8 floors · 34 apartments · 14,868 sq ft · built 2022 · class D6 · owner of record: Blackdragon Sanford Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 43 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 43 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 59 days | Annual |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | No current registration found |
| Facade inspection report (Cycle 10B) Applies Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. Agency page | Feb 21, 2028 in 460 days | No Cycle 10 report on record yet |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 7 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1139 days | Next cycle year 2029 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Oct 24, 2026 | Construction CLASS - 1 ATOI, I OBSERVED THAT WORK WAS CONTINUED WHILE SWO #4A52660 EXISTS HERE SINCE 09/24/26 - INDICATING NO OTHER EXTERIOR WORK ALLOWED AT EXP #3. I OBSERVED WORKERS WERE ON 7-8FL SCAFFOLD ON EXP #3, PERFORMING EXTE #39561008H | Dec 29, 2026 PENDING | $10,000 |
| Oct 24, 2026 | Construction CLASS - 2 OBSERVED SATURDAY 10/24/26 AFTER-HOUR VARIANCE PERMIT OBTAINED, BUT FORBADE ANY SCAFFOLD USE, EXTERIOR WORK OR WORK ABOVE 75FT. OBSERVED EXP #3 REAR YARD, WORKERS WERE ON 7-8 FLOOR SUPPORTED SCAFFOLD PERFORMING #39561012K | Dec 29, 2026 PENDING | $1,250 |
| Oct 24, 2026 | Construction CLASS - 2 ATOI, OBSERVED WORKERS IN THE LOBBY. CALLED OUT BUT ACCESS FOR INSPECTION WAS DENIED. WORKERS THEN WENT ON 8FL SCAFFOLD ON EXP #3 AND STARTED WORKING. INSPECTION DENIED PUT SAFETY STANDARDS AT RISK FOR EVERYONE #39561005M | Dec 29, 2026 PENDING | $2,500 |
| Sep 27, 2026 | Unknown CLASS - 2 MISCELLANEOUS VIOLATIONS.BC 3303.3 ATOI OF 8 STORY BUILDING AT ROOF LEVEL APPROX.27,653 SQ FT SITE CLOSED AND THERE WERE NO CONSTRUCTION ACTIVITY.UPON SHOUTING AT PERIMETER AND BANGING ON FENCE AND DOOR TO ALER #39559839X | Dec 1, 2026 PENDING | $2,500 |
| Sep 24, 2026 | Unknown CLASS - 1 BC3314.1 SUPPORTED SCAFFOLD.@8STORY NB SITE OBSERVE UNSAFE SUPPORTED SCAFFOLD UP TO ROOF LEVEL@ALL EXPOSURES CREATING FAILURE/DISLODGEMENT HAZARDS AFFECTING HEALTH&LIFE SAFETY:NOT MAINTAINED&MISSING DEBRIS NET+ #39559605N | Dec 1, 2026 PENDING | $10,000 |
| Sep 24, 2026 | Unknown CLASS - 2 @8STORY NB SITE IN EXTERIOR PHASE W/UNSAFE SUPPORTED SCAFFOLD UP TO ROOF LEVEL TOWERING OVER ADJOIN PROPERTY 42-08 UNION STREET WITH NO PROTECTION OF ROOF IN PLACE TO CODE BC3309.10 NOR ENGINEERED ENCLOSURE SYS #39559606P | Dec 1, 2026 PENDING | $2,500 |
| Jul 28, 2026 | Unknown CLASS - 2 BC 3314.1 AT TIME OF INSPECTION OBSERVED WORKER AT ROOF LEVEL WORKING ON A SUPPORTED SCAFFOLD NOT IN THE STATE OF READINESS, NO TOEBOARDS, NO PLANKS TIED DOWN OR GUARDRAIL SYSTEM AS REQUIRED IN 3314.5, 3314.5.5 #39557172H | Dec 29, 2026 | $2,500 |
