35 floors · 274,656 sq ft · built 1926 · class H1 · owner of record: Silver Autumn Htl Corp
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 42 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-03-04 (Pre-filing). Agency page | Dec 31, 2026 in 42 days | 2 of 2 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 274,656 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 163 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 163 days | Annual filing |
| Facade inspection report (Cycle 10B) Applies Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. DOB facade records for this building show $50,400 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2028 in 459 days | No Cycle 10 report on record yet |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 5 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1138 days | Next cycle year 2029 |
| Energy audit and retro-commissioning (2030) Likely applies Local Law 87 · Calendar year 2030 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 1270). Agency page | Dec 31, 2030 in 1503 days | Next due 2030 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Dec 18, 2025 | Construction CLASS - 2 AT THE TIME OF MY INSPECTION OBSERVED SIDEWALK SHED INSTALLED AT EXP#1 AND #2 -WITH HOTEL ADVERTISEMENT ON SHED PARAPET AT BOTH EXPOSURES(APPROX. 90% OF SWS PARAPET) AND AT EXP #2 BUS STOP SIGN OBSCURED WITH SH #39548049H | Jan 21, 2027 DEFAULT | $5,000 |
| Dec 4, 2025 | Unknown CLASS - 2 AT TIME OF INSPECTION, SWS PANELS WERE MISSING AT THE CORNER OF EXP 2, REMOVED FOR THE THANKSGIVING PARADE AND NOT REINSTALLED, FAILING TO MAINTAIN REQUIRED ENCLOSURE PER BC 3307.6.4.6. STOP ALL WORK WITHIN 20 #39547600X | Feb 12, 2026 IN VIOLATION | $0 |
| May 19, 2025 | Construction CLASS - 2 AT TIME OF INSPECTION OBSERVED ACTIVE SUSPENDED SCAFFOLDS. UPON REVIEWING MANUFACTURE SPECS FOR DELTA BEAMS AND SKYCLIMBER SPECS FOR PLATFORMS NOTICE IT DOES NOT CONFORM. BEAMS ARE USE WITH INNER CONNECTION TUB #39540389H | Jul 31, 2025 IN VIOLATION | $1,250 |
| Issued | Violation | Status |
|---|---|---|
| Aug 2, 2024 | FAILURE TO BENCHMARK FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 #00112 | DOB VIOLATION - ACTIVE |
| May 19, 2023 | HAZARDOUS CONDITION (FACADE) CYCLE 9B UNSAFE REPORT FILED #911136 | DOB VIOLATION - ACTIVE |
| Feb 24, 2000 | ELEVATOR 1P15303 #9013/117748 | DOB VIOLATION - ACTIVE |
| Feb 24, 2000 | ELEVATOR #90213117487 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Aug 2, 2024 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Report | Active |
| May 19, 2023 | Facades FISPHAZ CYCLE 9B UNSAFE REPORT FILED | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 19, 2026, 2:39 PM ET. BBL 1012700001.