th STORY, APARTMENT AT WEST | Jul 22, 2006 |
| Jun 25, 2001 | B | SECTION 27-2005 ADM CODE PROVIDE BRACES FOR AIR CONDITIONERS 3rd, 4th , 5th AND 6th STORIES BUILDING FRONT AT FRONT AREAWAY | Aug 4, 2001 |
| May 15, 1990 | B | SECTION 27-2039 ADM CODE PROVIDE ADEQUATE LIGHT OF NOT LESS THAN 60 WATTS INCANDESCENT OR EQUIVALENT ILLUMINATION FIRE STAIR ALL STYS. | Jul 2, 1990 |
| May 15, 1990 | B | SECTION 27-2010, 2011, 2012 ADM CODE CLEANSE AND DISINFECT TO THE SATISFACTION OF THIS DEPARTMENT AFTER REMOVING THE URINE AT BULKHEAD OF FIRE STAIR. | Jul 2, 1990 |
| May 15, 1990 | B | SECTION 27-2005 ADM CODE PROVIDE APPLICATION LEGALIZATION OF CONDITION OR DISCONTINUE USE OF A MAGNETIC LOCKING DEVICE ON BLDG VESTIBULE DOOR TO 1 STY PUB HALL. | Jul 2, 1990 |
| May 15, 1990 | B | SECTION 27-2040 ADM CODE INSTALL AND MAINTAIN SUFFICIENT LIGHT OR LIGHTS OF AT LEAST 100 WATTS INCANDESCENT OR EQUIVALENT EACH, TO LIGHT ADEQUATELY FROM SUNSET TO SUNRISE THE EAR COURT. | Jul 2, 1990 |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 3, 2026, 10:21 PM ET. BBL 4050460040.