| Jul 28, 2026 | Construction CLASS - 2 OBSERVED VEHICLE EXITING THE SITE AT VEHICULAR ACCESS POINT NOT CLEARLY MARKED WITH HI VISIBILITY OR ADDITIONAL SUPPORT AT VERTICAL MEMBERS CREATING HAZARDOUS CONDITIONS TO THE STRUCTURAL STABILITY OF THE SHED #39557173J | Dec 29, 2026 | $2,400 |
| Jul 17, 2026 | Construction CLASS - 1 OBSERVED: ACTIVE SITE CP PRESENT UPON INSPECTION NOTED FAILURE TO MAINTAIN HOUSEKEEPING,CARDBOARD, CEMENT AND DEBRIS MATERIALS IT NOTED IN DIFERENT LEVEL AND LOCATIONS CREATING HAZARDS CONDITION FOR WORKERS ON #39556769X | Dec 1, 2026 | $2,500 |
| Jun 12, 2026 | Unknown CLASS - 2 6/11/2026 6:41PM WHILE PERFORMING A SEVERE WEATHER ADVISORY INSPECTION OBSERVED AN 8 STORY RESIDENTIAL BUILDING W/ NO CONSTRUCTION ACTIVITY UPON SHOUTING AT PERIMETER AND BANGING ON FENCE AND DOOR TO ALERT WAT #39555512X | Mar 9, 2027 PENDING | $2,500 |
| May 19, 2026 | Unknown CLASS - 1 AT THE TIME OF INSPECTION OF AN 8-STORY ACTIVE JOB SITE UNDERGOING STUCCO AND STYROFOAM OPERATIONS, STYROFOAM RESIDUE WAS OBSERVED ON THE ADJACENT PROPERTY AT EXP# 4 AND ON EQUIPMENT, CREATING A HAZARDOUS CONDI #39554283R | Feb 2, 2027 | $10,000 |
| May 19, 2026 | Construction CLASS - 2 BC3307.6.4.10 AT THE TIME OF INSPECTION OF AN 8-STORY ACTIVE JOB SITE, THE SIDEWALK SHED AT EXP# 1 AND 2 WAS OBSERVED NOT MAINTAINED, WITH DETERIORATED MODSEAL THROUGHOUT THE STRUCTURE, CREATING A HAZARDOUS CO #39554284Z | Feb 2, 2027 | $2,400 |
| Feb 25, 2026 | Unknown CLASS - 2 3314.3PIPE SCAFFOLDS CONTRARY TO PLANS &UNSAFE.EXPO1 TRUSS INSTALLED AT 2FLR LEVEL ON SF NOT SHOWN ON PLANS.SF @EXPO1 IS 2 LAYERS: 1 5FT SECTION & 1 3FT SECTION, THIS NOT SHOWN ON PLANS.AT ENDS OF SF @EXPO1 LAR #39550927P | Jan 5, 2027 | $2,500 |
| Feb 25, 2026 | Construction CLASS - 1 ALTERNATE METHODS OF PROTECTION FOR ADJOINING PROPERTIES ARE CONTRARY TO SSP. OBS PIPESCAFFOLD INSTALLED @EXPOS 1,2,3 NOT SHOWN ON SSP PROVIDED. HOIST BEING INSTALLED @EXPO3 NOT SHOWN ON SSP. NEEDLEBEAMS INSTAL #39550925L | Jan 5, 2027 | $2,500 |
| Feb 25, 2026 | Unknown CLASS - 2 3301.13.7OBS MULTPL UNSAFE & HAZARDOUS CONDITIONS; CS DAILY LOG DOES NOT CONTAIN: SAFEGUARDS FOR ADJACENT PROPERTIES & TEMP EQUIP CONTRARY SSP, SSP NOT REFLECTING FIELD CONDITIONS, ACTIVE WORK ON FLRS W/ ICE&SN #39550929Z | Jan 5, 2027 | $2,500 |
| Feb 25, 2026 | Unknown CLASS - 1 3301.5UNSAFE CONDITIONS. ACTIVE WORK ON FLRS NOT CLEARED OF ICE&SNOW. FLOORS/STAIRS ARE ICY/SNOWY, CREATE FALL HZRDS FOR ALL. 3308.7ON MULTIPLE FLOORS & ELEVATOR SHAFT EDGES INADEQUATE GUARDRAILS; MISSING TOEBO #39550926N | Jan 5, 2027 | $5,000 |
| Jan 31, 2026 | Unknown CLASS - 1 OBSERVED SUPPORTED SCAFFOLD EXP #1 NETTING LOOSE, EXP #3 HAD LOOSE ITEM DANGLING OUTSIDE, CREATING HAZARDS TO PEDESTRIANS AND ADJACENT PROPERTY (BC 3314.1). STOP EXTERIOR WORK AND USE OF SCAFFOLD ON EXP #1 AND #39549821Z | Nov 10, 2026 IN VIOLATION | $5,000 |
