5 apartments · 5,633 sq ft · built 2021 · class S5 · owner of record: City Real Estate Group Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 44 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 44 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 60 days | Annual |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | No current registration found |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 10 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 775 days | Next cycle year 2028 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Feb 1, 2022 | Construction CLASS - 2 PEDESTRIAN PROTECTION DOES NOT MEET CODE SPECIFICATION-SIDEWALK SHED. NOTE:AT THE TIME OF INSPECTION OF A NEW BLDG JOB SITE W/NO WORK IN PROGRESS.SIDEWALK SHED IS IN PLACED AT EXP.#1 W/VALID PERMIT BUT DECKING #35638965R | May 24, 2022 DEFAULT | $10,000 |
| Jan 18, 2022 | Construction CLASS - 2 EXTERIOR WALLS ON EXPOSURES 2 AND 4 FROM 1ST. TO 2ND. FLOOR WERE INSTALLED WITH 1" OR 3/4" OUTBOARD RIGID INSULATION CONTRARY TO 2" CONTINUOUS INSULATION INDICATED ON ENERGY ANALYSIS AND EXTERIOR WALLS DETAILS #39054433M | Mar 8, 2022 DEFAULT | $6,250 |
| Nov 16, 2021 | Construction CLASS - 2 PEDESTRIAN PROTECTION DOES NOT MEET CODE SPECIFICATIONS DECKING OF SIDWALK SHED NOT EXTENDED FULL WIDTH OF SIDEWALK.NOTE:AT THE TIME OF INSPECTION OF A NEW BUILDING JOBSITE WITH NO WORK IN PROGRESS.BUILDING IS #35505905X | Feb 15, 2022 DEFAULT | $10,000 |
| Sep 9, 2021 | Construction CLASS - 2 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROVED AMENDMENTS.AT TIME OF INSPECTION OBSERVED C-JOIST HAD BEEN CUTTED AND BLOCKING BUILDING INSTEAD OF SOLID WHICH HAS BEEN PERFORATED.STOP A #35574474M | Dec 7, 2021 DEFAULT | $6,250 |
| Mar 9, 2021 | Construction CLASS - 2 TEMP CONST EQUIPMENT ONSITE-EXPIRED PERMIT(SIDEWALK SHED) @TIME OF MY INSP ON ACTIVE JOBSITE,I OBSERVED SWS INSTALLED@EXP1 UNDER PERMITQ00456928-I1-SH RELATED TO NB4200665426.AFTER RESEARCHING SWS PERMIT ON DOB #35550612P | Jun 1, 2021 IN VIOLATION | $625 |
| Mar 9, 2021 | Construction CLASS - 1 UNLAWFULLY CONT'D WORK WHILE ON NOTICE OF STOPWORK ORDER.@TIME OF MY INSP ON ACTIVE JOBSITE,I OBSERVED WORKERS ENGAGED IN LAYOUT OF COLDFORMED STEEL(CJOIST) FOR 2FL LEVEL@EXP2 WHERE THERE WAS SWO ISSUED3/3/21 B #35550606Z | Jun 7, 2022 IN VIOLATION | $5,000 |
| Mar 9, 2021 | Site Safety CLASS - 1 FAILURE TO MAINTAIN/DISPLAY ONSITE DOCS REQUIRED BY BCCH33 @TIME OF MYINSP ON ACTIVE&PERMITTED JOBSITE,I OBSERVED WORKERS ENGAGED IN CONST ACTIVITY ON SITE.SIDEWALK SHED WAS ALSO OBSERVED@EXP1.UPON REQUEST FOR #35550608M | Jun 7, 2022 IN VIOLATION | $1,250 |
| Mar 9, 2021 | Construction CLASS - 1 1704.1 FAILURE TO FILE SPECIAL INSP STATEMENT OR RESPONSIBILITY PRIOR TO PERMIT ISSUANCE&PRIOR TO WORK UNDER SPECIAL INSP REQUIREMENTS SPECIAL INSP/STATEMENT OF RESPONSIBILITY TR-1 NOT FILED(COLDFORMED STEEL) @ #35550607K | Jun 7, 2022 IN VIOLATION | $2,500 |
