1 floors · 100,000 sq ft · built 1962 · class E1 · owner of record: Terreno Morgan Ave, Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 63 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2019-07-16 (Accepted). Agency page | Dec 31, 2026 in 63 days | 1 of 1 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 100,000 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 184 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 184 days | Annual filing |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 1 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 794 days | Next cycle year 2028 |
| Energy audit and retro-commissioning (2034) Likely applies Local Law 87 · Calendar year 2034 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 2974). Agency page | Dec 31, 2034 in 2985 days | Next due 2034 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Nov 30, 2025 | Construction CLASS - 1 AT TIME OF INSPECTION, OBSERVED VERTICAL AND HORIZONTAL CRACKS AT MULTIPLE LOCATION OF INTERIOR (CITI BIKE WAREHOUSE) OF EXP.3 (REAR INTERIOR WALL) AND EXP.4 (RIGHT SIDE INTERIOR WALL)., REPAIR AND/REPLACE #39168673R | Mar 16, 2026 IN VIOLATION | $2,500 |
| Jul 1, 2025 | Boilers CLASS - 2 FAILURE TO FILE REQUIRED ANNUAL BOILER INSPECTION REPORTS FOR LOW-PRESSURE BOILER 30000079277N0001 IN ACCORDANCE WITH THE RULES OF THE DEPARTMENT.1RCNY 103-01(D)(1)REQUIRES THAT AN ANNUAL INSPECTION REPORT FOR #37035723Y | Dec 22, 2025 IN VIOLATION | $625 |
| Aug 18, 2007 | Boilers Hazardous B4B/50A/36/BQ9/.50A-NO BOILER ROOM ENCLOSURE.50B-NO WORK PERMIT FILED W/DOB FOR THE BOILER. #32052255P | Dec 18, 2007 IN VIOLATION | $0 |
| Aug 18, 2007 | Boilers Non-Hazardous B4B/34A/34B/38/50A/50B/50C/50D/36/.50A-BOILER ROOM NOT A STORAGE ROOM.50B-EXPOSED WOOD BEAMS IN BOILER ROOM.50C-SEALED AROUND FLUE PIPE TO BOILER ROOM CEILING.50D-NO WORK PERMIT FILED W/DOB FOR THE BOILER. #32052258K | Dec 10, 2007 IN VIOLATION | $0 |
| Aug 18, 2007 | Boilers Hazardous B4B/34A/34B/38/50A/50B/50C/36/BQ9/50D/.50A-BOILER ROOM NOT A STORAGE ROOM.50B-EXPOSED WOOD BEAMS IN BOILER ROOM.50C-SEALED AROUND FLUE PIPE TO BOILER ROOM CEILING.50D-NO WORK PERMIT FILED W/DOB FOR THE GAS FIRE #32052254N | Dec 1, 2008 DEFAULT | $0 |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #11093 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL LOW PRESSURE INSPECTION #10020 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #19323 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #39698 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #21126 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION #13817 | DOB VIOLATION - ACTIVE |
| Aug 16, 1996 | CONSTRUCTION #01MJ01 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Sep 23, 2024 | Boiler LBLVIO Violation Issued-Failure To File 2023 External Low Pressure Inspection Report | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 29, 2026, 8:55 AM ET. BBL 3029740001.