| Jan 19, 2026 | Construction CLASS - 1 BC 3303.4.2 (4.). OBSERVED SITE DEBRIS CONTAINER ON STREET FILLED TO THE BRIM & NOT COVERED CREATING HAZARDS OF STRUCK-BY&DISLODGEMENT TO THE PUBLIC/PEDESTRIAN AFFECTING ALL HEALTH & LIFE SAFETY. PROVIDE DEBR #39549309J | Oct 6, 2026 IN VIOLATION | $2,500 |
| Jan 19, 2026 | Unknown CLASS - 2 BC 3307.2.1 OBSTRUCTION OF STREETS. AT PERMITTED ACTIVE SITE OBSERVED SITES DEBRIS CONTAINER FRONT OF SITES OBSTRUCTING STREET,& VERIFIED PER RECORDS, SITE FAILED TO OBTAIN DEPARTMENT OF TRANSPORTATION PERMIT #39549308H | Oct 6, 2026 IN VIOLATION | $2,500 |
| Jan 19, 2026 | Site Safety CLASS - 1 @ACTIVE NB SITE WITH SUPERINTENDENT ON PERMIT I REQUESTED ONSITE PERSONNEL FOR SITE SAFETY PLAN WHICH WASN'T PROVIDED TO ENSURE SOUND CONSTRUCTION OF SIDEWALK SHEDS, PROPER SAFETY MEASURES, AND SAFE CONSTRUCTIO #39549311Z | Oct 6, 2026 IN VIOLATION | $2,500 |
| Jan 19, 2026 | Unknown CLASS - 1 BC3303.12 INOPERABLE FDNY TEMPORARY HOIST/ELEVATOR.@8 STORY NB SITE UP TO ROOF LEVEL OBSERVE ACTIVE WORK THROUGHOUT SITE & ABOVE 7TH FL & OVER 75FT IN HEIGHT W/ FDNY TEMPORARY HOIST/ELEVATOR NOT IN STATE OF REA #39549310R | Oct 6, 2026 IN VIOLATION | $5,000 |
| Jan 19, 2026 | Unknown CLASS - 2 BC 3307.4.7 NO WORK OR STORAGE ZONE BARRIER. OBSERVE SITES DEBRIS CONTAINER FILLED TO THE BRIM ADJACENT TO SITES SIDEWALK SHED& NO PROTECTIVE BARRIER IN PLACE FOR PEDESTRIAN TO BC3307.4.7 SECTION .3 TO PREVENT #39549307X | Oct 6, 2026 IN VIOLATION | $2,500 |
| Apr 8, 2025 | Construction CLASS - 2 JOB FENCE JOB#Q00220245 PERMIT EXPIRED ON 10/10/2022.@INACTIVE EXPIRED PERMIT 8STORY NB SITE OBSERVE JOB FENCE IN PLACE AT EXP#1 ADJACENT TO SIDEWALK AND I VERIFIED PER DEPARTMENTS RECORDS, THE JOB FENCE JOB#Q0 #39538881R | Jun 17, 2025 DEFAULT | $3,125 |
| Apr 8, 2025 | Unknown CLASS - 2 SIDEWALK SHED JOB#Q00516824 PERMIT EXPIRED ON 11/03/2023.@INACTIVE EXPIRED PERMIT 8STORY NB SITE OBSERVE SIDEWALK SHED IN PLACE AT EXP#1 COVERING SIDEWALK AND I VERIFIED PER DEPARTMENTS RECORDS, THE SIDEWALK SH #39538882Z | Jun 17, 2025 DEFAULT | $3,125 |
| Apr 3, 2025 | Unknown CLASS - 1 BC 3314.1 SCOPE SCAFFOLD: DURING INSPECTION OF AN INACTIVE SITE, I OBSERVED THAT THE SUPPORTED SCAFFOLD IN PLACE WAS MISSING DEBRIS NETTING, THE NETTING WAS DISLODGED, THE PLANKS WERE NOT TIED DOWN. THE LACK OF #39538751Z | Nov 16, 2026 IN VIOLATION | $2,500 |
| Apr 3, 2025 | Construction CLASS - 2 DURING INSPECTING OF A NONE ACTIVE SITE I OBSERVED THAT THE SUPPORTED SCAFFOLD IN PLACE HAD AN EXPIRED PERMIT JUNE 26, 2024 Q00893125-I1-SF WITH NO RENEWAL IN PROCESS DOB SYSTEM. ALL PERMITS MUST BE VALID AND M #39538750R | Nov 16, 2026 IN VIOLATION | $1,250 |