| Mar 9, 2021 | Construction CLASS - 1 BC3309.10 PROTECTION OF ROOFS @TIME OF MY INSP ON ACTIVE&PERMITTED JOBSITE,I OBSERVED WORKERS ENGAGED IN CONST ACTIVITY ONSITE.ALSO OBSERVEDTHAT NO ROOF PROTECTION WAS PROVIDED TO ADJACENT PROPERTY@EXP4 AS SHOW #35550610L | Jun 7, 2022 IN VIOLATION | $625 |
| Mar 9, 2021 | Construction CLASS - 1 28-UNLICENSED ACTIVITY ILLEGALLY ENGAGING IN ANY BIZ OR OCCUPATION W/OREQUIRED LICENSE OR OTHER AUTHORIZATION(NO DOB ISSUED WELDERS LICENSE)@TIME OF MY INSP ON ACTIVE JOBSITE,I OBSERVED WORKERS ENGAGED IN CONST #35550609Y | Jun 1, 2021 IN VIOLATION | $5,000 |
| Mar 9, 2021 | Construction CLASS - 1 FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING PER SEC REQUIREMENTS.@TIME OF MY INSP ON ACTIVE JOBSITE,I OBSERVED PERMIT HOLDER FAILED TO MAINTAIN ADEQUATE HOUSEKEEPING ONSITE.MATERIAL&EQUIPMENT WAS SOON SCATTERED O #35550613R | Sep 7, 2021 IN VIOLATION | $625 |
| Mar 3, 2021 | Construction CLASS - 1 3309.1 PROTECTION FOR ADJACENT PROPERTY.AT THE TIME OF MY INSPECTION AT A 4 STORY BUILDING UNDER CONSTRUCTION,I OBSERVED MASONRY WORK IN PROGRESS AT EXPO 2 APPROX 15-20 FEET HEIGHT ALSO REBAR EXTENDING ON TOP O #35549821N | Sep 7, 2021 IN VIOLATION | $2,500 |
| Mar 3, 2021 | Construction CLASS - 2 SWS DOES NOT MEET CODE SPECIFICATIONS.AT THE TIME OF MY INSPECTION AT A 4 STORY BUILDING UNDER CONSTRUCTION I OBSERVED SWS IN PLACE AT EXPO 1 ALSO OBSERVED THE SWS HAS NOT EXTENDED 5 FEET ON EACH SITE FOR ADJAC #35549822P | Sep 7, 2021 IN VIOLATION | $625 |
| Mar 3, 2021 | Construction CLASS - 1 WORK DOES NOT CONFORM TO APPROVED PLANS/DRAWINGS.AT THE TIME OF MY INSPECTION AT A 4 STORY BUILDING UNDER CONSTRUCTION,I OBSERVED MASONRY WORK IN PROGRESS AND A UTILITY POST WAS BUILT INTO THE WALL.UPON REVIEW #35549820L | May 25, 2021 IN VIOLATION | $625 |
| Mar 3, 2021 | Site Safety CLASS - 1 DOCUMENT TO BE KEPT ONSITE-SWS DRAWINGS.AT THE TIME OF MY INSPECTION AT A 4 STORY BUILDING UNDER CONSTRUCTION I OBSERVED SWS IN PLACE AT EXP1.UPON REQUEST FOR APPROVED DRAWINGS NONE WAS PROVIDED.REMEDY:PROVIDE #35549823R | Sep 7, 2021 IN VIOLATION | $1,250 |
| Feb 21, 2009 | Construction CLASS - 2 EXPIRED PERMIT. FENCE PERMIT EXPIRED AT TIME OF INSPECTION. TWO STORY BLDG DEMOLISHED NO ONE ON SITE. DEBRIS REMOVED SITE GRADED ADJACENT BLDG WEATHERPROOF. A SEARCH OF DOB RECORDS SHOWS DEMOLITION PERMIT #402 #34758622P | May 25, 2010 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| May 12, 2021 | CONSTRUCTION FAILURE TO PROVIDE SUPPORT OF EXCAVATION #CE02GM03 | VIOLATION UNSERVED ECB-ACTIVE |
| May 12, 2021 | CONSTRUCTION NO EARTHWORK NOTIFICATION #CE02GM04 | VIOLATION UNSERVED ECB-ACTIVE |
| May 12, 2021 | CONSTRUCTION GUARDRAIL SYSTEM MISSING FROM SCAF #CE10NP01 | VIOLATION UNSERVED ECB-ACTIVE |
| May 12, 2021 | CONSTRUCTION PLATFORM FOR SUPPORT SCAF NOT FULLY PLANKED OR TIE DOWN #CE10NP02 | VIOLATION UNSERVED ECB-ACTIVE |
| May 12, 2021 | CONSTRUCTION FL/MAINT A RECORD OF ORIENTATION+ #CE10NP03 | VIOLATION UNSERVED ECB-ACTIVE |
| May 12, 2021 | CONSTRUCTION CONSTRUCTION SUPERINTENDENT FAIL TO PERFORM HIS DUTIES #CE10NP04 | VIOLATION UNSERVED ECB-ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 10) | Active |
None open.