4 floors · 3 apartments · 4,320 sq ft · built 2001 · class C0 · owner of record: Kin Sheng Zhao As Trustee
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 56 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 56 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 72 days | Annual |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 300 days | Registered through 2027-09-01 |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 7 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1152 days | Next cycle year 2029 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 18, 2002 | Construction Non-Hazardous LOT LIN EWINDOWS ARE IMPROPERLY USED TO SUPPLY REQUIRED VENTILATION. REMEDY: PROVIDE PROPER VENTILATION. #34338843H | Feb 12, 2003 WRITTEN OFF | $0 |
| Jul 18, 2002 | Construction Non-Hazardous STAIR ENCLOSURE DOES NOT MEET THE REQUIRED TWO HOUR RATING DUE TO MISSING PIECE OF DRYWALL AT STAIR SIDE OF ENCLOSING WALL IN THE VICINITY OF THE STAIR PLAFORM REMEDY: PROVIDE 2 HR FIRE RATE DRYWALL. #34333533J | Feb 12, 2003 WRITTEN OFF | $0 |
| Jul 18, 2002 | Construction Non-Hazardous CELLAR STAIR IS NOT ENCLOSED BECAUSE THERE IS NO FIRE PROOF SELFT CLOSING DOOR AND RATED WALL AT TOP OF STAIRS. REMEDY: PROVIDE RATED ENCLOSED AND SELF CLOSING FIRE PROOF DOOR AT TOP OF STAIRS. #34340879M | Feb 12, 2003 WRITTEN OFF | $0 |
| Jul 18, 2002 | Construction Non-Hazardous GUARD RAILS ARE NOT PROVIDED AT SECTIONS OF BRICK PARAPET THAT ARE LESS THAN 3F 6" REMEDY - PROVIDE GUARD RAILS AT PARAPET LEVEL AT ROOF #34338580P | Feb 12, 2003 WRITTEN OFF | $0 |
| Jul 18, 2002 | Construction Non-Hazardous EXTERIOR GAS SERVICE'S NOT PROPERLY PROTECTED BY BOOARDS VEHICULAR TRAFFIC AT 1ST FLOOR PARKING AREA. REMEDY - PROVIDE ADDITIONAL PROTECTIONAROPUND GAS SERVICES #34338581R | Feb 12, 2003 WRITTEN OFF | $0 |
| Jul 18, 2002 | Construction Non-Hazardous BOILER FLUE NOT CARRIED 3 FEET ABOVE HIGHEST CONSTRUCTION ( PARAPET WALL ) REMEDY - RAISE FLUE PIPE 3 FEET ABOVE HIGHEST CONSTRUCTION #34338679P | Feb 12, 2003 WRITTEN OFF | $0 |
| Jul 18, 2002 | Construction Non-Hazardous APARTMENT DOOR OPENS DIRECTLY TO STAIR ENCLOSURE WHICH IS NOT PERMITTED IN A BUILDING OVER THREE STORIES. REMEDY: COMPLY WITH CODE. #34333526L | Feb 12, 2003 WRITTEN OFF | $0 |
| Jul 18, 2002 | Construction Non-Hazardous WORK CONTRARY TO PLANS IN THAT GARAGE DIMENSIONS SMALLER THAN SPECIFIED (2) ROOF DECKING CONSTRUCTED OF PLYWOOD INSTEAD OF METAL & CONCRETE (3) REAL LOT RETAINING WALL NOT SHOWN ON PLANS (4) CURB CUT IS 55 FEET #34338801J | Feb 12, 2003 WRITTEN OFF | $0 |
| Jul 18, 2002 | Construction Non-Hazardous XLASTIC SKYLIGHTS AT TOP OF STAIR ENCLOSURE ARE NOT PERMITTED SKYLIGHTS ARE NOT VENTED AND NO PROPER WIRE GRATING PROVIDED ABOVE AND BELOW SKYLIGHT. REMEDY: PROVIDE PROPER SKYLIGHT AND GRATING. #34338821R | Feb 12, 2003 WRITTEN OFF | $0 |
| Jul 18, 2002 | Construction Non-Hazardous FAILURE TO PROVIDE ACCESS TO ROOF VIA INTERIO R STAIR NO ROOF BULK HAEAD PROVIDED FOR 4 FAMILY DWELLING. REMEDY: PROVIDED REQUIRED ACCESS TOROOF. #34338832M | Feb 12, 2003 WRITTEN OFF | $0 |
| Jun 10, 2002 | Construction Non-Hazardous 1-HOUR RATED BOILER ENCLOSURE (WALL) IS PENETRATED BY AN UNRATED 10" DIAMETER METAL BOILER FLUE COMPROMISING INTEGRITY OF ONE HOUR RATED WALL REMEDY - PROVIDE 1HOUR FIRE PROTECTION AROUND BOILER FLUE #34338689Z | Feb 12, 2003 WRITTEN OFF | $0 |
| Jun 7, 2002 | Construction Non-Hazardous FAILURE TO PROVIDE REQUIRED NUMBER OF PARKING SPACES IN AN R6 DISTRICT ENCLOSED ACCESSARY OFF STREET PARKING SPACE DOES NOT MEET MININUM DIMENSIANS OF 18.5 X 8. UNENCLOSED OFF STREET PARKING SPACES AT REAR ARE #34333540H | Feb 12, 2003 WRITTEN OFF | $0 |
| Jun 7, 2002 | Construction Non-Hazardous LOT LINE WINDOWS INSTALLED WITHOUT A PERMIT NOT SHOWN ON PLANS. REMEDY: OBTAIN A PERMIT OR REMOVE WINDOWS. #34340890N | Feb 12, 2003 WRITTEN OFF | $0 |
| Issued | Violation | Status |
|---|---|---|
| May 31, 2007 | SEU AS BUILT CONDITIONS NOT CONFORMING TO APPROVED PLANS AS FOLLOWS: WIND OWS, NO HC ACCESS OR LIFT, INDIVIDUAL GRATES, EXTERIOR GAS AND ELECTRI C METERS W/ BOLLARDS, 4"CMU FACADE, NO FIRE RATED STEEL BRICK SHELVES AND BALCONIES, PARAPET HEIGHTS, PAINTED PARKING DRIVEWAY, NO 30FT FDNY ACCESS, 60FT CURB #229073 | DOB VIOLATION - ACTIVE |
| Jul 18, 2002 | CONSTRUCTION #0707OC | DOB VIOLATION - ACTIVE |
| Jul 18, 2002 | CONSTRUCTION #07211OC | DOB VIOLATION - ACTIVE |
| Jul 18, 2002 | CONSTRUCTION #07215OC | DOB VIOLATION - ACTIVE |
| Jul 18, 2002 | CONSTRUCTION #07216OC | DOB VIOLATION - ACTIVE |
None open.
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 5, 2026, 9:06 PM ET. BBL 4049940226.