| Feb 6, 2025 | Construction CLASS - 2 TEMPORARY CONSTRUCTION EQUIPMENT/INSTALLATION ON SITE EXPIRED PERMIT. AS NOTED: AT TIME OF INSPECTION ON A CONSTRUCTION SITE OF A PROPOSED 7STORY, BUILDING WAS CLOSED, OBSERVED CONSTRUCTION FENCE PERMIT HAD EXP #35689171P | Feb 25, 2027 DEFAULT | $3,125 |
| Feb 6, 2025 | Unknown CLASS - 2 TEMPORARY CONSTRUCTION EQUIPMENT/INSTALLATION ON SITE EXPIRED PERMIT "SIDEWALK SHED". AS NOTED: AT TIME OF INSPECTION ON A CONSTRUCTION SITEOF A PROPOSED 7 STORY BUILDING WAS CLOSED. OBSERVED CONSTRUCTION SIDEW #35689172R | Feb 25, 2027 DEFAULT | $3,125 |
| Sep 27, 2023 | Construction CLASS - 2 AT TIME OF INSPECTION NO COMPETENT PERSON, OR ANYONE IN CHARGE ON SITE. ONLY 2 WORKERS THAT DID NOT SPEAK ENGLISH ON SITE. SIGNALED WORKER TO CALL "BOSS". WAITED 15 MINUTES, NO ONE SHOWED., PROVIDE APPROVED /AC #39095856P | May 28, 2024 IN VIOLATION | $1 |
| Jun 26, 2023 | Construction CLASS - 2 NO EN DRAWING AND COM/CKHECK APPROVED FROM DOB PROVIDED ON THE JOB SITE AT THE TIME AT THE TIME OF INSPECTION., PROVIDE APPROVED /ACCEPTED CONSTRUCTION DOCUMENTS; PLEASE GO TO HTTPS://WWW1.NYC.GOV/SITE/BUILDING #39089113N | Nov 12, 2024 IN VIOLATION | $625 |
| Jun 20, 2023 | Construction CLASS - 2 I OBSERVED A SIDEWALK SHED/OVER HEAD PROTECTION INSTALLED AT EXPOSURES 1,3 & 4 WITH SCAFFOLD INSTALLED ON TOP APPROX. 48 FT AT EXPOS 2 & 4.AFTER REQUESTING TO SEE APPROVED SCAFFOLD DRAWINGS AS WELL AS 6 MONTHS #39517984R | Aug 29, 2023 DEFAULT | $3,125 |
| Jun 20, 2023 | Construction CLASS - 1 AT THE TIME OF MY INSPECTION OF A ACTIVE PROPOSED 8 STORY CONSTRUCTION SITE I OBSERVED SCAFFOLD BEING INSTALLED AT APPROX. 60 FEET IN HEIGHT AT EXPOSURE 3 & 4. UPON REVIEW OF DOB RECORDS THERE WAS NO ACTIVE PER #39517982N | Aug 29, 2023 DEFAULT | $12,500 |
| Jun 20, 2023 | Construction CLASS - 2 AT THE TIME OF MY INSPECTION OF A ACTIVE PROPOSED 8 STORY CONSTRUCTION SITE I OBSERVED A ROOF UNPROTECTED AT EXPOSURE 3. UPON REVIEW OF THE APPROVED SSP ROOF PROTECTION( FOAM & WOOD) SHOULD OF BEEN PROVIDED AT #39517990N | Aug 29, 2023 DEFAULT | $3,125 |
| Jul 5, 2022 | Construction CLASS - 1 NO ROOF PROTECTION IN PLACE TO CODE BC3309.10.ON 8 STORY NB SITE UP TO 4TH FLOOR OBSERVE EXPOSURE2 ADJOINING PROPERTY'S ROOF HAVE CONCRETE DEBRIS AND MISSING PROTECTIONS TO CODE BC3309.10 WHILE SITE CONTINUES C #39503033Y | Mar 2, 2023 IN VIOLATION | $2,500 |
| Jul 5, 2022 | Construction CLASS - 1 WORK NOT ADHERE TO SITE SAFETY PLAN.ON 8 STORY NB SITE UP TO 4TH FLOOR OBSERVE EXPOSURE2 ADJOINING PROPERTY MISSING SECTION OF OVERHEAD PROTECTION AND OCCUPANT IS NEAR BELOW THE SITE AND AFTER REVIEWING THE PRO #39503032M | Mar 2, 2023 IN VIOLATION | $2,500 |
| May 14, 2022 | Construction CLASS - 2 TEMPORARY CONSTRUCTION EQUIPMENT EXPIRED PERMIT.NOTE:AT THE TIME OF INSPECTION OBSERVED A HEAVY DUTY SIDEWALK SHED AT EXPOSURE ONE WITH PERMIT#Q00516824-SH.PEDESTRIAN WALKING UNDER THIS SIDEWALK SHED.ALSO OBSER #35639224Y | Sep 6, 2022 IN VIOLATION | $625 |
| Feb 4, 2022 | Construction CLASS - 2 CONSTRUCTION SITE JOB FENCE PERMIT EXPIRED ON 01-13-2022 #Q00220245.ATTIME OF INSPECTION ON AN ACTIVE 8 STORY NB PERMIT SITE IN SOE/FOUNDATION PHASE I OBSERVED JOB FENCE IN PLACE WHERE REQUIRED & UPON RESEARCH #35639534J | May 3, 2022 IN VIOLATION | $625 |
| Jan 21, 2022 | Construction CLASS - 1 JOB FENCE NOT CONSTRUCTED/MAINTAINED PER CODE EXPOSING ADJOINING PROPERTY OCCUPANTS AT EXP.#4 140-40 SANFORD AVE TO FALL HAZARD OVER 6 FT INTO SITE.AT TIME OF INSPECTION IN RESPONSE TO COMPLAINT I OBSERVED INAC #35641290P | Apr 19, 2022 DEFAULT | $12,500 |
| Jan 6, 2022 | Construction CLASS - 1 DURING EXCAVATION WORK IN PROGRESS AT EXPOSURE 2, EXISTING FOUNDATION WALL OF ADJACENT PROPERTY 42-04 UNION ST. EARTHWORK HAS PUNCTURED FOUNDATION WALL AND CREATED LARGE VERTICAL CRACK., SAFEGUARD PUBLIC AND PR #39053908M | Sep 13, 2022 IN VIOLATION | $10,000 |
| Jan 5, 2022 | Construction CLASS - 1 FAILURE TO OBTAIN REGISTERED DESIGN PROFESSIONAL EVALUATION PRIOR TO USING EXISTING STRUCTURE(ADJOINING PROPERTIES FOUNDATION WALLS)TO SUPPORT SITES CONCRETE FOUNDATION CONSTRUCTION.AT TIME OF INSPECTION ON A A #35641141L | Apr 12, 2022 DEFAULT | $12,500 |
| Jan 5, 2022 | Construction CLASS - 1 BC 3304.7 FAILURE TO MAINTAIN EXCAVATION SAFE MEANS OF INGRESS AND EGRESS FOR SITE PERSONNEL AND PUBLIC.AT TIME OF INSPECTION ON A ACTIVE 8 STORY NEW BUILDING SITE IN EXCAVATION & FOUNDATION PHASE I OBSERVED WO #35641140J | Apr 12, 2022 DEFAULT | $6,250 |
| Dec 2, 2021 | Construction CLASS - 2 JOB SITE FENCE NOT CONSTRUCTED OR MAINTAINED PURSUANT TO SUBSECTION.NOTE:AT TIME OF INSPECTION OF 8 STORY BUILDING AT EXCAVATION LEVEL UNDER CONSTRUCTION OBSERVED EXCAVATION AND SITE DRILLING/BORED WITH TEMPORA #35632576X | Aug 16, 2022 IN VIOLATION | $500 |
| Dec 2, 2021 | Construction CLASS - 2 FAILURE TO SAFETY EQUIPMENT MEASURE.NOTE:AT TIME OF INSPECTION OF 8 STORY BUILDING AT EXCAVATOIN LEVEL UNDER CONSTRUCTION OBSERVED RITE BOURED AT EXP #3 VERY CLOSE TO ADJACENT PROPERTY AND DAMAGE ADJACENT PROPE #35632577H | Aug 16, 2022 IN VIOLATION | $2,500 |
| Jul 8, 2020 | Construction CLASS - 2 FORMS FILED WITH DEPT.OF BUILDINGS DO NOT HAVE REQUIRED SIGNATURES.AS NOTED:AT TIME OF INSPECTION CONSTRUCTION SITE WAS CLOSED.OBSERVED 8 STORY CONCRETE CAST-IN PLACE NEW BUILDING AT FLOOR#4 SLAB LEVEL.TR-3 TEC #35651323L | Oct 4, 2022 IN VIOLATION | $250 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Oct 28, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Sep 18, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle B (premises is in Community District 7) | Active |
| Feb 22, 2024 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| Feb 22, 2024 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| Dec 1, 2023 | Energy Grade - LL33 FTP-EN-EGRDEA | Active |
| Dec 1, 2023 | Energy Grade - LL33 FTP-EN-EGRDEA | Active |
| Nov 2, 2023 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| Nov 2, 2023 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| Aug 2, 2023 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| Aug 2, 2023 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| May 2, 2023 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| May 2, 2023 | Benchmarking - LL84 FTF-EN-BENCH | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 28, 2026 | DOB Safety | AEUHAZ: | Open |
| Oct 24, 2026 | ECB | Construction: ATOI, I OBSERVED THAT WORK WAS CONTINUED WHILE SWO #4A52660 EXISTS HERE SINCE 09/24/26 - INDICATING NO OTHER EXTERIOR WORK ALLOWED AT EXP #3. I OBSERVED WORKERS WERE ON 7-8FL SCAFFOLD ON EXP #3, PERFORMING EXTE | Open |
| Oct 24, 2026 | ECB | Construction: OBSERVED SATURDAY 10/24/26 AFTER-HOUR VARIANCE PERMIT OBTAINED, BUT FORBADE ANY SCAFFOLD USE, EXTERIOR WORK OR WORK ABOVE 75FT. OBSERVED EXP #3 REAR YARD, WORKERS WERE ON 7-8 FLOOR SUPPORTED SCAFFOLD PERFORMING | Open |
| Oct 24, 2026 | ECB | Construction: ATOI, OBSERVED WORKERS IN THE LOBBY. CALLED OUT BUT ACCESS FOR INSPECTION WAS DENIED. WORKERS THEN WENT ON 8FL SCAFFOLD ON EXP #3 AND STARTED WORKING. INSPECTION DENIED PUT SAFETY STANDARDS AT RISK FOR EVERYONE | Open |
| Sep 27, 2026 | ECB | Unknown: MISCELLANEOUS VIOLATIONS.BC 3303.3 ATOI OF 8 STORY BUILDING AT ROOF LEVEL APPROX.27,653 SQ FT SITE CLOSED AND THERE WERE NO CONSTRUCTION ACTIVITY.UPON SHOUTING AT PERIMETER AND BANGING ON FENCE AND DOOR TO ALER | Open |
| Sep 24, 2026 | ECB | Unknown: BC3314.1 SUPPORTED SCAFFOLD.@8STORY NB SITE OBSERVE UNSAFE SUPPORTED SCAFFOLD UP TO ROOF LEVEL@ALL EXPOSURES CREATING FAILURE/DISLODGEMENT HAZARDS AFFECTING HEALTH&LIFE SAFETY:NOT MAINTAINED&MISSING DEBRIS NET+ | Open |
| Sep 24, 2026 | ECB | Unknown: @8STORY NB SITE IN EXTERIOR PHASE W/UNSAFE SUPPORTED SCAFFOLD UP TO ROOF LEVEL TOWERING OVER ADJOIN PROPERTY 42-08 UNION STREET WITH NO PROTECTION OF ROOF IN PLACE TO CODE BC3309.10 NOR ENGINEERED ENCLOSURE SYS | Open |
| Jul 28, 2026 | ECB | Unknown: BC 3314.1 AT TIME OF INSPECTION OBSERVED WORKER AT ROOF LEVEL WORKING ON A SUPPORTED SCAFFOLD NOT IN THE STATE OF READINESS, NO TOEBOARDS, NO PLANKS TIED DOWN OR GUARDRAIL SYSTEM AS REQUIRED IN 3314.5, 3314.5.5 | Closed |
| Jul 28, 2026 | ECB | Construction: OBSERVED VEHICLE EXITING THE SITE AT VEHICULAR ACCESS POINT NOT CLEARLY MARKED WITH HI VISIBILITY OR ADDITIONAL SUPPORT AT VERTICAL MEMBERS CREATING HAZARDOUS CONDITIONS TO THE STRUCTURAL STABILITY OF THE SHED | Closed |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 18, 2026, 2:49 PM ET. BBL 4051800038.